1.1.2 Additional requirements with respect to unit types as indicated in this Chapter are
                                 also to be complied with, as applicable.
                              
                              
                              
                            
                           
                           
                           
                              
                              
                              1.1.3 Where it is intended to operate the ballast system bypassing the ballast water
                                 treatment system (e.g. lifting operations of heavy-lift crane units which take in
                                 and discharge at the same location before repeating at another location), a risk
                                 assessment is to be carried out in accordance with IMO Resolution MEPC.162(56) - Guidelines for Risk Assessment Under Regulation A-4 of the BWM Convention (G7) - (Adopted on 13
                                    July 2007). Where ballast systems and tanks which bypass
                                 ballast water treatment systems are required to be cleaned between operations, these
                                 are to be identified on the plans and their cleaning procedures are to be included
                                 in the Operations Manual.