9.1.1 Before
a new installation (or any alteration or addition to an existing installation)
is put into service, trials are to be carried out. These trials are
in addition to any acceptance tests which may have been carried out
at the manufacturers' works and are to be based on the approved test
schedules list as required by Pt 7, Ch 8, 1.5 Plans and data submission 1.5.4.(h).
9.1.2 The
suitability of the positional mooring and/or thruster-assisted positional
mooring system is to be demonstrated during sea trials, observing
the following:
-
Response of the
system to simulated failures of major items of control and mechanical
equipment, including loss of electrical power.
-
Response of the
system under a set of predetermined manoeuvres for changing:
-
Location of
area of operation.
-
Heading of
the ship.
-
Automatic thruster
control and line tension optimisation.
-
Monitoring and
consequence analyses.
-
Simulation of
line breakage and damping.
-
Continuous operation
of the thruster-assisted positional mooring system over a period of
four to six hours.
9.1.3 Two
copies of the test schedules, as required by Pt 7, Ch 8, 1.5 Plans and data submission 1.5.4.(h), signed by the Surveyor
and Builder, are to be provided on completion of the survey. One copy
is to be placed on board the ship and the other submitted to LR.