4.9.1 During this phase the HazId performed in
the previous phase will be formally reviewed by the Administration
to ensure that:
-
.1 the HazId team was composed of qualified members;
-
.2 appropriate procedures for a HazId were followed;
and
-
.3 all hazards are identified.
4.9.2 The HazId will further increase the understanding
of the alternative and/or equivalency, and the list of requirements
will be revised based on the findings from the HazId.
4.9.3 The risk model and the results of the evaluation,
if considered in this phase, will be formally reviewed by the Administration.
If the evaluation criteria cannot be fulfilled even with the implementation
of risk control options, the approval process may be terminated at
this point or may be restarted with a modified design.
4.9.4 Any risk control measures that may have
been considered in the Preliminary design will be formally reviewed
by the Administration.