Shutdown procedures should be as follows:
-
.1 When all tank atmospheres have been checked
for an oxygen level of not more than 8% and the required in-tank pressure
has been obtained, shut the deck isolating/nonreturn valve.
-
.2 Open vent to atmosphere between the gas pressure
regulating valve and the deck isolating/nonreturn valve.
-
.3 Shut the gas pressure regulating valve.
-
.4 Shut down the inert gas blower.
-
.5 Close the blower suction and discharge valve.
Check that the drains are clear. Open the water washing system on
the blower while it is still rotating with the power supply of the
driving motor turned off, unless otherwise recommended by the manufacturer.
Shut down the water washing plant after a suitable period.
-
.6 Close the flue gas isolating valve and open
the air sealing system.
-
.7 Keep the full water supply on the scrubber
tower in accordance with the manufacturer's recommendation.
-
.8 Ensure that the water supply to the deck water
seal is running satisfactorily, that an adequate water seal is retained
and that the alarm arrangements for it are in order.