7.3.1 The requirements for testing should apply
to gas piping inside and outside the gas tanks. However, relaxation
from these requirements may be accepted for piping inside gas tanks
and open-ended piping.
7.3.2 Welding procedure tests should be required
for gas piping and should be similar to those required for gas tanks
in the IGC Code, paragraph 6.3.3.
Unless otherwise especially agreed with the Administration, the test
requirements should be in accordance with 7.3.3 below.
7.3.3 Test requirements
-
.1 Tensile tests: Generally, tensile strength
should not be less than the specified minimum tensile strength for
the appropriate parent materials. The Administration may also require
that the transverse weld tensile strength should not be less than
the specified tensile strength for the weld metal, where the weld
metal has a lower tensile strength than that of the parent metal.
In every case, the position of fracture should be reported for information.
-
.2 Bend tests: No fracture should be acceptable
after a 180° bend over a former of a diameter four times the thickness
of the test piece, unless otherwise specially required or agreed with
the Administration.
-
.3 Charpy V-notch impact tests: Charpy tests should
be conducted at the temperature prescribed for the base material being
joined. The results of the weld impact tests, minimum average energy
(E), should be no less than 27 J. The weld metal requirements
for sub-size specimens and singe energy values should be in accordance
with the IGC Code paragraph 6.1.4.
The results of fusion line and heat affected zone impact tests should
show a minimum average energy (E) in accordance with the transverse
or longitudinal requirements of the base material, whichever applicable,
and for sub-size specimens, the minimum average energy (E) should
be in accordance with the IGC Code, paragraph
6.1.4. If the material thickness does not permit machining
either full-sized or standard sub-size specimens, the testing procedure
and acceptance standards should be in accordance with recognized standards.
Impact testing is not required for piping with thickness less
than 6 mm.
7.3.4 In addition to normal controls before and
during the welding and to the visual inspection of the finished welds,
the following tests should be required:
-
.1 For butt welded joints for piping systems with
design temperatures lower than -10°C and with inside diameters
of more than 75 mm or wall thicknesses greater than 10 mm, 100% radiographic
testing should be required.
-
.2 When such butt welded joints of piping sections
are made by automatic welding processes in the pipe fabrication shop,
upon special approval, the extent of radiographic inspection may be
progressively reduced but in no case to less than 10% of the joints.
If defects are revealed the extent of examination should be increased
to 100% and shall include inspection of previously accepted welds.
This special approval should only be granted if well-documented quality
assurance procedures and records are available to enable the Administration
to assess the ability of the manufacturer to produce satisfactory
welds consistently.
-
.3 For other butt welded joints of pipes, spot
radiographic tests or other non-destructive tests should be carried
out at the discretion of the Administration depending upon service,
position and materials. In general, at least 10% of butt welded joints
of pipes should be radiographed.
Butt welded joints of high-pressure gas pipes and gas supply
pipes in ESD-protected machinery spaces should be subjected to 100%
radiographic testing.
The radiographs should be assessed
according to a recognized standardfootnote.
7.3.5 After assembly, all gas piping should be
subjected to a hydrostatic test to at least 1.5 times the design pressure.
However, when piping systems or parts of systems are completely manufactured
and equipped with all fittings, the hydrostatic test may be conducted
prior to installation aboard ship. Joints welded on board should be
hydrostatically tested to at least 1.5 times the design pressure.
Where water cannot be tolerated and the piping cannot be dried prior
to putting the system into service, proposals for alternative testing
fluids or testing methods should be submitted for approval.
7.3.6 After assembly on board, each gas piping
system should be subjected to a leak test using air, halides or other
suitable medium.
7.3.7 All gas piping systems including valves,
fittings and associated equipment for handling gas should be tested
under normal operating condition before set into normal operation.