The annex below has been consolidated into The International Code on the Enhanced
Programme of Inspections during Surveys of Bulk Carriers and Oil Tankers, 2011 (2011 ESP
CODE)
Part A – Code on the Enhanced Programme of Inspections
during Surveys of Double-Hull Oil Tankers
23 Paragraph 1.3.3 is replaced by the following:
-
"1.3.3 Where the damage found on the structure mentioned in
paragraph 1.3.1 above is isolated and of a localized nature which does not affect
the ship's structural integrity (as for example a minor hole in a cross-deck
strip), consideration may be given by the surveyor to allow an appropriate
temporary repair to restore watertight or weathertight integrity after evaluation
of the surrounding structure and impose an associated condition or recommendation
with a specific time limit in order to complete the permanent repair and retain
the validity of the relevant statutory certification."
24 The text in paragraph 2.6.1 is replaced by the following
new text:
-
"2.6.1 The minimum requirements for ballast tank
pressure testing at the renewal survey are given in 2.6.3 and in annex
3.
-
The minimum requirements for cargo tank testing at the renewal
survey are given in 2.6.4 and annex 3.
-
Cargo tank testing carried out by the vessel's crew under
the direction of the master may be accepted by the surveyor provided
the following conditions are complied with:
-
.1 the tank testing procedure has been submitted
by the owner and reviewed by the Administration or recognized organization
prior to the testing being carried out;
-
.2 there is no record of leakage, distortion or
substantial corrosion that would affect the structural integrity of
the tank;
-
.3 the tank testing has been satisfactorily carried
out within special survey window not more than 3 months prior to the
date of the survey on which the overall or close up survey is completed;
-
.4 the satisfactory results of the testing is
recorded in the vessel's logbook; and
-
.5 the internal and external condition of the
tanks and associated structure are found satisfactory by the surveyor
at the time of the overall and close up survey."
25 The text in paragraph 5.3.2.3 is replaced by the
following:
26 The following new paragraph 5.5 is added after the
existing paragraph 5.4:
-
"5.5 Rescue and emergency response equipment
-
If breathing apparatus and/or other equipment is used as
"Rescue and emergency response equipment" then the equipment should
be suitable for the configuration of the space being surveyed."
27 The existing paragraphs 5.5 and 5.6 are renumbered,
respectively.
28 In the table of contents, a new reference to paragraph
"5.5 Rescue and emergency response equipment" is added after reference to paragraph 5.4
and the existing reference to paragraph numbers 5.5 and 5.6 are renumbered
accordingly.
29 In the renumbered paragraph 5.6.7, the referenced
paragraph numbers 5.5.5 and 5.5.6 are replaced by 5.6.5 and 5.6.6.
30 The following new paragraph 6.1.3 is added after the
existing paragraph 6.1.2:
-
"6.1.3 For oil tankers subject to SOLAS regulation II-1/3-10, the Owner
should arrange the updating of the Ship Construction File (SCF) throughout
the ship's life whenever a modification of the documentation included
in the SCF has taken place. Documented procedures for updating the
SCF should be included within the Safety Management System."
31 The existing text under paragraph 6.3 is numbered as
paragraph 6.3.1 and the following new paragraph 6.3.2 is added at the end of paragraph
6.3:
-
"6.3.2 For oil tankers subject to SOLAS regulation II-1/3-10, the Ship
Construction File (SCF), limited to the items to be retained on board,
should be available on board."
32 The existing text under paragraph 6.4 is numbered as
paragraph 6.4.1 and the following new paragraphs 6.4.2 and 6.4.3 are added at the end of
paragraph 6.4:
-
"6.4.2 For oil tankers subject to SOLAS regulation II-1/3-10, on completion
of the survey, the surveyor should verify that the update of the Ship
Construction File (SCF) has been done whenever a modification of the
documentation included in the SCF has taken place.
-
6.4.3 For oil tankers subject to SOLAS regulation II-1/3-10, on completion
of the survey, the surveyor should verify any addition and/or renewal
of materials used for the construction of the hull structure are documented
within the Ship Construction File list of materials."
Annex 9 - Condition evaluation report
33 The general particulars are replaced by the following:
-
"General particulars
-
Ship's name:
|
Administration/recognized organization identity number: Previous
Administration/recognized organization identity number(s): IMO
number:
|
- …"
34 Note 3 to table 2 (Transverse section modulus of hull girder) is replaced by
the following:
-
"3 This section applies to ships constructed before 1 July
2002: Section moduli of transverse sections of the ship's hull girder have been
calculated by using the thickness of structural members measured, renewed or
reinforced, as appropriate, during the SC renewal survey most recently conducted
after the ship reached 10 years of age in accordance with the provisions of
paragraph 2.2.1.2 of annex 12, and found to meet the criteria required by the
Administration or the recognized organization and that Zact is not less
than Zmc (defined in note 2 below) as specified in appendix 2 to annex
12, as shown in the following table.
- Describe the criteria for acceptance of the minimum section moduli of
the ship's hull girder for ships in service required by the Administration or the
recognized organization."
Annex 12 - Criteria for longitudinal strength of hull girder for oil tankers
35 Paragraph 2.2.1.2 is replaced by the following:
-
".2 for ships constructed before 1 July 2002, the actual section moduli
(Zact) of the transverse section of the ship's hull girder
calculated in accordance with the requirements of 2.1.2.2 should meet the criteria
for minimum section modulus for ships in service required by the Administration or
recognized organization, provided that in no case Zact should be less
than the diminution limit of the minimum section modulus (Zmc) as
specified in appendix 2."
Part B – Code on the Enhanced Programme of Inspections
during Surveys of Oil Tankers Other Than Double-Hull Oil Tankers
37 Paragraph 1.3.3 is replaced by the following:
-
"1.3.3 Where the damage found on the structure mentioned in
paragraph 1.3.1 above is isolated and of a localized nature which does not affect
the ship's structural integrity (as for example a minor hole in a cross-deck
strip), consideration may be given by the surveyor to allow an appropriate
temporary repair to restore watertight or weathertight integrity after evaluation
of the surrounding structure and impose an associated condition or recommendation
with a specific time limit in order to complete the permanent repair and retain
the validity of the relevant statutory certification."
38 The text in paragraph 2.6.1 is replaced by the following
new text:
-
"2.6.1 The minimum requirements for ballast tank
pressure testing at the renewal survey are given in 2.6.3 and in annex
3.
-
The minimum requirements for cargo tank testing at the renewal
survey are given in 2.6.4 and annex 3.
-
Cargo tank testing carried out by the vessel's crew under
the direction of the master may be accepted by the surveyor provided
the following conditions are complied with:
-
.1 the tank testing procedure has been submitted
by the owner and reviewed by the Administration or recognized organization
prior to the testing being carried out;
-
.2 there is no record of leakage, distortion or
substantial corrosion that would affect the structural integrity of
the tank;
-
.3 the tank testing has been satisfactorily carried
out within special survey window not more than 3 months prior to the
date of the survey on which the overall or close up survey is completed;
-
.4 the satisfactory results of the testing is
recorded in the vessel's logbook; and
-
.5 the internal and external condition of the
tanks and associated structure are found satisfactory by the surveyor
at the time of the overall and close up survey."
39 The text in paragraph 5.3.2.3 is replaced by the
following:
40 The following new paragraph 5.5 is added after the
existing paragraph 5.4:
-
"5.5 Rescue and emergency response equipment
-
If breathing apparatus and/or other equipment is used as
"Rescue and emergency response equipment" then the equipment should
be suitable for the configuration of the space being surveyed."
41 The existing paragraphs 5.5 and 5.6 are renumbered,
respectively.
42 In the table of contents, a new reference to paragraph
"5.5 Rescue and emergency response equipment" is added after reference to paragraph 5.4
and the existing reference to paragraph numbers 5.5 and 5.6 are renumbered
accordingly.
43 In the renumbered paragraph 5.6.7, the referenced
paragraph numbers 5.5.5 and 5.5.6 are replaced by 5.6.5 and 5.6.6.
Annex 9 - Condition evaluation report
44 The general particulars are replaced by the following:
-
"General particulars
-
Ship's name:
|
Administration/recognized organization identity number: Previous
Administration/recognized organization identity number(s): IMO
number:
|
- …"
34 Note 3 to table 2 (Transverse section modulus of hull girder) is replaced by
the following:
-
"3 This section applies to ships constructed before 1 July 2002: Section
moduli of transverse sections of the ship's hull girder have been calculated by
using the thickness of structural members measured, renewed or reinforced, as
appropriate, during the SC renewal survey most recently conducted after the ship
reached 10 years of age in accordance with the provisions of paragraph 2.2.1.2 of
annex 12, and found to meet the criteria required by the Administration or the
recognized organization and that Zact is not less than Zmc
(defined in note 2 below) as specified in appendix 2 to annex 12, as shown in the
following table.
- Describe the criteria for acceptance of the minimum section moduli of the ship's
hull girder for ships in service required by the Administration or the recognized
organization."
Annex 12 - Criteria for longitudinal strength of hull girder for oil tankers
35 Paragraph 2.2.1.2 is replaced by the following:
-
".2 for ships constructed before 1 July 2002, the actual section moduli
(Zact) of the transverse section of the ship's hull girder
calculated in accordance with the requirements of 2.1.2.2 should meet the criteria
for minimum section modulus for ships in service required by the Administration or
recognized organization, provided that in no case Zact should be less
than the diminution limit of the minimum section modulus (Zmc) as
specified in appendix 2."