4.1 Requirements to be complied with by the manufacturer
                     
                     
                     
                     
                     4.1.1 The manufacturing plant is to be provided with suitable equipment and
                        facilities to enable proper handling of the materials, manufacturing processes and
                        structural components. The manufacturing plant is to have at its disposal sufficiently
                        qualified personnel. The Society is to be advised of the names and areas of
                        responsibility of the supervisory and control personnel in charge of the project.
                     
                     
                     
                     
                     4.2 Quality control
                     
                     
                     
                     
                     4.2.1 As far as required and expedient, the manufacturer’s personnel has to
                        examine all structural components both during manufacture and on completion, to verify
                        that they are complete, that the dimensions are correct and that workmanship is
                        satisfactory and meets the standard of good shipbuilding practice.
                     
                     
                     
                     
                     Upon inspection and corrections by the manufacturing plant, the structural components are
                        to be shown to the surveyor of the Society for inspection, in suitable sections,
                        normally unpainted condition and enabling proper access for inspection. 
                     
                     
                     
                     
                     The Surveyor may reject components that have not been adequately checked by the plant and
                        may demand their re-submission upon successful completion of such checks and corrections
                        by the plant.