| .1
|
IMO objectives:
|
Provide evidence as to whether and how the
proposal:
|
|
|
| .1 is within the scope of IMO's objectives;
and
|
|
|
| .2 is strictly related to the scope of the
Strategic Plan and contributes to the implementation of the
high-level actions established in the Plan.
|
|
|
| .2
|
(Compelling)
need:
|
Demonstrate and document:
|
|
|
| .1 the need for a proposed measure;
and
|
|
|
| .2 the compelling need addressed by a
proposal for a new convention or an amendment to an existing
convention.
|
|
|
| .3
|
Analysis of the
issue:
|
Provide an analysis of the proposed
measure, including a plausible demonstration of its practicability,
feasibility and proportionality.
|
|
|
| .4
|
Analysis of
implications:
|
Provide an analysis of the implications of
the proposal, addressing the cost to the maritime industry as well
as the relevant legislative and administrative burdens.footnote
|
|
|
| .5
|
Benefits:
|
Provide evidence that the benefits in terms
of enhanced maritime safety, maritime security or protection of the
marine environment expected to be derived from the inclusion of the
new item justify the proposed action.
|
|
|
| .6
|
Industry
standards:
|
Provide information on whether adequate
industry standards exist or are being developed.
|
|
|
| .7
|
Output:
|
Specify the intended output in SMART terms
(specific, measurable, achievable, realistic, time-bound). If a
final output cannot be specified, an interim output to be produced
before the end of the current biennium should be specified in SMART
terms.
|
|
|
| .8
|
Human element:
|
Provide the completed Checklist for
considering human element issues by IMO bodies (MSC-MEPC.7/Circ.1)
to demonstrate that the human element has been sufficiently
addressed.
|
|
|
| .9
|
Priority/urgency:
|
Provide, with reference to the current
Strategic Plan and High-level Action Plan:
|
|
|
| .1 evidence for the urgency of the proposed
unplanned output;
|
|
|
| .2 the date by which the proposed unplanned
output should be completed; and
|
|
|
| .3 the timescale needed for the respective
IMO organ to complete the work.
|
|
|
| .10
|
Action required:
|
Specify the action required of the IMO
organ.
|