Section
1 General
1.1 Application of these Rules
1.1.1 The requirements
of this Chapter are applicable to shiplift platform and transfer systems,
also called mechanical lift docks, as defined in Ch 5, 1.2 Scope of the Rules.
1.1.2 The requirements
are based on the understanding that:
-
The shiplift will, at
all times, be properly loaded in accordance with the designer’s
instructions and the loading conditions approved by Lloyd’s
Register (LR). Concentrations of loading greater than that indicated
by the specified maximum distributed load, or for any loading situations
or weather conditions which may result in the rated capacity of individual
hoists being exceeded are not allowed for.
-
Where the installation
is to be certified but not classed, the design criteria specified
assume that Periodical Survey procedures, at least equivalent to LR’s,
will be adhered to by the Owner. This is of particular importance
with respect to ropes and chains used to raise the platform.
-
The shiplift will at
all times be properly operated by trained and authorised personnel.
-
The shiplift will be
maintained by qualified and authorised personnel.
-
Compliance with the
requirements does not relieve the designers and/or Builders/contractors
of their contractual responsibilities to the client with regard to
the specification and the overall design and in-service performance
of the shiplift.
1.2 Scope of the Rules
1.2.1 The requirements
of this Chapter are applicable to shiplift and transfer system installations
in which vessels are raised and lowered by means of winches or jacks
when docked on an articulated or rigid platform structure.
1.2.2 The vessel
may be docked on a system of blocks, cradles or an air/hydraulic cushion
arrangement for subsequent transfer.
1.2.3 Docking systems
which incorporate a combination of both mechanical lift dock and floating
dock principles will be specially considered on the basis of these
requirements and LR’s Rules and Regulations for the Construction
and Classification of Floating Docks.
1.2.4 When specifically
requested, end and side transfer arrangements will be examined and
included in the class notation or certification issued. However, where
the design concept of the platform involves an interaction or interdependence
between the platform and transfer system, as in the case of a rigid
platform with flexible ship support system, the transfer system will
be considered as an essential and integral aspect of class or certification.
1.2.5 All civil
engineering interface works, including hoist foundations, piling and
associated sea-bed conditions, shore transfer pits and dockside structures,
are excluded from LR’s involvement.
1.2.6 These requirements
do not apply to hoisting platforms used on vessels or to mechanical
elevators used to lift people.
1.3 Classification procedure
1.3.1 Classification
covers the design, construction, testing and subsequent Periodical
Surveys of Shiplift and Transfer Systems to the extent indicated within
these requirements and is achieved by way of the intervention of LR
Surveyors at the appropriate stages of design, construction, installation,
commissioning, and periodical examinations during service. The following
procedure is to be adopted where LR classification is required:
-
Approval of plans covering
structural, electrical, mechanical, hydraulic and control engineering
aspects of the installation.
-
The material for primary
structural steel adopted for a classed installation is required to
comply with Ch 5, 3.2 Materials for classed installations of these requirements.
-
Fabrication under Survey
of steelwork, hoists and hydraulic cylinders at the place of manufacture,
including verifying that approved materials and suitably qualified
welders using approved weld procedures are employed in the fabrication.
-
Survey at the factory
to include the control panel (or MCC) and load pin for the load monitoring
system.
-
Certification on the
appropriate forms of wire ropes and chains which are to be manufactured
at a works approved by LR.
-
Survey of the platform
structure, hoists, electrical, control and hydraulic systems during
installation and on-site assembly.
-
Proof load and initial
operational testing of the facility, as specified in Ch 5, 7.2 Load tests and 7.6.
-
Periodical Surveys and
tests, as specified in Ch 5, 8.7 Classification of installations not built under Survey.
1.4 Certification procedure
1.4.1 Where certification, which is distinct from classification, of the shiplift and transfer
system is requested, the procedures to be adopted are the same as those for
classification outlined in Ch 5, 1.3 Classification procedure, with the following exceptions:
- The material for primary structural steel adopted for certified installations is
required to comply with Ch 5, 3.1 Materials for certificated installations of these requirements.
- A class notation will not be assigned to certified shiplifts and transfer
systems.
- Periodical Surveys after commissioning of the shiplift and transfer
system need not be carried out by LR. However, the Owner’s/designer’s attention is
drawn to Ch 5, 1.1 Application of these Rules 1.1.2.(b) with respect to
the need for ongoing Surveys.
1.5 Interpretation of the Rules
1.5.1 The interpretation
of the Rules is the sole responsibility, and at the sole discretion,
of LR. Any uncertainty in the meaning of the Rules is to be referred
to LR for clarification.
1.6 Responsibilities of the Owner/Operator, Builder and designer
1.6.1 It is the
responsibility and the duty of the Builder or main contractor to enable
the Surveyors to satisfy themselves that the materials, workmanship
and arrangements comply with the classification requirements, by arrangement
for the Surveyors to be present at appropriate stages during the work
and for presenting the items to be surveyed in such a way that the
Surveyors are readily able to establish that all component/ sub-component
items have been manufactured, assembled and tested in accordance with
the appropriate requirements.
1.6.2 Surveys undertaken
by LR, when providing services, are on the basis of periodical visits
involving both monitoring and direct survey. It should be noted that
LR’s Surveyors will not, generally, be in continual attendance.
Since construction and installation are continuous processes, the
Builder has the overall responsibility to ensure and document that
the construction meets LR’s requirements, is in accordance with
the approved drawings, and that any amendments agreed with LR’s
Surveyors have been complied with.
1.6.3 It is the
responsibility of the Owners, Operators, designers, building contractors
and any repairers to acquaint themselves fully with the scope of these
requirements and associated obligations, and satisfy themselves that
these requirements are sufficient for their purposes.
1.6.4 The attention
of the Owner, Operators, Builders and designers is drawn to statutory
requirements which may be imposed by the relevant National Authorities
that may not be within the scope of classification or certification.
If there is any conflict between local statutory requirements and
those of LR then the local requirements will take priority without
necessarily affecting LR classification/certification, provided the
structural strength and safety aspects are not compromised.
|