Section
1 General requirements
1.1 Scope
1.1.1 Provision is made in this Chapter for the manufacture and testing of
plastic pipes, together with approval requirements for base materials used in the
construction or repair of composite vessels, other marine structures, piping and any
associated machinery components and fittings which are to be certified or are intended
for classification.
1.1.2 These materials
and products are to be manufactured and surveyed in accordance with
the general requirements of Ch 14, 1 General requirements, Ch 14, 2 Tests on polymers, resins, reinforcements and associated materials and Ch 14, 3 Testing procedures of
this Chapter; and LR’s Materials and Qualification Procedures
for Ships (MQPS) Book K, see
Ch 1, 2.2 LR Approval – General 2.2.2, which, in addition to the
test programme, also details the procedures for application for approval
of manufacturers and products and details of the information to be
supplied by the manufacturer.
1.1.3 For base
materials, the manufacturer's works do not require approval by Clasifications
Register (hereinafter referred as 'LR'), however the Quality Control
procedures must be acceptable in accordance with the appropriate Section
of this Chapter.
1.1.7 For the
purposes of these Rules a ‘plastics material’ is regarded
as an organic substance which may be thermosetting or thermoplastic
and which, in its finished state, may contain reinforcements or additives.
1.1.8 Materials
not listed in Ch 14, 2.1 Scope 2.1.1 may be considered
for approval on a case-by-case basis. The approved test results will
be listed on the issued certificate. Subject to satisfactory service
experience and validation of approval, the material may be entered
in Ch 14, 2.1 Scope 2.1.1 of the Rules.
1.2 Information on material quality and application
1.2.1 Where plastics
products are to be classed or certified, the manufacturer is to provide
the material producer with such information as is essential to ensure
that the base materials to be used are in accordance with the approval
requirements and the product specification. This information is to
include any survey requirements for the materials.
1.3 Manufacture
1.3.1 Plastics
products are to be made at works which have been approved (or accepted)
for the type of product being supplied using base materials that have
been approved.
1.3.3 In order
that a works can be approved (or accepted), the manufacturer is required
to demonstrate to the satisfaction of LR that the necessary manufacturing
and testing facilities are available and are supervised by qualified
personnel. A specified programme of tests is to be carried out under
the supervision of the Surveyors, and the results are to be to the
satisfaction of LR. When a manufacturer has more than one works, the
approval (or acceptance) is only valid for the individual works which
carried out the test programme.
1.3.4 In order
to maintain approval, the manufacturer is required to confirm in writing
that there have been no changes in the formulation or production process
for the material in question and that the site of manufacture remains
unchanged.
1.4 Survey procedure
1.4.1 The Surveyors
are to be allowed access to all relevant parts of the works and are
to be provided with the necessary facilities and information to enable
them to verify that manufacture is being carried out in accordance
with the approved procedure. Facilities are also to be provided for
the selection of test material, the witnessing of specified tests
and the examination of materials, as required by the Rules.
1.4.2 Prior to
the provision of test material for acceptance, manufacturers are to
provide the Surveyors with details of the order, specification and
any special conditions additional to the Rule requirements.
1.4.3 Before final
acceptance, all test materials are to be confirmed as typical of the
manufactured product and be submitted to the specified tests and examinations
under conditions acceptable to the Surveyors. The results are to comply
with the specification and any Rule requirements and are to be to
the satisfaction of the Surveyors.
1.4.4 These specified
tests and examinations are to be carried out prior to the despatch
of finished products from the manufacturer's works.
1.4.5 In the event
of any material proving unsatisfactory, during subsequent working,
machining or fabrication, it is to be rejected, notwithstanding any
previous certification.
1.5 Alternative survey procedure
1.5.1 Where materials
are manufactured in quantity by semi-continuous or continuous processes
under closely controlled conditions, an alternative system for testing
and inspection may be adopted, subject to the agreement of the Surveyors.
1.6 Post-cure heating
1.6.1 Post-cure
heating is to be carried out in properly constructed ovens which are
efficiently maintained and have adequate means for control and recording
of temperature. The oven is to be such as to allow the whole item
to be uniformly heated to the necessary temperature. In the case of
very large components which require post-cure heating, alternative
methods will be specially considered.
1.7 Test material
1.7.1 Sufficient
material is to be provided for the preparation of the test specimens
detailed in the specific requirements. It is, however, in the interests
of manufacturers to provide additional material for any re-tests which
may be necessary, as insufficient or unacceptable test material may
be a cause for rejection.
1.7.2 Where test
materials, (either base materials or product sample materials) are
selected by the Surveyor or a person nominated by LR, these are to
be suitably identified by markings which are to be maintained during
the preparation of the test specimens.
1.7.3 All base
material samples for testing are to be prepared under conditions that
are as close as possible to those under which the product is to be
manufactured. Where this is not possible, a suitable procedure is
to be agreed with the Surveyor.
1.7.4 During production,
check test samples are to be provided as requested by the Surveyor.
1.7.5 Should the
taking of these samples prove impossible, model samples are to be
prepared concurrently with production. The procedure for the preparation
of these samples is to be agreed with the Surveyor.
1.7.6 The dimensions,
number and orientation of test specimens are to be in accordance with
the requirements of a National or International Standard acceptable
to LR.
1.8 Re-test procedure
1.8.1 Where test
material fails to meet the specified requirement, two additional tests
of the same type may be made at the discretion of the Surveyor.
1.8.2 Where an
individual test result in a group (minimum five) deviates from the
mean by more than two standard deviations in either the higher or
lower direction, the result is to be excluded and a re-test made.
Excluded results of tests are to be reported with confirmation that
they have been excluded. Only one exclusion is acceptable in any group
of tests.
1.9 Visual and non-destructive examination
1.9.2 When there
is visible evidence to doubt the soundness of any material or component,
such as flaws or suspicious surface marks, it is to be the responsibility
of the manufacturer to prove the quality of the material by any suitable
method.
1.10 Rectification of defective material
1.10.1 Small
surface blemishes may be removed by mechanical means provided that,
after such treatment, the dimensions are acceptable, the area is proved
free from structural defects and the rectification has been completed
to the satisfaction of the Surveyor.
1.10.2 Repair
procedures for larger defects are to be agreed with LR prior to implementation.
1.11 Identification of products and base materials
1.11.1 The manufacturer
of approved materials is to identify each batch with a unique number.
1.11.2 The manufacturer
of plastics products is to adopt a system of identification which
will enable all finished products to be traced to the original batches
of base materials. Surveyors are to be given full facilities for tracing
any component or material when required.
1.11.3 When any
item has been identified by the personal mark of a Surveyor, or deputy,
this is not to be removed until an acceptable new identification mark
has been made by a Surveyor. Failure to comply with this condition
will render the item liable to rejection.
1.11.4 Before
any pipe or fitting is finally accepted it is to be clearly marked
by the manufacturer in at least one place with the particulars detailed
in the appropriate specific requirements as given in Ch 14, 4 Plastic pipes and fittings.
1.11.5 Where
a number of identical items are securely fastened together in bundles,
the manufacturer need only brand the top item of each bundle. Alternatively,
a durable label giving the required particulars may be attached to
each bundle.
1.12 Certification
1.12.1 Certification
of the finished product is to be in accordance with the requirements
of the appropriate Sections.
|