7 Each security force will be associated with
a specific geographical polygon(s) which will be activated in the
DDP as a standing order.
8 The Secretariat will advise all SOLAS Contracting
Governments operating in the production environment of the LRIT system,
each time a security force is created in the DDP. In this respect,
an exclusion will be automatically added to all SOLAS Contracting
Governments with respect to the security force in question. SOLAS
Contracting Governments will then consider deactivating the above
exclusion or instructing their LRIT Data Centre (DC) to provide flag
State LRIT information, if they so wish, to the specified security
force created in the DDP.
9 Within the special geographical polygon, SOLAS
Contracting Governments might identify further critical areas within
which they might decide that ships entitled to fly their flag should
transmit flag State LRIT information at more frequent than the default
6-hour intervals in order to provide more accurate information to
the security forces. In such cases, the SOLAS Contracting Governments
concerned should instruct their DCs to transmit flag State LRIT information
accordingly. The distribution facility will receive whatever information
is sent to it by the flag States through the IDE and, as indicated
above, will not be able to initiate or reset any changes in the rate
of transmission of flag State LRIT information.