LR IV.4 Additional Design Requirements for Descriptive note FSRU Ready
LR IV.4.1
FSRU Ready is assigned with extension of one or more of the following
associated characters shown in brackets, detailing aspects of design and
construction that are in accordance with these Rules in force on the date of
‘contract of construction’.
- A Approval in principle
- S Structural reinforcement
- MOOR Long term station-keeping capability of
mooring system
LR IV.4.2
For assignment of the characters A, S and MOOR, the design
appraisal is to be carried out in accordance with these Rules. Following aspects are
to be especially considered for intended regasification operation in the future.
- FSRU Ready (A)
- Risk assessment is to be carried out as required by
1.1.10 to 1.1.11 and LR 1.1-04 to LR 1.1-05 of these Rules.
- Proposed location, space and arrangement feasibility
for future regasification facility are to be examined for compliance
with applicable requirements of these Rules.
- FSRU Ready (S)
- The descriptive note is for FSRU operation at
sheltered nearshore environments with breakwater facilities or any other
topographical protection. It is assumed that FSRU can escape to a safe
location as planned when the environmental threshold for the
disconnection is exceeded. For FSRU operation mode at sheltered
nearshore environments, 50% of the design load values defined in these
Rules and associated ShipRight procedures for the ship operations in the
North Atlantic environment may be used for the design loads for the FSRU
mode. Otherwise, direct calculation of site-specific design load is to
be carried out in accordance with The Rules and Regulations for the
Classification of Offshore Units, July Pt 10, Ch 2, 3, Dynamic load
components.
- Hull girder longitudinal strength is to be in
accordance with the requirement of LR 3.13 of these Rules. The weight is
to include future items such as regasification plant, equipment and
piping systems, etc. Where the FSRU operational information such as
weight distribution of future facilities, site environmental condition,
berthing arrangement and operational profile are not known, design still
water bending moment and shear force envelope may be assumed the same as
LNG ship design values in sheltered water.
- Local scantlings are to be in accordance with the
requirements of LR 3.14 to LR 3.26 of these Rules. The supporting
structures of membrane cargo containment system and independent cargo
tanks structures are to be designed for increased design vapour pressure
proposed by designer. In general, increased design vapour pressure 0,07
MPa may be assumed for membrane LNG ships.
- Primary structures of cargo holds or cargo tanks are
to be verified with the requirements of relevant ShipRight Structural
Design Assessment (SDA) and ShipRight Fatigue Design Assessment (FDA)
procedures. If it is considered necessary, verification of structural
reinforcements is also to be carried out for the supporting structures
of regasification plant and major equipment, such as a suction drum. For
membrane LNG ships with conventional arrangement and scantlings,
separate Fatigue Design Assessment for the FSRU mode operation is not
required. and Structural Design Assessment may be waived provided that
the design loads for North Atlantic ship operation is dominant.
- Sloshing analysis is to be carried out for
unrestricted filling levels. For independent cargo tanks primarily
constructed of plane surfaces, critical structures such as tripping
brackets of horizontal stringers are to be examined for strength and
fatigue performance against sloshing loads.
- The descriptive note is for hull structure and
independent cargo tanks only. Requirements for membrane cargo
containment systems are not covered by FSRU Ready (S). If it is
requested that membrane cargo containment systems and associated
internal structure, equipment and pipework exposed to fluid motion such
as pump tower be considered, separate assessments are to be carried out
in accordance with 4.14.3 and LR 4.14-03 of these Rules and LR’s
Guidance on the operation of membrane LNG ships to reduce the risk
of damage due to sloshing.
- FSRU Ready (MOOR)
- Mooring arrangements are to comply with The Rules
and Regulations for the Classification of Offshore Units, Pt 3, Ch 10,
16 Long-term nearshore positional mooring system for jetty mooring
system or equivalent, where applicable.
- The Rules and Regulations for the Classification of
Offshore Units, Pt 3, Ch 10, 1 General to Pt 3, Ch 10, 15 Trials
are to be complied for the other types of mooring system.
- Fatigue assessment of mooring fitting and its
supporting structure can be an exception to the mooring system
assessment. Where the FSRU operational information is not known, the
limiting environmental parameters for the FSRU operation should be
proposed.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
![](LR-FooterLogo.png) |
|