Section
2 Scope of survey for equipment
2.1 Accommodation/temporary refuge
units
2.1.1 Design appraisal and survey of structure, pipework, HVAC arrangements,
and fire and overpressure protection is required. See also C2.37 and C2.41.
2.2 Accumulators
2.3 Air receiver and drier vessels
2.3.1 Where the maximum air pressure is equal to 7 barg (100 psi) or greater, a
survey to Code requirements including design appraisal is required.
2.3.2 Where the pressures are less than 100 psi, valid manufacturers’
documentation can be accepted. Material is to be manufactured to a recognised
pressure vessel standard.
2.3.3 Typical acceptable standards: BS 5169, ASME VIII Div. 1 and BS 5500.
2.4 Air winches
2.5 Blast rated boundaries/enclosures
2.5.1 Design appraisal for rated blast overpressure and construction under
survey is required.
2.6 Blow out preventers and BOP control
unit
2.7 Burner (flare) booms or towers
2.7.1 Design appraisal is required with respect to:
- Environmental loads.
- Loads onto platform unit.
- Location and length with respect to heat radiation hazard.
- Construction under survey.
2.7.2 Typical acceptable Standards are Structural Design A.I.S.C., Fabrication
AWS D1.1, BS 4870, BS 4871 and Heat Radiation API RP 521.
2.8 Coolers/chillers
2.9 Compressors/compressor packages
2.9.1 Reciprocating machines above 100 kW are to be built under survey with
design appraisal of piping systems, any contained pressure vessels and torsional
vibration characteristics for large reciprocating machines. Hydrostatic tests to be
witnessed and manufacturers’ data examined for other components. See also
C2.53 and C2.55.
2.10 Cranes
2.11 Deluge systems
2.11.1 Review of P&IDs, hydraulic calculations, area coverage and pump
capacities is required. For survey, see C2.12, C2.41 and C2.45.
2.12 Diesel prime movers
2.12.1 For air compressors, mud pumps, cement pumps, generators and drawworks
except fire.
2.12.2 Pumps and emergency generators.
2.12.3 Design appraisal with respect to vibration (i.e., hazardous areas),
torsional vibration characteristics of shaft system and witness of commissioning of
machines is required.
2.12.4 For fire pumps, vessel propulsion, auxiliary service and emergency
generators.
2.12.5 Survey is required where the power is equal to or in excess of 100kW and
to include above. If power is less than 100kW, manufacturers’ documentation can be
accepted. Engines should be suitably marinised, batch and line approved and able to
operate under the conditions specified in LR Rules.
2.13 Distillation plants
2.14 Drums
2.15 Electrical equipment
2.15.1 Survey at manufacturers’ works is not required for equipment that is not
specified in LR Classification Rules requirements. Equipment must be manufactured in
accordance with a recognised Standard and manufacturers’ certificates are required.
Flameproof and I.S. equipment is to be supplied with relevant certification and
documentation issued by a recognised authority and must be suitable for the
application. After installation under survey, the integrity of the complete system
is to be established.
2.16 Emergency shut-down systems/fire and gas
systems
2.16.1 Witness of testing and documentation review at suppliers’ works by a
specialist LR Surveyor is recommended (mandatory where full Cause and Effect Testing
is not repeated during the installation commissioning phase).
2.16.2 Design appraisal requirements will vary according to the responsibilities
assigned to the supplier by the main design contractor. For programmable systems,
details of Hardware, system specification and Software QA manuals will be required
for review. (Process control systems do not require LR survey at suppliers’
works).
2.17 Fans
2.17.1 Survey at manufacturers’ works is not required. Manufacturers’
documentation to be supplied.
2.17.2 When intended for use in hazardous areas, fans must be of non-sparking
type.
2.18 Filters
2.19 Fire and foam pumps
2.20 Flare booms and towers
2.21 Flexible hoses
2.21.1 Manufacturers’ documentation, including prototype burst testing is
required. Fire test certification is generally required for hydrocarbons, high
pressure and essential control service.
2.22 Fluid transfer systems (fluid swivel
type)
2.22.1 Strength design appraisal and survey during manufacture, assembly and
test is required.
2.23 Gas turbines/compressors
2.24 Geared machinery
2.24.1 Witness of commissioning and testing after installation is required.
2.25 Heat exchangers
2.25.1
Hydrocarbons. Design appraisal and survey during manufacture to Code
requirements is required.
2.25.2
Non-hydrocarbons, Design pressures greater than or equal to 7 barg (100 psi).
Design appraisal and survey during fabrication is required. See also C2.43,
which applies equally to shell and tube exchangers.
2.25.3
Non-hydrocarbons. Design pressures less than 7 barg (100 psi). Manufacturers’
documentation can be accepted with hydrostatic tests being witnessed after
installation. Material is to be manufactured to a recognised pressure vessel
standard.
2.25.4 Typical acceptable codes: PD 5500, ASME VIII Div. 1 & 2 and TEMA
Standards.
2.26 Helideck
2.26.1 Design appraisal of structure, markings, lights, obstacle free/drop off
zones, fire and escape arrangements is required. Survey under fabrication as for
modules.
2.27 Hoists
2.28 Hydrocyclones
2.28.1 Survey at manufacturers’ works is not required for proprietary drilling
equipment.
2.29 Hydro-pneumatic accumulators – Manifolds,
fluid reservoirs
2.29.1 Design appraisal and construction under survey is required.
2.29.2 Typical acceptable standards: BS 5045 and ASME VIII Div. 1.
2.30 Impressed current CP system
2.30.1 Design appraisal. Survey of installation, witness test and commissioning
are required.
2.31 Inert gas generator
2.31.1 Design appraisal and survey at manufacturers’ works. Witness test and
commissioning are required.
2.32 Lifeboats, TEMPSCs, rescue craft and
davits
2.32.1 Design appraisal and survey at manufacturers’ works. Witness test and
commissioning are required.
2.33 Lifting appliances and cranes
2.33.1 To be built under survey in accordance with the LR’s Code for Lifting
Appliances in a Marine Environment, which would include design appraisal, material
identification, weld procedures and welder qualification tests, approval of NDT
procedures and testing on completion. Care is to be taken that the appliance is
suitable for use under dynamic loading offshore.
2.33.2 Air winches (non-personnel). No survey required at source.
Manufacturers’ documentation will be accepted provided it includes evidence of
hydrostatic test of pressure parts.
2.33.3 Cranes mountings, including pedestals. Design appraisal and construction
under survey is required. Witness of testing and commissioning after installation is
also required.
2.33.5 Personnel hoist. Design appraisal and construction under survey is
required. Witness of testing and commissioning after installation is also
required.
2.33.6 Other lifting devices. Where LR Certification is required by the client,
design appraisal and survey with load testing after installation on the
platform/unit is required.
2.33.7 Other lifting devices. Where LR Certification is not required,
inspection and testing at the manufacturers’ works is required only for devices with
a capacity greater than or equal to 10 tonnes. Devices with a capacity of less than
10 tonnes can be accepted if presented with valid manufacturers’ documentation. In
addition, they must be tested after installation.
2.34 Loading instrument
2.34.1 To be verified for LR Classification compliance – see
Pt 1 Regulations. Hardware to be type approved for marine use.
2.35 Manifolds, choke, production, test,
etc.
2.35.1 Design appraisal and survey is required.
2.35.2 Typical acceptable standards: ANSI B3 1.3.
2.36 Metering packages and equipment
2.36.1 To be built under survey with design appraisal of piping systems aspects
and any pressure vessels. Hydrostatic test to be witnessed and manufacturers’ data
examined for all other aspects.
2.37 Modules (all types)
2.37.1 Design appraisal and survey of structure during construction is required
and the following loads should be considered in the design.
- Environmental.
- Equipment and operational weights.
- Construction, including lifting case.
2.38 Mooring systems (floating
installations)
2.38.1 Structural. Design appraisal and survey during manufacture is required
for all components, including anchors, cables, chains, turret structure, etc.
2.38.2 Machinery. Design appraisal is required for all main bearings, mooring
winches and chain stoppers.
NOTE:
Quayside mooring equipment can be accepted on the basis of
manufacturers’ documentation.
2.39 Offloading systems
2.39.2 Strength design appraisal of mooring winches, breakaway couplings, etc.,
is required.
2.40 Pig launchers and receivers
2.41 Pipework and fittings
2.41.1 All fabricated pipework, e.g., process systems, gas and liquid fuel
systems, fire main, compressed air lines, hydraulic systems, mud systems, etc., will
be subject to design appraisal and survey during fabrication. Pipe fittings will
normally be accepted with manufacturers’ documentation, but significant fabricated
items may require survey at manufacturers’ works. Fabricated saddles for use in the
fire main should be supplied with a copy of a valid proof test certificate.
2.41.2 The survey must include:
- Review of QA/QC system.
- Examination at works during fabrication and test.
- Review and acceptance of weld procedures and welder
qualification tests.
- Review and acceptance of NDT procedures.
- Verification of materials against relevant mill
certificates.
- Appraisal of P&IDs, material and pipe schedules.
2.41.3 Where pipework is included as part of a package, it is to be surveyed as
above.
2.41.4 Typical acceptable standards: ANSI B3 1.3.
2.42 PLCs/programmable electronic
systems
2.42.1 Hardware to be type approved for offshore use. Software to be developed
under suitable software QA system. LR to witness commissioning tests.
2.43 Pressure vessels
2.43.1 (Separators, knockout drums, pulsation dampers, etc., including auto
sprinkler and fire-extinguishing storage systems).
2.43.2 Where the system gauge pressure in bar multiplied by the internal volume
in litres exceeds 200, vessels are to be built under survey which would include
design appraisal, material identification, weld procedure and welder qualification
tests and approval of NDT procedures. The vessel is to be built in accordance with a
recognised Code or Standard and subject to hydrostatic test and internal examination
on completion.
2.43.3 Typical acceptable codes: PD 5500 and ASME VIII.
2.44 Process equipment (bulk)
2.44.1 All equipment, whether installed initially or at a subsequent date,
should be manufactured to a relevant Code, Standard or specification and written
confirmation of this, together with appropriate test certificates, should be
obtained from the manufacturer. See C2.41 and the remainder of this appendix
for individual equipment items.
2.45 Pumps – Fire, water deluge, foam,
etc.
2.45.1 All fire-fighting pumps (and prime movers) to be built under survey.
2.45.2 Material certificates and certificates for hydrostatic testing of cast
casings, etc., to be reviewed.
2.46 Pumps for other services
2.46.1 Survey at manufacturers’ works for verification purposes is not
required. Manufacturers’ documentation including material certificates is to be
supplied.
2.47 Radio tower
2.47.1 Design appraisal will be required only in respect of:
- Environmental loads.
- Loads transmitted to the structure.
- Location relating to the helideck.
2.47.2 No fabrication inspection is required.
2.48 Regenerators and absorbers, glycol –
(fired) boilers and steam receivers – (fired)
2.48.1 Design appraisal and survey is required, see also C2.43 and C2.25.
2.49 Separators
2.50 Steel – Plate, rolled sectors, tubulars
and pipe
2.50.1 For certification, inspection/validation at mill in accordance with a
recognised Standard and specification is required on all material for primary
structures. However, certification of other IACS members will in general be
acceptable.
- Jackets including conductor framing.
- Piles.
- Any secondary steel that is connected directly to the primary
structure.
- Any structural steel utilised for the load-bearing framework of
the module.
- Where floors contribute to the strength and integrity of the
module. Where steel is procured from steelworks approved by LR, our scope
will normally be limited to witness of mechanical testing and check of
results against agreed specifications. In the event of primary steel being
procured from stockists, LR involvement will normally consist of
verification of test certificates, material identification and confirmation
of properties against agreed specifications.
2.50.2 Materials for secondary structures need not be inspected at source
provided the material is manufactured in accordance with a recognised Standard and
is supported by manufacturers’ valid mill certificates.
2.50.3 Examples of secondary structures include gangways, walkways, handrails,
cladding, helideck, floors, pipe supports, equipment plinths, mud and similar tanks
and installation aids.
2.51 Strainers
2.52 Tanks
2.52.1 Dry mud, barytes, bulk cement, chemicals:
- Design appraisal and survey is required if the above tanks are
to be subjected to any positive or negative pressure conditions.
- If not pressurised, the Surveyors may accept a Third Party
Inspection Certificate with evidence of testing for the purpose
intended.
2.52.2 Non hazardous liquid storage tanks – Open, vented or hydrostatic head
only. Third party Inspection Certificate with evidence of construction and testing
to a recognised Code or specification is required.
2.52.3 Pressurised lubricating oil or seal-oil tanks. Design appraisal and
survey is required.
2.52.4 Fuel tanks and hazardous liquid tanks. Design appraisal and survey is
required. Typical acceptable standards: BS 799 part IV and BS 2654.
2.53 Turbines and compressors
2.53.1 Design pressure greater than or equal to 7 barg (100 psi). Surveyor is to
verify manufacturers’ documentation, witness hydraulic tests of pressure parts and
commissioning of machines.
2.53.2 Design pressure less than 7 barg (100 psi). Surveyor is to verify
manufacturers’ documents and witness commissioning. Material is to be manufactured
to a recognised pressure vessel standard.
2.53.3 Gas turbines. Consideration should be given to the codes used for
pressure-retaining components and the need for containment, with a view to
minimising and localising damage in the event of rotor blade failure. Survey of
fabricated pressure-retaining items will generally be required.
2.54 Umbilicals for subsea completion control
systems
2.54.1 Design appraisal and survey at source to include review of manufacturing
and quality plans is required. Witness of factory acceptance tests and documentation
review is also required.
2.55 Valves including emergency shut-down and
safety valves
2.55.1 In general, valves and fittings need not be surveyed at source provided
they are manufactured in accordance with a recognised Code or Standard and are
identifiable with a manufacturers’ certificate which includes the materials used for
pressure-containing parts.
2.55.2 Details of certain large valves and fittings of welded construction will
require to be submitted for special consideration, (e.g., Riser ESDVs, SSIVs, etc.).
Design appraisal and survey of these items will be required in most cases.
2.55.3 Testing of pressure relief valves to be witnessed during commissioning at
fabrication sites.
2.55.4 Typical acceptable standards: Safety Valve Design API RP 520, Valves API
6 series, B55351 and Fittings BS 1640.
2.56 Ventilation and pressurisation systems
including fire dampers
2.56.1 Design appraisal: hazardous area zones and structural fire protection.
The systems are to be surveyed and tested during installation and commissioning.
2.56.2 Fire Dampers are to be type approved.
2.57 Well control equipment
2.57.1 Design appraisal for manufacture. Surveyors will issue a Certificate of
Conformity following completion of the equipment and when satisfied that the
equipment has been built and tested in accordance with the approved Specification
for Manufacture. Manufacturers’ records of materials, inspection and tests should be
assessed by the Surveyor.
2.57.2 For Verification (Wells Examination). Well control equipment will be
subject to a design examination and survey during construction/assembly and testing
where the equipment is designated as safety critical to the Installation.
2.57.3 Work done by others to meet the requirements of the well examination
scheme will contribute to verification.
2.58 Well control panel
2.58.1 Design appraisal and survey, as for pipework and fittings.
2.59 Winches
2.60 Xmas trees
|