Section 22 Oxy-acetylene Welding and Cutting Plants
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules and Regulations for the Classification of Offshore Units, July 2022 - Part 1 Regulations - Chapter 3 Periodical Survey Regulations - Section 22 Oxy-acetylene Welding and Cutting Plants

Section 22 Oxy-acetylene Welding and Cutting Plants

22.1 Frequency of surveys

22.1.1 Pipe-laying units having an OXY notation in accordance with Pt 3, Ch 17 Pipe-laying Units are to be surveyed annually in accordance with the requirements of Pt 1, Ch 3, 22.2 Scope of surveys. A Special Survey in accordance with the requirements of Pt 1, Ch 3, 22.2 Scope of surveys is to be held at intervals not exceeding five years.

22.2 Scope of surveys

22.2.1 At each Annual Survey, leak testing of plant piping is to be performed using the ordinary operating pressures for oxygen and acetylene respectively. The gas supply to the plant piping is to be stopped by the central regulator being closed and the pressure in the plant piping is to then remain constant for at least eight hours. If pressure drop occurs in oxygen and/or acetylene plant piping, the plant is to be checked and repaired. The tests are to be carried out to the satisfaction of the Surveyor.

22.2.2 At each Special Survey, all plant piping is to be blown-through and be leak tested in accordance with the following:
  1. Dry and oil-free nitrogen is to be used for leak testing of low-pressure acetylene and oxygen piping and the test pressure is to be 12 bar. After eight hours, the pressure drop is not to exceed 0,4 bar.
  2. Acetylene piping on the high-pressure side is to be leak tested with dry and oil-free nitrogen at 25 bar. 25 bar relates to the maximum cylinder filling pressure at 15 °C. Where it is proposed to use cylinders with a higher filling pressure, the test pressure is to be agreed with LR.
  3. Oxygen piping on the high-pressure side is to be leak tested with 200-bar oxygen or dry and oil-free nitrogen. 200 bar relates to the maximum cylinder filling pressure at 15 °C. Where it is proposed to use cylinders with a higher filling pressure, the test pressure is to be agreed with LR.
  4. All valves, joints and other connections are to be checked for leakage by appropriate means.

The tests are to be carried out to the satisfaction of the Surveyor and be carried out by an appropriately qualified person.

Note Prior to the leak tests, blow-through of acetylene and oxygen piping is to be carried out with dry and oil-free nitrogen. Nitrogen is to be blown in from the high-pressure side and be carried off at the outlet station. The outlet station(s) (torch, stop valves, regulators, manometers, flash back arrestors and non-return devices) is to be removed during the blow-through process. At blow-through, the pressure is to be gradually increased to approximately 12 bar and the blow-through process is to continue till dirt no longer escapes from the pipe. High-pressure pipes are to be blown-through separately. The risk of injury to personnel or damage to the plant from blown-through gas and dirt is to be considered.

Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.