9.7.1 A method should be devised to test the correct
functioning of all units and alarms and it may be necessary to simulate
certain conditions to carry out an effective testing programme.
9.7.2 Such a programme should include checking:
-
.1 all alarm and safety functions;
-
.2 the functioning of the flue gas isolating valves;
-
.3 the operation of all remotely or automatically
controlled valves;
-
.4 the functioning of the water seal and nonreturn
valve (with a backflow pressure test);
-
.5 the vibration level of the inert gas blowers;
-
.6 for leakages: in systems four years old or
more, deck lines should be examined for gas leakage;
-
.7 the interlocking of the soot blowers;
-
.8 oxygen measuring equipment, both portable and
fixed, for accuracy by means of both air and a suitable calibration
gas.