9.1.1 Companies, with a view to ensuring the timely
compliance of the ships they operate with the provisions of regulation V/19-1, should make the
necessary arrangements for the conduct of the conformance tests set
out in MSC.1/Circ.1257 well ahead
of the date on which the survey of the radio installation, which
determines the date on which the ship is required to comply with the
provisions of regulation V/19-1,
becomes due.
9.1.2 Such an approach would enable the
Companies to identify whether the shipborne equipment is capable
of transmitting LRIT information and if not to make the
necessary arrangements for the rectification of any hardware or
software deficiencies.
9.1.3 The conformance tests should be conducted
by the ASPs which the Administration has recognized within the framework
of the Revised performance standards and through which the ship
will be transmitting LRIT information to the LRIT Data Centre
identified by the Administration or the ASPs they have authorized
to carry out conformance tests.