Section
1 General
1.1 Application
1.1.1 These Rules apply to dock gates, as defined in Pt 2, Ch 2, 1.3 Types of dock gate. Although the Rules are,
in general, for steel floating docks of all welded construction, other materials and
design configurations will be specially considered.
1.1.2 The following aspects are not covered by these Rules:
- connections to the dock walls/entrance;
- slots for sliding/rolling dock gates;
- stability aspects;
- the dock structure supporting the dock gate;
- equipment and machinery for operating the dock gate;
- electrical and hydraulic systems;
- portable equipment, staging or temporary supports; and
- mooring lines or dock side winches.
1.2 Basis of design
1.2.1 Design life. The design life is to be defined by the designer,
however, it is recommended that the design life be at least 60 years.
1.2.2 Water density. The water density is to be specified by the
designer based on the intended operation of the dock gate. Where the water density
is not known, it is to be taken as 1,025 t/m3.
1.3 Types of dock gate
1.3.1 Floating dock gate. A floating dock gate consists of a large
floating steel box which is ballasted to seat the dock gate in the opening of the
dock. The dock gate is re-floated by de-ballasting and is then towed clear of the
entrance to the dry dock. Floating dock gates can also be hinged at the side of the
dock. See
Figure 2.1.1 Floating dock gate.
1.3.2 Sliding and rolling dock gate. A floating or sliding dock gate
consists of a narrow rectangular box which is opened by moving the gate into a
recess in the side of the entrance. The dock gate is lightly ballasted so that it
can be moved on a track or slid into the recess. See
Figure 2.1.2 Rolling or sliding dock gate.
1.3.3 Mitre gates. Mitre gates are a pair of hinged gates which form a
‘V’ shape with the greater hydrostatic pressure being on the outside of the V and
hence holding the gates closed. See
Figure 2.1.3 Mitre gate.
1.3.4 Flap gates. Flap gates are hinged at the bottom in way of the
entrance sill of a dock and are opened by being lowered down into the water so that
they lie flat on the seabed below the entrance sill. Buoyancy tanks are often used
in conjunction with hydraulic rams or winches to lower the gate. See
Figure 2.1.4 Flap gate.
1.4 Materials
1.4.1 These Rules relate to the construction of welded steel dock gates.
1.4.2 The materials used in the construction of the dock gate are to be
manufactured and tested in accordance with the requirements of the Rules for the Manufacture, Testing and Certification of Materials, July 2022. Materials for which provision is not made therein may
be accepted, provided that they comply with an approved specification and such tests
as may be considered necessary.
1.4.3 Steel having a specified minimum yield stress of 235 N/mm2 is
regarded as mild steel. Steel having a higher specified minimum yield stress is
regarded as higher tensile steel.
1.4.4 For the determination of the hull girder section modulus, where higher
tensile steel is used, a higher tensile steel factor, kL, is given
in Pt 2, Ch 2, 1.4 Materials 1.4.4.
Table 2.1.1 Values of kL
Specified
minimum yield stress in N/mm2
|
kL
|
235
|
1,0
|
265
|
0,92
|
315
|
0,78
|
355
|
0,72
|
390
|
0,68
|
Note Intermediate values by linear interpolation
|
1.4.5 The local scantling requirements of higher tensile steel plating,
longitudinals, stiffeners and girders can be based on a k factor determined
as follows:
or 0,66, whichever is the greater.
where
σo |
= |
specified minimum yield stress in N/mm2. |
1.4.7 Consideration will be given to the use of bolted connections within the dock gate
main structure. Such bolted connections are to comply with the requirements of
Eurocode 3, Part 1-8. All bolts used for primary connections are to be high strength
friction grip bolts. For normal operating load scenarios, the bolts are to be
designed to be non-slip. Under extreme loading conditions (including seismic), the
bolts can be designed on the basis of their ultimate shear strength.
1.5 Plans and information required
1.5.1 A document describing the full operational cycle of the dock gate including repair
and maintenance is to be submitted.
1.5.2 The full range of environmental operating conditions is to be defined,
including:
- Highest and lowest astronomical tides (HAT and LAT) for the
site location and the associated return period.
- Maximum and operational significant wave heights and periods
and directions associated with a 60-year return period for the site. Information
is also to include the effects of waves from passing marine craft.
- Maximum current speeds and directions at site including the
effects of ships' propulsion units.
- Seabed conditions and likelihood of silting in vicinity of
site.
- The anticipated effects of passing marine craft at site.
- For areas subject to sub-zero temperatures the lowest mean
daily average temperature (MDAT) for the location is to be submitted.
- Extreme snow and ice loading.
- Foreseeable accident events are to be defined including
collision, grounding, and degradation
- Seismic conditions where appropriate.
1.5.3 Operational data is to be provided including;
- Vehicle loading data on ramps and decks.
- Design uniformly distributed loadings.
- Loads imposed by tugs or berthing.
- Passenger/pedestrian loadings.
- Docking arrangements.
- Ballasting and de-ballasting sequence where
appropriate.
- Design air pressures where compressed air is used for
ballasting or de-ballasting operations.
- Any other loadings not specified above.
1.5.4 The following plans are to be submitted for approval:
- General arrangement plan.
- Section at mid-length.
- Structural plans of tank boundaries (if any).
- Structural plan of shell including bottom of dock gate or
pontoons (if applicable).
- Structural plans of bulkheads and pillars.
- Structural plans of deck/walkway/roadway.
- Structural plans of ramps.
- Welding and construction details.
- Material grades.
- Mooring and towing attachments and seats.
- Sealing arrangement.
- Air pipes and discharges.
- Corrosion prevention arrangements.
- Hydrostatic curves.
1.5.5 The critical joints and critical weld connections are to be shown on the structural
plans.
1.6 Data required
1.6.1 In addition to the requirements of Pt 2, Ch 2, 1.5 Plans and information required, the
following is to be submitted:
- Dock gate lightweight.
- The total lightweight should be sub-divided into weights
of:
- pontoon or dock gate or walls;
- wing walls above pontoon/dock gate dock level;
- supporting blocks;
- machinery and outfit;
- end aprons/working platforms; and
- deck roadway surfacing where appropriate.
- Depth of water in dock.
- Proposed distance of air pipe openings below the safety deck
inside tanks and/or the pontoon deck in centre tanks, as applicable.
- The hydrostatic head assumed for the design of boundary
bulkheads separating adjacent ballast tanks, to be taken as the maximum
allowable difference between the filling levels of adjacent ballast tanks. This
head should be included in the dock operating instructions. If not specified, it
will be taken as 3,5 m.
- The hydrostatic head obtained from Hydrostatic Curves to be
used for structural design of dock boundary bulkheads and internal bulkheads
which separate a ballast tank from a dry space.
- Section modulus calculation.
- Global strength calculations.
- NDE plan showing the critical joints and critical welds.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
 |
|