10.2.1 Details
                                 of the design and construction of the fuel gas burning equipment for
                                 steam boilers, oil and gas heater furnaces, reformers, etc. are to
                                 be in accordance with the Rules and Regulations for the Construction and Classification of Ships for the Carriage of Liquefied Gases in Bulk, July 2022, or with agreed codes and specifications normally used
                                 for similar plants in land installations, suitably modified and/or
                                 adapted for the marine environment. Ignition of the burners is to
                                 be by means of permanently installed igniters, or properly located
                                 and interlocked pilot burners and main burners arranged for sequential
                                 ignition.
                                 
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              10.2.2 Gas
                                 or gas/air mixtures having relative densities compared with that of
                                 air at the same temperature greater than one are not to be used as
                                 fuels for fired pressure vessels situated below deck. Proposals to
                                 burn such mixtures above deck will be specially considered in each
                                 case.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              10.2.3 Proposals
                                 for the furnace purging arrangements prior to ignition of the burners
                                 are to be submitted. Such arrangements are to ensure that any accidental
                                 leakage of product liquid or gas into the furnace, from a liquid or
                                 gas heating element, or from the accidental ingestion of flammable
                                 gases and/or vapours, does not result in hazardous conditions.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              10.2.4 Compartments
                                 containing fired pressure vessels, heaters, reformers, etc. for heating
                                 or processing hazardous substances are to be so arranged that the
                                 compartment in which the fired equipment is installed is maintained
                                 at a higher pressure than the combustion chamber of the equipment.
                                 For this purpose, induced draught fans or a closed stokehold system
                                 of forced draught may be employed. Alternatively, the fired equipment
                                 may be enclosed in a pressurised air casing.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              10.2.5 The
                                 fired equipment is to be suitably lagged. The clearance spaces between
                                 the fired equipment and any tanks containing oil are to be not less
                                 than 760 mm. The compartments in which the fired equipment is installed
                                 are to be provided with an efficient ventilating system.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              10.2.6 Smoke
                                 box and header box doors of fired equipment are to be well-fitting
                                 and shielded, and the uptake joints made gastight. Where it is proposed
                                 to install dampers in the uptake gas passages of fired equipment,
                                 the details are to be submitted. Dampers are to be provided with a
                                 suitable device whereby they may be securely locked in the fully open
                                 position.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              10.2.7 Each
                                 item of fired equipment is to have a separate uptake to the top of
                                 the stack casing. Where it is proposed to install process fired equipment
                                 with separately fixed furnaces converging into a convection section
                                 common to two or more furnaces and/or a secondary radiant section
                                 at the confluence of the fired furnace uptake to the convection section,
                                 the proposed arrangements, together with the details of the furnace
                                 purging and combustion controls, are to be submitted.