Construction stage
|
|
Inspection items
|
Primary surface preparation
|
1
|
The surface temperature of steel, the
relative humidity and the dew point shall be measured and recorded before the
blasting process starts and at times of sudden changes in weather.
|
|
2
|
The surface of steel plates shall be
tested for soluble salt and checked for oil, grease and other
contamination.
|
|
3
|
The cleanliness of the steel surface
shall be monitored in the shop-primer application process.
|
|
4
|
The shop-primer material shall be
confirmed to meet the requirements of 2.3 of table 1.
|
Thickness
|
|
If compatibility with the main coating
system has been declared, then the thickness and curing of the zinc silicate
shop primer to be confirmed to conform to the specified values.
|
Block assembly
|
1
|
After completing construction of the
block and before secondary surface preparation starts, a visual inspection for
steel surface treatment including edge treatment shall be carried out.
Any oil, grease or other visible contamination shall be
removed.
|
2
|
After blasting/grinding/cleaning and
prior to coating, a visual inspection of the prepared surface shall be carried
out. On completion of blasting and cleaning and prior to the
application of the first coat of the system, the steel surface shall be tested
for levels of remaining soluble salts in at least one location per
block.
|
3
|
The surface temperature, the relative
humidity and the dew point shall be monitored and recorded during the coating
application and curing.
|
4
|
Inspection
shall be performed of the steps in the coating application process mentioned in
table 1.
|
5
|
DFT
measurements shall be taken to prove that the coating has been applied to the
thickness as specified and outlined in annex
3.
|
Erection
|
1
|
Visual
inspection for steel surface condition, surface preparation and verification of
conformance to other requirements in table 1, and the agreed specification shall be
performed.
|
2
|
The surface
temperature, the relative humidity and the dew point shall be measured and
recorded before coating starts and regularly during the coating
process.
|
3
|
Inspection
shall be performed of the steps in the coating application process mentioned in
table 1.
|