Close up survey requirements
|
All web frame rings, in all ballast
tanks (see note 1)
|
All web
frame rings, in a cargo wing tank (see note 1)
|
A minimum
of 30% of all web frame rings, in each rmaining cargo wing tank (see
notes 1 and 3)
|
All
transverse bulkheads, in all cargo and ballast tanks (see note 2)
|
A
minimum of 30% of the deck and bottom transverses, including adjacent
structural members, in each cargo centre tank (see note 3)
|
Additional complete transverse web frame rings or deck and bottom
transverse including adjacent structural members as considered necessary
by the surveyor
|
Notes:
|
1
Complete transverse web frame ring including adjacent structural
member.
|
2
Complete transverse bulkhead, including girder and stiffener systems and
adjacent members.
|
3 The
30% shall be rounded up to the next whole integer.
|