Appendix - Test Method for Fixed Water-Based Fire-Fighting Systems for Ro-Ro Spaces and Special Category Spaces
Clasification Society 2024 - Version 9.40
Statutory Documents - IMO Publications and Documents - Circulars - Maritime Safety Committee - MSC.1/Circular.1430/Rev.1 - Revised Guidelines for the Design and Approval of Fixed Water-Based Fire-Fighting Systems for Ro-Ro Spaces and Special Category Spaces – (7 December 2018) - Appendix - Test Method for Fixed Water-Based Fire-Fighting Systems for Ro-Ro Spaces and Special Category Spaces

Appendix - Test Method for Fixed Water-Based Fire-Fighting Systems for Ro-Ro Spaces and Special Category Spaces

1 SCOPE

1.1 This test method is intended for evaluating the effectiveness of fixed water-based fire-fighting systems installed in ro-ro spaces and special category spaces with deck heights up to and including 5 m and/or up to and including 2.5 m.

1.2 The test programme has two objectives:
  • .1 establishing nozzle location, nozzle characteristics, minimum water delivery rate and minimum water pressure for systems which will provide the required level of system response time, suppression and control; and

  • .2 establishing the minimum area of operation of the system for the purpose of determining hydraulic design requirements for wet pipe, dry pipe and preaction systems.

2 GENERAL REQUIREMENTS

2.1 Sampling

The nozzles and other components to be tested should be supplied by the manufacturer together with design and installation criteria, operational instructions, drawings and technical data sufficient for the identification of the components.

2.2 Tolerances

Unless otherwise stated, the following tolerances should apply:
  • .1 length: ± 2% of value;

  • .2 volume: ± 5% of value;

  • .3 pressure: ± 3% of value; and

  • .4 temperature: ± 2% of value.

2.3 Observations

The following observations should be made during and after each test:
  • .1 time of ignition;

  • .2 activation time of first nozzle;

  • .3 time when water flows out through first nozzle;

  • .4 time when water flow is shut off;

  • .5 time when the test is terminated; and

  • .6 total number of activated nozzles.

2.4 Test hall and environmental conditions

The test hall where the tests are conducted should have a minimum floor area of 300 m2 and a ceiling height in excess of 8 m. The test hall may be equipped with a forced ventilation system, or be natural ventilated, in order to ensure that there is no restriction in air supply to the test fires. The test hall should have an ambient temperature of between 10 and 25oC at the start of each test.

2.5 Measurement equipment

2.5.1 Temperatures should be measured using plain K-type thermocouple wires not exceeding 0.5 mm in diameter. The thermocouple head should be protected against direct water impingement, e.g. by tin cans.

2.5.2 System water pressure should be measured by using suitable equipment. Total water flow rate should be determined by a direct measurement or indirectly by using the pressure data and "k" factor of the nozzles.

2.5.3 The measurements should be made continuously throughout the tests.

2.6 System operational conditions

The tests should simulate the conditions of an actual installed system regarding objectives such as time delays between the activation of the system and minimum system water pressure or water delivery. In addition, the use of a pre-primed fire suppression enhancing additive, if applicable, should be taken into account.

3 DETERMINATION OF FIRE SUPPRESSION AND CONTROL CAPABILITIES

3.1 Principle

These test procedures test the effectiveness of a water-based fire-fighting system against two different scenarios: a cargo fire in a simulated freight truck, and a passenger vehicle fire.

3.2 Fire source

3.2.1 The primary fire source for both scenarios consists of EUR standard wood pallets (ISO 6780:2003), stored inside with the moisture content of 14 ± 2%. Figure 3.2.1 shows details of a EUR pallet.

3.2.2 Plywood panels made of pine or spruce are used as targets. The panels should be approximately 12 mm thick. The ignition time of the panel should not be more than 35 s and the flame spread time at 350 mm position should not be more than 100 s as measured in accordance with resolution A.653(16).

3.2.3 For ignition, commercial heptane should be applied.

Figure 3.2.1 - Typical dimensions of the standard EUR pallet

3.3 Apparatus

3.3.1 Test area

The tests should be conducted in a test hall as specified in paragraph 2.4 above, under a flat, smooth, non-combustible ceiling of at least 100 m2. There should be at least a 1 m space between the perimeters of the ceiling and any wall of the test hall.

3.3.2 Fire scenario 1: cargo fire in a simulated freight truck (see figures 3.3.2.1 to 3.3.2.3)

3.3.2.1 The primary fuel package consists of 112 wood pallets arranged in an array of 2 (wide) x 7 (high) x 8 (long) and raised up on a level of 2.8 m so that the top level of the fuel package is at 3.8 to 3.9 m above the floor.

3.3.2.2 The support frame for the wood pallet array of paragraph 3.3.2.1 should be constructed using open steel racks. The wood pallet piles should be standing freely on horizontal steel beams without any solid bottoms.

3.3.2.3 The fuel pallet array should be half-shielded by a 4.5 m long, 2.6 m wide steel plate (thickness at least 2 mm) at 4 m height. The plate should be properly fixed so that during a test it does not bend to provide an unobstructed passage of water onto the fuel package.

3.3.2.4 Plywood panel targets (acting also as obstructions) of dimensions 3.6 m (wide) x 2.4 m (high) should be arranged symmetrically on both sides of the fuel package at 1 m distance so that the top edge is at the same level as the top level of the wood pallet array.

3.3.2.5 The fire should be ignited by two steel trays centrally located under the fuel package as shown in figures 3.3.2.1 to 3.3.2.3. The square trays are 25 cm high and 0.1 m2 of free surface area. The trays should be filled with water and 1 l of heptane so that the free rim height above the liquid surface is 4 cm. The distance between the bottom of the wood pallet piles and liquid surface is 29 cm.

Figure 3.3.2.1 - Side view of the cargo fuel package in a simulated truck

Figure 3.3.2.2 - End view of the cargo fuel package in a simulated truck

Figure 3.3.2.3 - Top view of the cargo fuel package in a simulated truck

3.3.3 Fire scenario 2: passenger vehicle fire (see figures 3.3.3.1 and 3.3.3.2)

3.3.3.1 The primary fuel package consists of 12 wood pallets arranged in an array of 1 pallet (wide) x 6 pallets (high) x 2 pallets (long) constructed inside a passenger vehicle mock-up.

3.3.3.2 The passenger vehicle mock-up is constructed of nominally 2 mm steel.

3.3.3.3 Plywood panel targets (acting also as obstructions) of dimensions 1.2 m (wide) x 1.75 m (high) should be arranged symmetrically on both sides of the mock-up at 0.6 m distance so that the top edge is at the same level as the top level of the mock-up car.

3.3.3.4 The fire should be ignited by a steel tray centrally located under the fuel package as shown in figures 3.3.3.1 and 3.3.3.2. The square tray is 10 cm high and 0.1 m2 of free surface area. The tray should be filled with water and 1 l of heptane so that the free rim height above the liquid surface is 4 cm.

3.4 Nozzle positioning

Nozzles should be installed in an array at the ceiling level in accordance with the manufacturer's design and installation criteria. Tests should be repeated with three different relative locations between the nozzle array and the fuel package, i.e. centre of ignition under one nozzle, between two nozzles and between four nozzles, as shown in figure 3.4.

Figure 3.3.3.1 - Side view of the passenger vehicle fuel package

(The dashed lines visualize the shape of a car; the ceiling plate is to be fixed in its location as found most practical)

Figure 3.3.3.2 - Top view of the passenger vehicle fuel package

Figure 3.4 - Nozzle positioning in the two scenarios

3.5 Instrumentation

3.5.1 Instrumentation for the continuous measuring and recording of test conditions should be employed. At least the following measurements should be made:
  • .1 gas temperature at 7.5 cm below the ceiling at locations shown in figure 3.5.1;

  • .2 gas temperature at the targets to indicate ignition of targets as shown in figure 3.5.2; and

  • .3 system water pressure near the centre of the piping array.

3.5.2 System water flow rate should be defined with suitable means for the system.

Figure 3.5.1 - Thermocouple locations in the two scenariosfootnote

Figure 3.5.2 - Thermocouple locations at the plywood targets for determining ignition of targetsfootnote

3.6 Test programme and test procedure

3.6.1 Test programme

3.6.1.1 Tests should be conducted at the minimum system water pressure at the minimum distance between the lowest part of the nozzles and the ceiling, as specified by the manufacturer.

3.6.1.2 Three tests should be conducted at ceiling heights 5 m and/or 2.5 m, with different nozzle grid locations relative to the fuel package as specified in figure 3.4.1.

3.6.2 Test procedure

3.6.2.1 Prior to starting the test the moisture content of the fuel package should be measured at several locations along the full package with a probe-type moisture meter and the results should be reported.

3.6.2.2 The actual test procedure for all tests is as follows:
  • .1 the water pressure used at the start of the test should be set at the minimum value for the system specified by the manufacturer, flowing six open nozzles. If more than six nozzles operate during the test, the water supply pressure should be adjusted accordingly, to keep the required minimum system water pressure;

  • .2 the tray should be filled with 1 litre of heptane on the water base as described in paragraph 3.3.2.5 or 3.3.3.4;

  • .3 the measurements are started;

  • .4 the flammable liquid pool fire(s) should be lit by means of a torch or a match;

  • .5 the fire should be allowed to burn freely for a period of 2.5 min;footnote

  • .6 the test is continued for 30 min after system activation;

  • .7 any remaining fire should be manually extinguished; and

  • .8 the test is terminated.

3.7 Acceptance criteria

The principal acceptance criteria are based on the following factors:
  • .1 gas temperatures measured at locations not directly affected by impinging flames;

  • .2 damage to the fuel package; and/or

  • .3 ignition of targets.

    Note 1: Damage to the fuel package is defined by the fraction of charring of the full package. The damage to each individual wood pallet should be evaluated separately and the total fraction calculated based on the detailed results. Totally black, i.e. totally charred pallet is denoted as 100% damage of the pallet (even though the pallet may have maintained its shape) and totally intact pallet is denoted as 0% damage. Partially charred pallets should be visually evaluated. Proper and adequate photographs of the damaged fuel package should be included in the test report.

    Note 2: Ignition of targets is defined by the method described in figure 3.5.2, if the visibility during the test is such that it cannot be visually observed.

3.7.1 Fire scenario 1: cargo fire in a simulated freight truck (ceiling height 5 m)

The following four criteria should be met:

  • .1 after system activation the maximum five minute average at any of the three measurement locations at the exposed end of the fuel package should not exceed 300oC;

  • .2 after system activation the maximum five minute average at any of the three measurement locations at the concealed end of the fuel package should not exceed 350oC;

  • .3 total damage to the wood pallet array should not exceed 45% as defined after the test; and

  • .4 the plywood targets should not ignite during the test.

3.7.2 Fire scenario 2: passenger vehicle fire

The following two criteria should be met:
  • .1 after system activation the maximum five minute average at any of the four measurement locations should not exceed 350oC; and

  • .2 the plywood targets should not ignite during the test.

4 DETERMINATION OF AREA OF OPERATION

4.1 Both fire scenarios include hidden fires that burn intensely throughout the tests. The suppression tests as defined in paragraph 3.6.1 can be applied in establishing the area of operation of wet pipe, dry pipe and pre-action systems. The evaluation is based on the test with the largest number of nozzles activating.

4.2 The ceiling area of 100 m2 as defined in paragraph 3.3.1 most likely is not sufficient for defining the area of operation. The ceiling should be large enough to allow installation of a sufficient number of nozzles so that it is unambiguous that the nozzles activating truly represent the maximum number of active nozzles.

4.3 The area of operation is determined by multiplying the largest number of nozzles activating in the tests by two and defining the corresponding coverage area.

5 TEST REPORT

The test report should, as a minimum, include the following information:
  • .1 name and address of the test laboratory;

  • .2 date of issue and identification number of the test report;

  • .3 name and address of applicant;

  • .4 name and address of manufacturer or supplier of the nozzles;

  • .5 test method and purpose;

  • .6 nozzle identification;

  • .7 description of the tested nozzles and system performance;

  • .8 detailed description of the test set-up including drawings and photos of the fuel package and targets before and after the tests;

  • .9 date of tests;

  • .10 measured nozzle pressure and flow characteristics;

  • .11 identification of the test equipment and used instruments;

  • .12 test results including observations and measurements made during and after the test;

  • .13 deviations from the test method;

  • .14 conclusions; and

  • .15 date of the report and signature.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.