Regulation E-1 - Surveys
1 Ships of 400 gross tonnage and above to which
this Convention applies, excluding floating platforms, FSUs and FPSOs,
shall be subject to surveys specified below:
-
.1 An initial survey before the ship is put in
service or before the Certificate required under regulation regulation
E-2 or E-3 is issued for the first time. This survey shall verify
that the ballast water management plan required by regulation
B-1 and any associated structure, equipment, systems, fitting,
arrangements and material or processes comply fully with the requirements of this
Convention. This survey shall confirm that a commissioning test has been conducted
to validate the installation of any ballast water management system by
demonstrating that its mechanical, physical, chemical and biological processes are
working properly, taking into account the guidelines developed by the
Organization.footnote
-
.2 A renewal survey at intervals specified by
the Administration, but not exceeding five years, except where regulation E-5.2, E-5.5, E-5.6, or E-5.7 is
applicable. This survey shall verify that the Ballast Water Management
plan required by regulation B-1 and
any associated structure, equipment, systems, fitting, arrangements
and material or processes comply fully with the applicable requirements
of this Convention.
-
.3 An intermediate survey within three months
before or after the second Anniversary date or within three months
before or after the third Anniversary date of the Certificate, which
shall take the place of one of the annual surveys specified in paragraph
1.4. The intermediate surveys shall ensure that the equipment, associated
systems and processes for Ballast Water Management fully comply with
the applicable requirements of this Annex and are in good working
order. Such intermediate surveys shall be endorsed on the Certificate
issued under regulation E-2 or E-3.
-
.4 An annual survey within three months before
or after each Anniversary date, including a general inspection of
the structure, any equipment, systems, fittings, arrangements and
material or processes associated with the Ballast Water Management
plan required by regulation B-1 to
ensure that they have been maintained in accordance with paragraph
9 and remain satisfactory for the service for which the ship is intended.
Such annual surveys shall be endorsed on the Certificate issued under regulation E-2 or E-3.
-
.5 An additional survey, either general or partial,
according to the circumstances, shall be made after a change, replacement, or
significant repair of the structure, equipment, systems, fittings, arrangements
and material necessary to achieve full compliance with this Convention. The survey
shall be such as to ensure that any such change, replacement or significant repair
has been effectively made, so that the ship complies with the requirements of this
Convention. When an additional survey is undertaken for the installation of any
ballast water management system, this survey shall confirm that a commissioning
test has been conducted to validate the installation of the system by
demonstrating that its mechanical, physical, chemical and biological processes are
working properly, taking into account the guidelines developed by the
Organization.footnote
2 The Administration shall establish appropriate
measures for ships that are not subject to the provisions of paragraph
1 in order to ensure that the applicable provisions of this Convention
are complied with.
3 Surveys of ships for the purpose of enforcement
of the provisions of this Convention shall be carried out by officers
of the Administration. The Administration may, however, entrust the
surveys either to surveyors nominated for the purpose or to organizations
recognized by it.
4 An Administration nominating surveyors or recognizing
organizations to conduct surveys, as described in paragraph 3 shall,
as a minimum, empower such nominated surveyors or recognized organizationsfootnote to:
-
.1 require a ship that they survey to comply with
the provisions of this Convention; and
-
.2 carry out surveys and inspections if requested
by the appropriate authorities of a port State that is a Party.
5 The Administration shall notify the Organization
of the specific responsibilities and conditions of the authority delegated
to the nominated surveyors or recognized organizations, for circulation
to Parties for the information of their officers.
6 When the Administration, a nominated surveyor,
or a recognized organization determines that the ship's Ballast Water
Management does not conform to the particulars of the Certificate
required under regulation E-2 or E-3 or is such that the ship is not fit
to proceed to sea without presenting a threat of harm to the environment,
human health, property or resources such surveyor or organization
shall immediately ensure that corrective action is taken to bring
the ship into compliance. A surveyor or organization shall be notified
immediately, and it shall ensure that the Certificate is not issued
or is withdrawn as appropriate. If the ship is in the port of another
Party, the appropriate authorities of the port State shall be notified
immediately. When an officer of the Administration, a nominated surveyor,
or a recognized organization has notified the appropriate authorities
of the port State, the Government of the port State concerned shall
give such officer, surveyor or organization any necessary assistance
to carry out their obligations under this regulation, including any
action described in Article 9.
7 Whenever an accident occurs to a ship or a defect
is discovered which substantially affects the ability of the ship
to conduct Ballast Water Management in accordance with this Convention,
the owner, operator or other person in charge of the ship shall report
at the earliest opportunity to the Administration, the recognized
organization or the nominated surveyor responsible for issuing the
relevant Certificate, who shall cause investigations to be initiated
to determine whether a survey as required by paragraph 1 is necessary.
If the ship is in a port of another Party, the owner, operator or
other person in charge shall also report immediately to the appropriate
authorities of the port State and the nominated surveyor or recognized
organization shall ascertain that such report has been made.
8 In every case, the Administration concerned
shall fully guarantee the completeness and efficiency of the survey
and shall undertake to ensure the necessary arrangements to satisfy
this obligation.
9 The condition of the ship and its equipment,
systems and processes shall be maintained to conform with the provisions
of this Convention to ensure that the ship in all respects will remain
fit to proceed to sea without presenting a threat of harm to the environment,
human health, property or resources.
10 After any survey of the ship under paragraph
1 has been completed, no change shall be made in the structure, any
equipment, fittings, arrangements or material associated with the
Ballast Water Management plan required by regulation
B-1 and covered by the survey without the sanction of the Administration,
except the direct replacement of such equipment or fittings.
|