For bulk carriers constructed before 1 July 1999 being within
the application limits of regulation 4.3,
which have been constructed with an insufficient number of transverse
watertight bulkheads to satisfy that regulation, the Administration
may allow relaxation from the application of regulations
4.3 and 6 on condition that
they shall comply with the following requirements:
-
.1 for the foremost cargo hold, the inspections
prescribed for the annual survey in the enhanced programme of inspections
during surveys required by regulation
XI-1/2 shall be replaced by the inspections prescribed therein
for the intermediate survey of cargo holds;
-
.2 are provided with bilge well high water level
alarms in all cargo holds, or in cargo conveyor tunnels, as appropriate,
giving an audible and visual alarm on the navigation bridge, as approved
by the Administration or an organization recognized by it in accordance
with the provisions of regulation XI-1/1;
and
-
.3 are provided with detailed information on specific
cargo hold flooding scenarios. This information shall be accompanied
by detailed instructions on evacuation preparedness under the provisions
of section 8 of the International
Safety Management (ISM) Code and be used as the basis for crew training
and drills.