5.2.1 Two copies of the transport and stepping procedures with confirmation that the
                                 dressing and stepping was carried out under LR supervision is to be signed by the
                                 Surveyor and the Rigger. One copy is to be placed on board the vessel and the other
                                 submitted to LR.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              5.2.2 The dock tuning procedure, i.e. step by step tightening of stays and jacking up of
                                 the mast, may be carried out without supervision of the Surveyor.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              5.2.3 The initial pre-tension applied to the rig is to be measured and recorded for
                                 intermediate stages and the final state. These recorded values are to be included in
                                 the rig stepping report.