(S) 3 Guidelines for
Surveys for the International Sewage Pollution Prevention Certificate
(SI) 3.1 Initial
surveys – see part "General", section 4.1
(SI) 3.1.1 For sewage pollution prevention the
examination of plans and designs should consist of:
-
(SI) 3.1.1.1 examining as appropriate
the arrangements for the provision of a sewage treatment plant, or
of a sewage comminuting and disinfecting system, or of a sewage holding
tank (MARPOL Annex IV reg.9);
-
(SI) 3.1.1.2 if a sewage treatment plant is fitted,
checking that it is type approved by the administration in accordance
with the appropriate resolution (MARPOL Annex IV regs. 9.1.1 and 9.2.1);
-
(SI) 3.1.1.3 if a sewage comminuting and disinfecting
system is fitted, checking that it is approved by the administration
and that facilities for the temporary storage of sewage are provided
(MARPOL Annex IV reg.9.1.2);
-
(SI) 3.1.1.4 if a sewage holding tank is fitted,
checking its capacity having regard to the number of persons on board
(MARPOL Annex IV regs. .9.1.3 and 9.2.2);
-
(SI) 3.1.1.5 examining the arrangements
for the provision of a standard discharge connection (MARPOL Annex
IV reg.10);
-
(SI) 3.1.1.6 examining the arrangements
for the provision of a pipeline for the discharge of sewage to a reception
facility (MARPOL Annex IV reg.10).
(SI) 3.1.2 For sewage pollution prevention the
survey during construction and after installation should consist of:
-
(SI) 3.1.2.1 checking externally, as applicable,
the sewage treatment plant or the sewage comminuting and disinfecting
system, and confirming their operation (MARPOL Annex IV regs.4.1.1 and 9.1.1, 9.1.2 and 9.2.1);
-
(SI) 3.1.2.2 if a sewage holding tank is fitted,
checking that it has been constructed in a satisfactory manner, and
checking that the holding tank has a means to indicate visually the
amount of its contents (MARPOL Annex IV regs.
.9.1.3 and 9.2.2);
-
(SI) 3.1.2.3 confirming that a standard
discharge connection is provided (MARPOL Annex IV reg.10);
-
(SI) 3.1.2.4 confirming that a pipeline
for the discharge of sewage to a reception facility is provided (
MARPOL Annex IV reg.10).
(SR) 3.2 Renewal
surveys – See "General", section 4.5
(SR) 3.2.1 For sewage pollution prevention the
examination of current certificates and other records should consist
of:
-
(SR) 3.2.1.1 checking the validity,
as appropriate, of the Cargo Ship Safety Equipment Certificate, the
Cargo Ship Safety Radio Certificate and the Cargo Ship Safety Construction
Certificate or the Cargo Ship Safety Certificate or Passenger Ship
Safety Certificate;
-
(SR) 3.2.1.2 checking the validity of
the International Load Line Certificate or International Load Line
Exemption Certificate;
-
(SR) 3.2.1.3 checking the validity of
the International Oil Pollution Prevention Certificate;
-
(SR) 3.2.1.4 checking the validity of
the International Air Pollution Prevention Certificate;
-
(SR) 3.2.1.4bis
confirming, when
appropriate, the validity of the International Energy Efficiency Certificate
(MARPOL Annex VI, regs. 6.4 and 6.5);
-
(SR) 3.2.1.5 checking the validity of
the International Ship Security Certificate;
-
(SR) 3.2.1.6 checking the certificates
of class, if the ship is classed with a classification society;
-
(SR) 3.2.1.7 checking, when appropriate,
the validity of the International Certificate of Fitness for the Carriage
of Dangerous Chemicals in bulk or the Certificate of Fitness for the
Carriage of Dangerous Chemical in Bulk;
-
(SR) 3.2.1.8 checking, when appropriate,
the validity of the International Certificate of Fitness for the Carriage
of Liquefied Gases in Bulk;
-
(SR) 3.2.1.9 checking when appropriate
the validity of the International Pollution Prevention Certificate
for the Carriage of Noxious Liquid Substances in Bulk;
-
(SR) 3.2.1.10 checking that the ship's
complement complies with the Minimum Safe Manning Document (SOLAS
74/88 reg.V/13(b));
-
(SR) 3.2.1.11 checking that the master,
officers and ratings are certificated as required by the STCW Convention;
-
(SR) 3.2.1.12 checking the validity
of the Safety management certificate (SMC) and that a copy of the
Document of Compliance (DOC) is on board, where applicable;
-
(SR) 3.2.1.13 checking whether any new
equipment has been fitted and, if so, confirm that it has been approved
before installation and that any changes are reflected in the certificate;
-
(SR) 3.2.1.14 confirming the availability
of the International Anti-Fouling System Certificate (AFS 2001 Annex
4 reg.2), when applicable.
(SR) 3.2.2 For sewage pollution prevention the
renewal survey should consist of:
-
(SR) 3.2.2.1 confirming that no change
has been made nor any new equipment installed which would affect the
validity of the certificate (MARPOL Annex IV reg.4.8);
-
(SR) 3.2.2.2 examining externally the sewage pollution
prevention system and confirming, as far as practicable its satisfactory
operation (MARPOL Annex IV, reg. 9);
-
(SR) 3.2.2.3 confirming that a procedure
for discharge of animal effluent is implemented on board (MARPOL 73/78/07
Annex IV reg.11.1.1).
-
(SR) 3.2.2.4 confirming, for ships where a sewage
holding tank is fitted as a sewage system, that an approval for the
rate of discharge is available (MARPOL IV, regs. 9.1.3 and 11.1.1)
-
(SR) 3.2.3 For sewage pollution prevention
the completion of the renewal survey should consist of:
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
 |
|