3.4.1 Specification of the coating system applied
to the seawater ballast tanks and double-side skin spaces, record
of the shipyard’s and shipowner’s coating work, detailed
criteria for coating selection, job specifications, inspection, maintenance
and repairfootnote shall be documented in
the Coating Technical File (CTF), and the Coating Technical File shall
be reviewed by the Administration or an organization recognized by
the Administration.
3.4.2 New construction stage
The Coating Technical File shall contain at least the following
items relating to this Standard and shall be delivered by the shipyard
at new ship construction stage:
-
.1 copy of Statement of Compliance or Type Approval
Certificate;
-
.2 copy of Technical Data Sheet, including:
- product name and identification mark and/or number;
- materials, components and composition of the coating system,
colours;
- minimum and maximum dry film thickness;
- application methods, tools and/or machines;
- condition of surface to be coated (de-rusting grade, cleanness,
profile, etc.); and
- environmental limitations (temperature and humidity);
-
.3 shipyard work records of coating application,
including:
- applied actual space and area (in square metres) of each compartment;
- applied coating system;
- time of coating, thickness, number of layers, etc.;
- ambient condition during coating; and
- method of surface preparation;
-
.4 procedures for inspection and repair of coating
system during ship construction;
-
.5 coating log issued by the coating inspector
– stating that the coating was applied in accordance with the
specifications to the satisfaction of the coating supplier representative
and specifying deviations from the specifications (example of daily
log and non-conformity report, see annex 2);
-
.6 shipyard’s verified inspection report,
including:
- completion date of inspection;
- result of inspection;
- remarks (if given); and
- inspector signature; and
-
.7 procedures for in-service maintenance and repair
of coating systemfootnote.
3.4.3 Maintenance, repair and partial re-coating
Maintenance, repair and partial re-coating activities shall
be recorded in the Coating Technical File in accordance with the relevant
section of the Guidelines for coating maintenance and repairfootnote.
3.4.4 Re-coating
If full re-coating is carried out, the items specified in paragraph
3.4.2 shall be recorded in the Coating Technical File.
3.4.5 The Coating Technical File shall be kept
on board and maintained throughout the life of the ship.