The following plans and documentation are to be submitted for each FSRU
Ready descriptive note with applicable associated characters:
- FSRU Ready (A)
- Design screening completed in accordance with LR's
ShipRight Procedure for Risk Based Certification (RBC)
requirements.
- Risk assessment to demonstrate the elimination or
mitigation of risk from new, novel or alternative designs.
- Regasification system general arrangement. Plans
showing the general arrangement of all areas where equipment, components
and piping systems are located.
- Regasification system process flow diagram.
- Hazardous area plan.
- Other plans related to FSRU operation, as required
by LR.
- FSRU Ready (S)
- Hull girder strength calculations.
- Local scantlings calculations.
- Strength and fatigue analyses for cargo tank and/or
cargo hold structures.
- Sloshing analysis for supporting structures of
membrane cargo containment system or independent type cargo tanks
structures where necessary.
- Plans showing arrangement, materials and scantlings
of on-deck and underdeck supporting structure of regasification plants
and other major equipment.
- Strength and fatigue analyses of on-deck and
underdeck supporting structure of regasification plants and other major
equipment.
- Protection of hull structure against cryogenic
leakage.
- Other plans related to FSRU operation, as required
by LR.
- FSRU Ready (MOOR)
- Mooring arrangement.
- Mooring load analysis.
- Plans showing the supporting structures of mooring
fittings.
- Strength analysis of mooring fitting and its
supporting structure.
- Other plans related to FSRU operation, as required
by LR.