Section
3 Plans and particulars
3.1 General
3.1.1 Before
the work is commenced, plans in triplicate, together with the relevant
information as detailed in this Section, are to be submitted for consideration.
Any subsequent modifications are subject to approval before being
put into operation.
3.1.2 Any
alterations to basic design, construction, materials, manufacturing
procedure, equipment, fittings or arrangements of the process are
to be re-submitted for approval.
3.1.3 For
Category 1 ships, the plant is to be capable of sustaining an emergency
condition at full operating temperatures and pressures with the hull
statically listed to an angle of 22 ° and statically trimmed to an angle of 10° beyond
the maximum normal operating trim. These angles may be modified by
the Committee in particular cases as it considers necessary. The stress
calculations for the plant and the supporting structure are to take
account of this condition. Wind loads need not be considered to be
acting during this emergency condition.
3.1.4 For
Category 2 ships, the plant is to be capable of sustaining an emergency
condition at full operating temperatures and pressures with the hull
statically listed to an angle of 15° and statically trimmed to
an angle of 5° beyond the maximum normal operating trim. These
angles may be modified by the Committee in particular cases as it
considers necessary. The stress calculations for the plant and the
supporting structure are to take account of this condition. Wind loads
need not be considered to be acting during this emergency condition.
3.2 Hull construction
3.2.2 Plans
showing the general arrangement of the ship are to be submitted, giving
the location of the following:
- Hatches and other openings to enclosed plant spaces and adjacent
cofferdams.
- Doors, hatches, ventilation and other openings to crew accommodation,
stations essential for operation at sea, control stations, store rooms
and workshops.
- Coated tanks or tanks constructed of special material.
- Additional structure associated with the plant above the deck.
- Proposed grouping of areas within the plant for segregation purposes.
3.2.3 Plans
for mooring, anchoring and linking, as applicable, together with relevant
wind and sea data are to be submitted for information.
3.2.4 Plans
outlining the containment arrangements in the event of an accident,
together with all relevant information, are to be submitted.
3.2.5 Particulars
of the marine environment and safety arrangements associated with
the process plant are to be submitted, including:
- Arrangements for preventing the ingress of water into the ship
or structure where process plant and equipment protrude through the
weather deck.
- Proposed emergency flooding procedures and their control.
3.2.6 Particulars
of the proposed storage arrangements of hazardous and/or toxic substances,
feedstocks and products in bulk, on the ship or structure, are to
be submitted.
3.3 Process plant
3.3.1 A description
of the expected method of operation of the process plant and a diagram
showing the process flow are to be submitted.
3.3.2 General
arrangement plans of the process plant showing the hazardous and safe
zones and spaces are to be submitted, indicating the following:
- Spaces where toxic gases or vapours may accumulate.
- Spaces where flammable gases or vapours may accumulate.
- Areas maintained at an over-pressure to prevent the ingress of
such gases or vapours.
3.3.3 Details
of the flammability, toxicity, corrosivity and reactivity of the substances
entering, being processed and leaving, or stored in, each compartment,
together with details of any exothermic and hazardous reactions particularly
with regard to sea-water and other materials normally found in the
marine environment, are to be submitted.
3.3.4 Plans
of the layout of the process plant indicating the hatches and other
openings to enclosed plant spaces and cofferdams are to be submitted.
3.3.5 Details
and arrangements of the blow-down systems, including quantities of
materials and the capacity and working pressure of the containers
installed for the reception of the materials to be blown down, are
to be submitted.
3.3.6 Proposals
for de-watering blow-down tanks in which hot oils and/or chemicals
are discharged are to be submitted.
3.3.7 Proposals
for the purging, gas freeing, inerting or otherwise rendering safe
of the process plant and storage facilities are to be submitted.
3.3.8 Particulars
of the arrangements for protecting the process plant systems and vessels
against temperature, over-pressure and vacuum are to be submitted.
3.3.9 Proposals
for the disposal of hazardous or toxic gases and liquid effluents
during normal plant operation, including any proposed flare systems,
are to be submitted.
3.3.10 Particulars
of the proposals for isolating the ship or structure from the shore
installation and/or lightering ships or vessels, where applicable,
and from the supply of fuel to boilers, etc. in the process plant
and the return flow of chemicals or process effluent, are to be submitted,
including:
- Feedstock supply and product discharge, with details of the arrangements
showing the location of shut-off valves and of the control and indicating
stations.
- The process plant parameters and analysis of transient conditions
under which emergency shutdown will be initiated and the time estimated
to obtain a safe environment.
- The proposed emergency procedures for controlled shutdown of the
process plant, i.e. depressurising, inerting, etc. and the arrangements
for the continued operation of the essential services necessary to
allow for such controlled shutdown under the emergency conditions
of Pt 7, Ch 2, 3.1 General 3.1.3 or Pt 7, Ch 2, 3.1 General 3.1.4, as applicable.
3.3.11 Plans
for the ventilation of process plant compartments are to be submitted,
together with the following information:
- Location of hazardous and safe zones and spaces.
- Location of all possible sources of ignition.
- Location of air inlets and outlets.
- Number of complete air changes per hour.
- Estimated maximum and minimum ambient temperatures for the regions
in which the plant is to operate.
- Expected heat loss of the process plant to the compartment environment.
3.3.12 Particulars
of any dust or gas explosion hazard in the enclosed compartments of
the process plant are to be submitted.
3.3.13 Proposals
for the decontamination of the process plant compartments are to be
submitted.
3.3.14 Proposals
for the detection of vapour or gas and of oxygen deficiency in the
process plant compartments are to be submitted.
3.4 Mechanical equipment associated with the process plant
3.4.1 A list
of mechanical equipment associated with the process plant, with the
exception of any boilers and other pressure vessels, to be installed
in the ship or structure is to be submitted.
3.4.2 Details
of safety and relief devices and their discharge arrangements are
to be submitted.
3.4.3 When
required, in order to facilitate inspection, plans showing the materials
of construction, working pressures and temperatures, maximum power
and revolutions per minute, as applicable, are to be submitted before
the work is commenced.
3.4.4 Calculations
of the torsional vibration characteristics of the shafting systems,
where applicable, are to be submitted in accordance with the requirements
of Pt 5, Ch 8 Shaft Vibration and Alignment.
3.5 Boilers and other pressure vessels associated with the process
plant
3.5.1 Plans
of the boilers and other pressure vessels, including the proposals
for the support of the vessels, are to be submitted.
3.5.2 Details
of the safety and relief devices and their discharge arrangements
are to be submitted.
3.5.3 Stress
calculations are to be submitted, taking into account the ship linear
and angular accelerations, roll and pitch amplitudes, ship flexure
and wind loads appropriate to any condition which may normally arise
at sea. Where applicable, calculations for the emergency condition
in Pt 7, Ch 2, 3.1 General 3.1.3 or Pt 7, Ch 2, 3.1 General 3.1.4 are to be submitted. Due consideration
is to be given to the effects of thermal expansion and contraction
on the support points of the vessels.
3.5.4 Outline
plans of all types of fired equipment, ventilation arrangements with
projected casing temperatures, uptake arrangements, gas and/or fuel
oil burning arrangements and controls are to be submitted.
3.6 Pumping and piping systems associated with the process plant
3.6.1 Plans
of the process plant piping systems, showing the materials of construction,
scantlings, support and expansion arrangements, together with the
calculations, are to be submitted for consideration.
3.6.2 The
following diagrammatic plans for systems associated with the process
plant are to be submitted, in addition to those required by Pt 5, Ch 13 Ship Piping Systems and Pt 5, Ch 15 Piping Systems for Oil Tankers or Chapter V of the Rules for Ships for Liquefied Gases,
as applicable:
- The Shipbuilder's plan of the general pumping arrangements, including
air and sounding pipes and any cross flooding pipes and fittings.
- Pumping arrangements at the fore and aft ends, drainage of cofferdams
and process spaces.
- Bilge, ballast and fuel oil pumping arrangements in the process
plant machinery space, including the capacities of the pumps on bilge
service.
- Arrangement of fuel oil pipes and fittings at settling and service
tanks.
- Arrangement of gas and/or fuel oil piping in connection with gas
and/or oil burning arrangements.
- Fuel oil overflow systems, where fitted.
- Arrangement of boiler feed system.
- Arrangement of compressed air systems for the process plant.
- Arrangements of lubricating oil and cooling water systems, fuel
oil settling, service and other oil tanks not forming part of the
ship's structure.
3.6.3 Plans
showing the arrangement and dimensions of main steam pipes, with details
of flanges, bolts and weld attachments and particulars of the materials
of the pipes, flanges, bolts and welding consumables, are to be submitted
for consideration.
3.6.4 Details
of the safety and relief devices and their discharge arrangements
are to be submitted.
3.7 Electrical equipment for the process plant
3.7.1 Details
of the electrical system(s) are to be submitted, including the following:
- A statement quoting the standard or Code of Practice in accordance
with which the installation has been designed.
- A statement quoting the standard of design and/or manufacture
of electrical equipment, e.g. BS, NEMA, VDE, etc.
- A schedule of the normal operational loads on the system, estimated
for the different operating conditions expected.
- Expected range of ambient temperature.
3.7.2 The
following line diagram plans and particulars are to be submitted:
- General arrangement plan of the process plant showing the location
of the major items of electrical equipment.
- Line diagram of the installation(s) indicating the rating of the
various items of rotating machinery, converters, transformers and
protective devices, together with the types and sizes of cables and
the makes and types of protective devices.
- Arrangement plans and circuit diagrams of the switchboards.
- Calculations of short-circuit currents at the main switchboards,
sub-switchboards and the secondary side of transformers.
- General arrangement plan of the process plant showing the location
of electrical equipment in hazardous zones, together with the Code
of Practice on which they are based.
- A schedule of safe-type electrical equipment located in hazardous
zones, giving details of the type of equipment employed, the certifying
authority and the certificate number.
3.7.3 Written
confirmation and Works' Test Certificates that all items of electrical
equipment comply with the relevant standard or Code of Practice are
to be supplied.
3.8 Control equipment for the process plant
3.8.1 Details
of the control system(s) are to be submitted, together with the following
line diagrams and particulars:
- Line diagrams of any control system(s) fitted.
- General arrangement plan of the process plant showing the locations
of items of control equipment and the locations of hazardous zones.
- Schedule of the parameters which are monitored and controlled,
including alarms and shutdown devices.
3.9 Fire protection, detection and extinction
3.9.1 Plans
of fire protection, detection and extinction arrangements, together
with details of the fire and explosion hazards involved, are to be
submitted.
|