5.2.2 The generating
and distribution system is to be so arranged that after any single
failure, steering capability can be maintained or regained immediately,
and the effectiveness of the steering after such a fault will not
be reduced by more than 50 per cent. This may be achieved by the parallel
operation of two or more generating sets, or alternatively when the
electrical requirements may be met by one generating set in operation,
on loss of power, the automatic starting and connection to the switchboard
of a standby set, provided that this set can restart and run a thruster
with its auxiliaries.
5.2.3 The failure
of one thruster unit or its control system is not to render any other
thruster inoperative.
5.2.4 A single
failure of generator/switchboard should not lead to failure of any
other generator/switchboard.