Clasification Society Rules and Regulations - Rules and Regulations for the Classification of Offshore Units, January 2016 - Part 1 REGULATIONS - Chapter 3 Periodical Survey Regulations - Section 13 Drilling plant facility |
||
![]() Section 13 Drilling plant facility13.1 Frequency of surveys13.1.1 Drilling units having a DRILL notation in accordance with Pt 3, Ch 7 Drilling Plant Facility are to be surveyed annually in accordance with the requirements of 2.7. A Special Survey in accordance with the requirements of Pt 1, Ch 3, 13.2 Scope of surveys is to be held at intervals not exceeding five years. 13.2 Scope of surveys13.2.1 At each Special Survey, the Surveyor is to examine and test as necessary the following components of the drilling plant facility:
13.2.2 Pressure vessels forming part of the drilling plant facility are to be examined in accordance with the requirements of Pt 1, Ch 3, 17 Pressure vessels for process and drilling plant, see also Pt 1, Ch 3, 2.5 Production and oil storage units and Pt 1, Ch 3, 2.7 Drilling units. 13.2.3 Piping systems for mud, cement and other systems subject to considerable erosion are to be examined for leaks and corrosion. 13.2.4 Safety and communication systems and hazardous areas are to be examined in accordance with Pt 1, Ch 3, 16 Safety and communication systems and hazardous areas. |
||
|
||
|