4.2.1 The piping system for conveying the CBT
ballast shall be such that it can be flushed to a slop tank with water,
and shall be so arranged that oily water does not enter any dedicated
clean ballast tank when the piping system is flushed.
4.2.2 The piping system(s) of each dedicated clean
ballast tank must, not later than 1 July 1983, have at least two valves
that isolate that tank from the piping system(s) serving the cargo
tank.
4.2.3 The dedicated clean ballast tanks must be
connected to the least practicable number of cargo pumps.
4.2.4 The discharge of CBT ballast to the sea
is to be monitored by an oil content meter approved by the Administration
and sufficient sample points are to be provided in the discharge piping
of pumps serving dedicated clean ballast tanks to enable supervision
of the oil content in the ballast water being discharged.