1 Part 2 of the annex to Guidelines for approval
of Ballast Water Management Systems (G8) provides the test and performance
specifications required for the approval of such systems.
2 The tests carried out in compliance with the
above requirements for a specified Treatment Rated Capacity (TRC)
should be considered valid for type approval of a Ballast Water Management
System with a higher TRC that consists of multiple units
of that approved Ballast Water Management System, provided the
ultimate functioning and effectiveness of the system on board a ship
of the type and size for which the equipment will be certified will
not be adversely affected.
3 The manufacturer shall give evidence by using
mathematical modelling and/or calculations or by full scale shipboard
testing that the system and its performance regarding
D-2 standard will not be adversely affected and that only
the pipe work and flow partitioning are concerned.