7.1.2 Before
a new installation (or any existing installation, which has been subject
to alteration or addition which may affect the performance characteristics
of the system) is put into service, sea trials are to be carried out
to the approved schedule and to the Surveyor's satisfaction, see
Pt 7, Ch 4, 1.3 Information and plans required to be submitted 1.3.5.(g).
7.1.3 The
suitability of the dynamic positioning system is to be demonstrated
during sea trials, observing the following:
-
Response of the
system to simulated failures of major items of control and mechanical
equipment, including loss of electrical power, verifying the findings
of the FMEA where required.
-
Response of the
system under a set of predetermined manoeuvres for changing:
-
Location of
area of operation.
-
Heading of
the ship.
-
Continuous operation
of the system over a period of four to six hours.
7.1.5 Records
and data regarding the performance capability of the dynamic positioning
system are to be maintained on board the ship and are to be made available
at the time of the Annual Survey, see
Pt 1, Ch 3, 2.2 Annual Surveys 2.2.27.