Section
1 General
1.1 Application
1.1.1 The
requirements of this Chapter apply to tankers equipped with bow/stern
loading arrangements to facilitate the transfer of cargo oil from
offshore loading terminals, such as loading platforms, loading buoys,
FPSOs and FSUs, and are additional to those applicable in other Parts
of the Rules. These requirements also apply to submerged turret loading
systems where applicable.
1.1.2 Requirements
additional to these Rules may be imposed by the National Authority
with whom the ship is registered and/or by the Administration within
whose territorial jurisdiction the ship is intended to operate.
1.1.3 The
materials used are to be suitable for the intended service conditions.
1.2 Class notations
1.2.1 Ships
complying with the requirements of this Chapter will be eligible to
have one of the following special features notations included in the
class notation:
-
Ships fitted with
a bow loading system, BLS.
-
Ships fitted with
a stern loading system, SLS.
-
Ships fitted with
submerged turret loading systems, TLS.
1.3 Surveys
1.4 Submission of plans and documentation
1.4.1 In addition
to the plans and information required by other relevant Sections of
the Rules, the plans and information detailed below are to be submitted:
-
Bow/stern
loading:
Detail drawing(s) showing:
- Cargo loading equipment.
- Manifold position and pipeline connections.
- Mooring equipment layout, including design loads and supporting
structure.
- Fire safety arrangements.
- Control station(s).
-
Systems
and arrangements:
General arrangement. Plans showing the general
arrangement of all areas where the piping systems are located, together
with ventilation arrangements and details of openings for any enclosed
spaces at the fore and/or aft part of the ship.
Diagrammatic arrangement. Plans indicating all
piping systems arrangements associated with loading systems between
cargo tank area and manifold. The plans are to include details of
means of isolation, manifold arrangement, means of draining, inerting,
cleaning and gas freeing of the cargo piping. Also details of manifold
drip tray arrangements with means of drainage, together with any stripping
line arrangements, are to be submitted. If the ship is to be installed
with a vapour emission control system, plans showing details of piping
arrangements are also to be submitted.
Piping system specification. Piping design information
which includes the materials specifications, design pressure, maximum
allowable transfer rate, corrosion allowance, and design ambient weather
conditions. Also the design forces and moments for which the presentation
manifold, together with the terminal flange and associated supporting
arrangements have been designed, are to be submitted.
Operating Manuals. Operating Manuals are to be
submitted for approval and provided on board. The Manuals are to include
the following information:
- Particulars of piping arrangements and control systems.
- Operating criteria.
- Procedures for connecting/disconnecting the cargo hose, isolation
arrangements, inerting, cleaning, gas freeing of the pipe line and
drainage of the drip tray.
- Procedures to be followed during cargo handling operations. These
are to include guidance on procedures to be followed in the event
of sudden closure of the terminal valve.
- Detailed communication sequence concerning pre-mooring, mooring,
pre-loading, loading and tanker departure phases.
Where the ship is fitted with dynamic positioning and/or a positional
mooring system(s), the information required by Pt 7, Ch 4, 1.3 Information and plans required to be submitted 1.3.7 and Pt 7, Ch 8, 1.5 Plans and data submission 1.5.6 is also to be submitted
as applicable.
-
Submerged
turret loading:
Detail drawing(s) showing:
- Arrangement of turret room, including receiving structure, locking
mechanism and traction winch equipment with associated supporting
structure and design loadings.
- Turret hatch and operating equipment, including hydraulic power
pack and control systems, and cargo loading equipment.
- Turret room fire safety arrangements.
- Turret room electrical installations.
- Piping arrangements for all systems associated with the turret
loading.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
![](LR-FooterLogo.png) |
|