6.1.2 On completion, tanks and reservoirs for service and storage of system fluids are to
be tested by a head of water equal to the maximum to which the tanks may be
subjected, but not less than 2,5 m above the crown of the tank.
6.1.3 After installation on board, piping systems together with associated fittings that
are under internal pressure, are to be subjected to a running test at the intended
maximum working pressure.
6.1.4 Testing is to cover the following items:
- Verification of control, alarm, and safety systems.
- Tests simulating failure of refrigeration equipment to
verify correct functioning of alarms and systems in service.
- Verification of accuracy, calibration and functioning of
temperature control for refrigeration systems.