LR IV.3 Required Information and Plans for Descriptive note FSRU Ready
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules and Regulations for the Construction and Classification of Ships for the Carriage of Liquefied Gases in Bulk, July 2022 - LR IV Information and Plans - LR IV.3 Required Information and Plans for Descriptive note FSRU Ready

LR IV.3 Required Information and Plans for Descriptive note FSRU Ready

  LR IV.3.1 The following plans and documentation are to be submitted for each FSRU Ready descriptive note with applicable associated characters:

  1. FSRU Ready (A)
    1. Design screening completed in accordance with LR's ShipRight Procedure for Risk Based Certification (RBC) requirements.
    2. Risk assessment to demonstrate the elimination or mitigation of risk from new, novel or alternative designs.
    3. Regasification system general arrangement. Plans showing the general arrangement of all areas where equipment, components and piping systems are located.
    4. Regasification system process flow diagram.
    5. Hazardous area plan.
    6. Other plans related to FSRU operation, as required by LR.
  2. FSRU Ready (S)
    1. Hull girder strength calculations.
    2. Local scantlings calculations.
    3. Strength and fatigue analyses for cargo tank and/or cargo hold structures.
    4. Sloshing analysis for supporting structures of membrane cargo containment system or independent type cargo tanks structures where necessary.
    5. Plans showing arrangement, materials and scantlings of on-deck and underdeck supporting structure of regasification plants and other major equipment.
    6. Strength and fatigue analyses of on-deck and underdeck supporting structure of regasification plants and other major equipment.
    7. Protection of hull structure against cryogenic leakage.
    8. Other plans related to FSRU operation, as required by LR.
  3. FSRU Ready (MOOR)
    1. Mooring arrangement.
    2. Mooring load analysis.
    3. Plans showing the supporting structures of mooring fittings.
    4. Strength analysis of mooring fitting and its supporting structure.
    5. Other plans related to FSRU operation, as required by LR.

Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.