2.1.1 The
units and formulae used in the Rules are in SI Units.
2.1.2 It is
the responsibility of the Shipbuilder as main contractor to ensure
that the documentation required is prepared and submitted in accordance
with a project schedule which has been agreed by LR.
2.1.3 The
main propulsion machinery will be approved for the maximum continuous
power, and associated shaft speed or equivalent design and performance
criteria.
2.1.4 Main
propulsion machinery will be considered for operation at a higher
power rating than the classification rating for short time intervals
(referred to as short-term high power operation) in conjunction with
the intended operation service profile.
2.1.5 Facilities
are to be provided for cleaning, inspection and maintenance of main
propulsion and auxiliary machinery including boilers and pressure
vessels.
2.1.6 Where
it is proposed to depart from the requirements of the Rules, an Engineering
and Safety Justification, see
Vol 1, Pt 1, Ch 2, 2.2 Definitions is to be submitted to Clasifications Register ('LR')
for consideration.