3.2.1.1 The tests should be performed in a room
having an ambient temperature of 10ºC to 25ºC at the start
of each test. Details of the test hall geometry, the ventilation conditions
and environmental conditions should be given in the fire test report.
3.2.1.2 The fire-extinguishing tests of the system
should be carried out using the following test compartments:
-
.1 Test compartment 1
-
The test should be performed in a 100 m2 room
with 5 m ceiling height and ventilation through a 2 m x 2 m door opening
according to figure 2. The engine mock-up should be designed according
to figures 1 and 3. The door opening to the test compartment may be
covered during the test at the same rate as the foam layer is building
up in the compartment to avoid foam leakage through the door opening.
-
.2 Test compartment 2
-
The test should be performed in a test compartment having
a volume greater than 1,200 m3, but not greater than 3,500
m3, and a ceiling height exceeding 7.5 m. The ventilation
of the test compartment should be achieved by a 2 m x 2 m door opening
at floor level (as in test compartment 1) combined with a maximum
20 m2 total ventilation area, distributed in the ceiling
and/or along the walls, just below the ceiling. The door opening to
the test compartment may be covered during the test at the same rate
as the foam layer is building up in the compartment to avoid foam
leakage through the door opening.
The fire test should be performed in a test apparatus consisting
of:
-
.1 a simulated enginefootnote of size (width x length x height) 1 m x
3 m x 3 m constructed of sheet steel with a nominal thickness of 5
mm. The simulated engine is fitted with two steel tubes of 0.3 m in
diameter and 3 m in length, which simulate exhaust manifolds and a
grating. At the top of the simulated engine a 3 m2 tray
is arranged (see figures 1 and 3); and
-
.2 a floor plate system of 4 m x 6 m and 0.5 m
in height surrounding the simulated engine with a tray (4 m2 in
area), underneath (see figure 1).
The fire test should be carried out using the following
fire scenarios:
-
.1 combination of the following fire programmes
(Test fuel: commercial fuel oil or light diesel oil):
-
.1 low-pressure spray on top of the simulated
engine centred with nozzle angled upward at a 45° angle to strike
a 12 mm to 15 mm diameter rod 1 m away; and
-
.2 fire in trays under (4 m2) and on
top (3 m2) of the simulated engine;
-
.2 high-pressure horizontal spray fire on top
of the simulated engine. (Test fuel: commercial fuel oil or light
diesel oil);
-
.3 low pressure concealed horizontal spray fire
on the side of the simulated engine with oil spray nozzle positioned
0.1 m in from the end of the simulated engine and 0.1 m2 tray
positioned 1.4 m in from the engine end at the inside of floor plate.
(Test fuel: commercial fuel oil or light diesel oil); and
-
.4 flowing fire 0.25 kg/s from top of mock-up
(see figure 3) (Test fuel: heptane).
|
|
|
|
Table 1 – Oil spray fire test parameters
|
|
|
Fire type
|
Low pressure
|
High pressure
|
|
|
Spray nozzle
|
Wide spray angle
(120° to 125°) full cone type
|
Standard angle (at
6 bar) full cone type
|
|
|
Nominal oil
pressure
|
8 bar
|
150 bar
|
|
|
Oil flow
|
0.16 ± 0.01
kg/s
|
0.050 ± 0.002
kg/s
|
|
|
Oil
temperature
|
20 ± 5°C
|
20 ± 5°C
|
|
|
Nominal heat
release rate
|
5.8 ± 0.6
MW
|
1.8 ± 0.2
MW
|
|
|
|
|
|
|
3.2.4
Foam generator installation
requirements for tests
3.2.4.1.1 Foam generators and foam delivery duct
outlets should not be installed above the simulated engine in such
a way that the foam flow directly hits the test fires. The generators
and foam delivery duct outlets should also not be located near the
door or ventilation openings.
3.2.4.1.2 The inlet foam solution supply pressure
to the foam generators should be maintained within the acceptable
range determined in appendix 3, throughout the tests.
3.2.4.1.3 The number and spacing of foam generators
and foam delivery duct outlets should be based on the manufacturer's
system design and installation manual.
3.2.4.1.4 The mounting arrangement and orientation
of the foam generators should be in accordance with the manufacturers'
instruction.
3.2.4.2
Inside air foam systems
3.2.4.2.1 Foam generators should be installed
inside the test room at the uppermost level of the space. The vertical
distance between the generators and test room ceiling and floor should
be recorded and reflected in the manufacturer's design manual.
3.2.4.3
Systems using outside air
3.2.4.3.1 For systems where the foam generators
will be located outside the protected space, the test generators should
be located outside the test room and arranged to supply foam through
ducts of equivalent size or diameter as the foam generator. The length
and configuration of the foam delivery ducts should be the maximum
length to be used on board as specified by the manufacturer, but in
no case less than 5 m vertically and 5 m horizontally. Foam delivery
duct outlets should be located near the ceiling, or if located on
a side wall, within 1 m of the ceiling. The locations of the foam
delivery duct outlets should be recorded and reflected in the manufacturer's
design manual.
3.2.4.3.2 For systems where the foam generators
will be located inside the protected space and supplied by fresh air
ducts, the test generators should be located on the manufacturer's
instructions.