6.1.1 Before
a new installation (or any alteration or addition to an existing installation)
is put into service, tests are to be carried out to ensure satisfactory
operation of the navigational equipment. These tests are in addition
to any acceptance tests which may have been carried out at the manufacturers'
works and are based on the approved test schedule as required by Pt 7, Ch 9, 1.2 Information and plans required to be submitted 1.2.1.
6.1.2 For IBS Notation, testing at the manufacturer's works and trials on
board are to be carried out that cover the individual components and
their interaction; and the bridge functions and their integration
to form the Integrated Bridge System.
6.1.3 Two
copies of the test schedule, signed by the Surveyor and Builder, are
to be provided on completion of the survey. One copy is to be placed
on board the ship and the other submitted to LR.
6.1.4 Acceptance
tests and trials for Programmable Electronic Systems are to include
verification of software lifecycle activities appropriate to the stage
in the system's lifecycle at the time of system examination.