6.3.1 As far as possible oxygen systems should be designed so that they may be
disassembled for cleaning and testing outside the chambers without the need for
separating any permanent or semi-permanent joints, brazed or welded. The number of
couplings should be kept to a minimum.
6.3.2 It is recommended that individual components or assemblies be pre-tested
before being made up into the complete system. After installation the complete
system should be tested to at least 1.5 times the working pressure using water, air
or nitrogen. On completion of the above test the system should be thoroughly dried
and then pressurised with dry air or nitrogen to the normal operating pressure. The
system should then be shut off and the leakage rate measured, where a pressure drop
of 0,5 per cent in 12 hours shall not be exceeded, taking into account any
temperature change.
6.3.3 Following completion of the leak rate test, the system must be purged and tested to
ensure that all traces of test gases, including air or nitrogen, are removed before
filling with oxygen to its operating pressure.
6.3.4 All manifolds and connections, complete with supply pipes and fittings, should be
pressure tested at least once every four years to 1.5 times the working pressure.
The pressure gauges on the system should be tested for accuracy at the same time.
The first at four years from the date of build or date of Major Survey for
Classification as recorded on the Class Direct website, and thereafter five years
from the date recorded from the previous Major Surveys.
6.3.5 At intervals of approximately 12 months, the oxygen storage cylinders are to be
visually examined for collected dirt and moisture, excessive corrosion and general
condition.
6.3.6 All breathing gas cylinders are to be tested hydrostatically to at least 1.5 times
the working pressure every five years. A certificate of test is to be obtained.
Additional in service inspections as per IMCA D018 is to be complied with.