5.1 The conformance test should be conducted either
by a recognized ASP or by an authorized testing ASP.
5.2 Subject to the provisions of paragraphs 5.2.1
and 5.2.2, the conformance test should be conducted using a communication
system which provides coverage in all sea areas for which the ship
is certified to operate.
5.2.1 Subject to the provisions of paragraphs
5.2 and 5.2.2, the results of the conformance test are not in any
way prejudiced by the location or whereabouts of the ship when the
conformance test is conducted.
5.2.2 Notwithstanding the provisions of paragraph
5.2, for ships constructed before 31 December 2008 and certified to
operate in sea areas A1, A2, A3 and A4, the conformance test for sea
area A4 may be conducted separately taking into account the provisions
of regulation V/19-1.4.1.3.
5.3 For ships constructed on or after 31 December
2008, the conformance test should be:
-
.1 conducted after the completion of the initial
survey of the radio installation, provided such survey has indicated
that, as far as the radio installation is concerned, the ship meets
the related requirements for the issue of a radio related certificate;
and
-
.2 satisfactorily completed prior to the issue
of a certificate as a result of satisfactory completion of the related
initial survey.
5.4 For ships constructed before 31 December 2008,
the conformance test should be:
-
.1 conducted prior to the date on which a ship
would need to demonstrate compliance with the requirements of regulation V/19-1; and
-
.2 satisfactorily completed prior to the amendment
of the record of equipment to document compliance with the requirements
relating to Long-range identification and tracking system or prior
to the issue of a certificate, in case the ship in question is undergoing
a related renewal survey.
5.5 Administrations should establish, for ships
constructed before 31 December 2008, dates, ahead of the dates stipulated
in regulation V/19-1.4.1 for
the phased in implementation of the requirement to transmit LRIT information,
by which the conformance testing should be carried out with a view
to ensuring the timely compliance of the ships entitled to fly their
flag with the requirements of regulation
V/19-1.
5.6 Notwithstanding the provisions of regulation V/19-1.4.1, ships the construction
of which has commenced before 31 December 2008 but has been, or is
to be, completed on or after 31 December 2008 should comply with the
obligation to transmit LRIT information before they are put into service.
For such ships the conformance test should be conducted and satisfactorily
completed as specified in paragraph 5.3.