Section 16 Long-term nearshore positional mooring system
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules and Regulations for the Classification of Offshore Units, July 2022 - Part 3 Functional Unit Types and Special Features - Chapter 10 Positional Mooring Systems - Section 16 Long-term nearshore positional mooring system

Section 16 Long-term nearshore positional mooring system

16.1 General

16.1.1 The requirements of this Section shall apply to inshore/at-shore-moored units with station-keeping capabilities to remain at terminal facilities and are additional to those applicable in other Sections of the Rules. This shall cover units with permanent or semi-permanent mooring systems at terminal facilities such as floating power generation, LNG terminals with onshore regasification or a FSRU that regasifies cargo LNG and exports to a gas network onshore. Essentially, this Section does not apply to a ‘mooring system’ anchored to the sea bed.

16.1.2 The terminal mooring system is to provide restraining forces at terminal facilities in the long term, normally within the entire duration of service life of units which are not required to leave the berth during unfavourable weather conditions, unless it is planned to do so. This will suggest mooring systems at the following inshore/at-shore facilities (where units' offloading manifolds are often connected to a distribution facility onshore through marine loading arms or flexible hoses):
  • Jetty, which is a structure providing berths at some distance from the shore. A jetty may be connected to the shore by a causeway, or may be of the island type.
  • Quay, which is a berth structure backing on to the shore or reclaimed land.
  • Dolphin, which is an isolated structure or strongpoint to facilitate holding a unit in position at its berth; with bollards or hooks for securing the unit and for preventing it from moving away from a berth due to combined wave, wind and current action.

16.1.3 The jetty/pier layout and mooring equipment arrangement and specifications, in addition to the plans and data listed in Pt 3, Ch 10, 1.4 Plans and data submission, will be subject to review and approval. The information and plans are to be submitted in an agreed electronic format, to cover the design review and class approval of the long-term nearshore positional mooring system.

16.2 Environment condition

16.2.1 The extreme environmental conditions applicable to the location or operating areas are to be specified, together with all operating environmental limits. Detailed specialist environmental reports are to be submitted, with sufficient supporting information to demonstrate the validity of the limiting criteria. See Pt 3, Ch 10, 3 Environmental conditions for more details.

16.2.2 Wave headings of all the possible direction should be considered unless limited heading angles are defined in the specialist environmental report.

16.2.3 Sea bed bathymetry may vary considerably around the units in case they are moored near the shoreline. Such a change in bathymetry may affect waves and currents. The current load can be even higher in the under-keel clearance. This should be investigated in the environmental specialist report and considered for the analysis.

16.2.4 A tsunami can have significant effects on the units. The specialist environmental report should include the likelihood of a tsunami and its effect, if applicable.

16.2.5 The design environmental combinations for permanent inshore/at-shore-moored units at exposed location could follow Pt 3, Ch 10, 4.3 Design combinations of return periods of environmental parameters.

16.2.6 For permanent inshore/at-shore-moored units operating in protected waters such as harbours or inland lakes, or semi-permanent units where such units need not remain at shore in adverse weather conditions, the design environmental return periods could be less as agreed with LR and shall be considered as a design limitation of the units.

16.2.7 When a unit is disconnectable and is expected to operate near other structures, return period should be at least 10 years. This is applicable, for instance, to a FSRU operating near other structures operating at another jetty in the same harbour.

16.2.8 For semi-permanent units, disconnection procedures from terminal facilities such as marine loading arms or flexible hoses are to be included in the operation manual submitted for approval. The manual at the minimum should contain:

  • Environment parameter threshold to disconnect;
  • Actions at incremental environment towards threshold value to disconnect (e.g. actions at incremental wind speeds before disconnection).

16.3 Mooring layout

16.3.1 The optimum restraining force distribution in mooring layout at terminal facilities, either inshore or at-shore, is provided by combined breast and spring lines arrangement. Within the context of this sub-Section:

  • Breast lines are mooring lines orientated as perpendicular as possible to the longitudinal centreline of the units and as far aft and forward as possible.
  • Spring lines are mooring lines orientated as parallel as possible to the longitudinal centreline of the units.

16.3.2 A mooring layout plan is to be submitted for approval. The arrangement of such combined mooring lines shall be demonstrated to be capable of:

  • Maintaining excursion of units during offloading/cargo transfer operation within allowable operating envelope of gangways and access structures (if present), and marine loading arms or flexible hoses; as defined by terminal facilities administrator and/or manufacturer specifications.
  • Maintaining mooring load below working load limit of mooring line and its tail component, during operation. The working load limit is to follow Table 10.6.1 Minimum factors of safety for anchor lines for floating offshore installations at a fixed location. For fibre ropes, follow Pt 3, Ch 10, 9 Fibre ropes.
  • Maintaining restraining forces exerted to shipboard mooring fittings below their respective SWL capacities.

16.4 Design considerations

16.4.1 The terminal mooring system is to be designed by considering as applicable, requirements of Pt 3, Ch 10, 4 Design aspects, Pt 3, Ch 10, 5 Design analysis and Pt 3, Ch 10, 6 Anchor lines; this shall cover verification on strength adequacy and fatigue life of mooring components including applicable factors of safety and detailed design methodology. For further reference, see the ShipRight procedure for Long-Term Nearshore Positional Mooring System associated with this Section of the Rules.

16.4.2 The corrosion and wear should be considered for mooring system design.

16.4.3 For nearshore positional mooring system with novel features, the design considerations and methodology should be reviewed and agreed by LR.

16.4.4 The effect of passing vessel on nearshore positional mooring system should be considered and the loads induced by passing vessel shall be combined with relevant environmental conditions.

16.4.5 The effects of long period waves such as infragravity waves, that could force seiching especially in certain enclosed mooring terminal, as well as further impact of infragravity waves which may be free or bound to sea and swell waves, should be considered.

16.4.6 In the location where snow or ice can be accreting, the effect should be considered in the design and analysis.

16.4.7 Sea bed bathymetry may affect waves and currents in case the floating system is moored near the shoreline. Such an effect should be taken into account for the design.

16.4.8 UV degradation and high temperature for the mooring lines above the water can reduce the mooring strength and fatigue capacities especially on fibre ropes and should be considered during the design.

16.4.9 The above water components of the mooring system especially fibre ropes are vulnerable to fire and blast. This can particularly be an issue for jetty moored FLNG units with large topsides processing facilities where there may be jet fire scenarios which the mooring system should survive. This risk should be considered during the design for accidental and post-accidental fire and blast design conditions.

16.5 Mooring winches

16.5.1 The specifications and performance of mooring winch for terminal mooring system shall follow Pt 3, Ch 10, 11 Anchor winches and windlasses Design load cases for mooring winches are given in Table 10.11.1 Design load cases.

16.5.2 The associated maximum allowable stresses are to be based on the factors of safety given in Table 10.11.2 Load case factors of safety.

16.6 Mooring fittings and components

16.6.1 The design and specification of mooring components shall comply with Pt 3, Ch 10, 6 Anchor lines and Pt 3, Ch 10, 10 Fairleads, bending shoes and stoppers

16.6.2 The design and specification of mooring fittings shall ensure that mooring fittings and supporting structure to which they are attached do not suffer structural damage before the mooring line breaks.

16.6.3 The design and construction of mooring fittings and their supporting hull structure are to comply with Pt 4, Ch 6, 1.1 General 1.1.6.

16.7 Mooring terminal facilities

16.7.1 Safety aspects in designing mooring at terminal facilities should be put in place, including access by emergency services, escape routes from hazardous areas and the provision of fire-fighting equipment.

16.7.2 Although design aspects of mooring terminal facilities are excluded in this Section, LR shall consider recognised standards and/or guidelines which provide recommendations and initial design strategy to build, maintain and refurbish mooring terminals. Provided that the level of safety is agreed by LR, the followings publications could be adopted:

  • BS 6349-2:2019, “Maritime works, Part 2:Code of practice for the design of quay walls, jetties and dolphin”;
  • A number of related publications by working groups under Association for Waterborne Transport Infrastructures (PIANC), e.g. PIANC Report 153: “Recommendations for the Design and Assessment of Marine Oil and Petrochemical Terminals”, and PIANC Report 116: “Safety Aspects affecting the Berthing Operations of Tankers to Oil and Gas Terminals”;
  • OCIMF MEG4, 4th edition 2018, Section 9.5 pertinent to quick release hooks and bollards.

16.8 General guidelines on maintenance and inspection

16.8.1 A mooring system management plan is to be provided to record the lifecycles of mooring equipment (e.g. mooring fittings, fairleads, mooring lines, tails, pennants, joining shackles, etc.), including operating, maintenance and inspection instructions as recommended by the original equipment manufacturer. Publications from OCIMF (i.e. latest edition of Mooring Equipment Guidelines) can be adopted as agreed with LR.

The mooring system management plan is to be approved by LR and must be retained on board throughout the service life of the unit and be considered as live documents for recording any changes that have occurred to the mooring system since the unit was built or on the day the long-term near shore positional mooring system notation was given.

16.8.2 The format of the mooring system management plan shall contain, as a minimum, information covering the following:

  • Mooring system design philosophy;
  • Records of mooring system including historical data of upgrades or modifications to mooring equipment; and
  • Inspection, maintenance including record for related documents and certifications, and retirement strategy for mooring lines based on guidance from the original equipment manufacturer.

For chain, wire and other steel components, see Pt 3, Ch 20, 2 General guidelines on inspection of mooring system components. For fibre rope, the industry standard such as CI 2001-04: Fibre Rope Inspection and Retirement Criteria recognised by INTERTANKO can be adopted as applicable.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.