8 Installation Survey and Commissioning Procedures Following Type Approval
Clasification Society 2024 - Version 9.40
Statutory Documents - IMO Publications and Documents - Resolutions - Marine Environment Protection Committee - Resolution MEPC.279(70) – 2016 Guidelines for Approval of Ballast Water Management Systems (G8) – (Adopted on 28 October 2016) - 8 Installation Survey and Commissioning Procedures Following Type Approval

8 Installation Survey and Commissioning Procedures Following Type Approval

8.1 The additional information outlined in the paragraphs below is intended to facilitate ship operations and inspections and assist ships and Administrations in preparing for the procedures set out in the Survey Guidelines for the purpose of the International Convention for the Control and Management of Ships' Ballast Water and Sediments under the Harmonized System of Survey and Certificationfootnote, developed by the Organization, which describe the examination of plans and designs and the various surveys required under regulation E-1 of the Convention.

8.2 The Administration issuing the International Ballast Water Management Certificate should verify that the following documentation is on board in a suitable format:
  • .1 for the purpose of information, a copy of the Type Approval Certificate of BWMS;

  • .2 the operation, maintenance and safety manual of the BWMS;

  • .3 the ballast water management plan of the ship;

  • .4 installation specifications, e.g. installation drawing, Piping and Instrumentation diagrams, etc.; and

  • .5 installation commissioning procedures.

8.3 Prior to issuance of the International Ballast Water Management Certificate, following the installation of a BWMS, the Administration should verify that:
  • .1 the BWMS installation has been carried out in accordance with the technical installation specification referred to in paragraph 8.2.4;

  • .2 the BWMS is in conformity with the relevant Type Approval Certificate of BWMS;

  • .3 the installation of the complete BWMS has been carried out in accordance with the manufacturer's equipment specification;

  • .4 any operational inlets and outlets are located in the positions indicated on the drawing of the pumping and piping arrangements;

  • .5 the workmanship of the installation is satisfactory and, in particular, that any bulkhead penetrations or penetrations of the ballast system piping are to the relevant approved standards; and

  • .6 the installation commissioning procedures have been completed.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.