Ballast water exchange at sea
Clasification Society 2024 - Version 9.40
Statutory Documents - IMO Publications and Documents - Circulars - Maritime Safety Committee - MSC/Circular.1021 – Design Suggestions for Ballast Water and Sediment Management Options in New Ships – (Adopted on 21 March 2002) - Annex - Design Suggestions for Ballast Water and Sediment Management Options in New Ships - 2 Considerations at the design phase of new ships - Ballast water exchange at sea

Ballast water exchange at sea

  2.10 Where Ballast Water Exchange at sea is the chosen method, the overall design strength and stability of the ship should be sufficient to permit its execution on all ballast voyages and in all except severe weather conditions. For the guidance of the master, the maximum sea state and swell conditions identified by the builder, if any, in which ballast water exchange can safely be carried out should be recorded in the Ballast Water Management Plan.

  2.11 The design of the ship should make it easy to achieve exchange at sea, by reducing the demands upon other crew resources. In particular it should endeavour to minimize:

  • .1 the number of operational steps;

  • .2 the time taken, and

  • .3 the number of partially loaded tanks and the duration of their partial loading, needed to complete a ballast water exchange sequence.

  2.12 The design of the ship should include consideration of the consequences of ballast water exchange at sea including: stability, hull girder strength, shear forces, resonance, sloshing, stemming, propeller immersion, limitations brought about by insufficient strength in various parts of the ship when the tanks are sequentially emptied and appropriate strengthening incorporated to allow this operation to be conducted safely.

  2.13 Where the sequential method of exchange is to be used, particular attention should be given to the ballast tank layout, total ballast capacity, individual tank configuration and hull girder strength. If the Plan requires simultaneously emptying and refilling closely matched diagonal tanks then consequential torsional stresses should be considered. Still water bending moments, shear forces and stability should remain at or within safe limits.

  2.14 Where the flow-through method of exchange is to be used adequate provision should be made to avoid the risk of over pressurization of ballast tanks or ballast piping. Enhancements in this regard may include the installation of additional air pipes, installation of tanker hatches (as an alternative to deck manholes), internal overflow pipes (to avoid water flowing over the deck) and interconnecting ballast trunks between tanks where applicable and possible.

  2.15 Where the dilution method of exchange is to be used adequate provision should be made for appropriate piping arrangements to facilitate the loading of ballast water and, simultaneously, the unloading of the ballast water at the same flow rate. The hydrodynamic performance of the ballast tank is crucial to ensure full water exchange and sediment scouring.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.