Section
1 General welding requirements
1.1 Scope
1.1.1 This Chapter
specifies requirements for fabrication and welding during construction
and repair of ships or other marine structures, and their associated
pressure vessels, machinery, equipment, components and products intended
for use in these structures.
1.1.3 The requirements
relate to fusion welding. Special consideration will be given to the
use of other welding processes based on these requirements.
1.1.4 It is the
responsibility of the manufacturer to ensure compliance with all aspects
of these Rules and inform the Surveyor of any deviations that have
occurred. All deviations are to be recorded as non-compliances along
with the corrective actions taken and failure to do this is considered
to render the fabrication to be in non-compliance with the Rules.
1.1.5 Welded constructions
that comply with National or International specifications may be accepted
to the satisfaction of the surveyor, provided that these specifications
give reasonable equivalence to the requirements of this Chapter.
1.1.6 All welded
construction is to be to the satisfaction of the Surveyor.
1.2 Design
1.2.1 Prior to
commencing any work, the component to be manufactured is to be subjected
to design review and approval in accordance with the Rule requirements.
1.2.2 The material
characteristics that are affected by welding, particularly the loss
of strength (e.g. in precipitation or strain hardened aluminium alloys)
are to be considered in the design. The weld joints in such materials
are to be arranged such that they are in areas of lower stress.
1.3 Materials
1.3.1 Materials
used in welded construction are to be manufactured at works approved
by LR. The use of materials from alternative sources will be subject
to agreement of the Surveyor and satisfactory verification testing.
1.3.3 Materials
used in welded construction are to be readily weldable and are to
have proven weldability, unless requirements are agreed with LR in
advance.
1.3.5 When ordering
materials for construction, consideration is to be taken of the possible
degradation of properties during fabrication or post-weld heat treatment.
Where these materials are used, consideration is to be given to additional
test requirements being specified to the supplier.
1.3.6 The identity
of materials is to be established by way of markings etc, during fabrication,
so that traceability to the original manufacturer’s certificate
is maintained.
1.3.7 Pre-fabrication
shop primers may be applied prior to welding, provided that they are
of an approved type and have been tested to demonstrate that they
have no deleterious effects on the completed weld.
1.3.8 Where it
is proposed to weld forgings and/or castings, full details of the
joint details, welding procedures and post-weld heat treatments are
to be submitted for consideration.
1.4 Requirements for manufacture and workmanship
1.4.2 Where structural
components are to be assembled and welded in works sub-contracted
by the builder, the Surveyor is to inspect the sub-contractor’s
works to ensure that compliance with the requirements of this Chapter
is achieved.
1.4.3 The manufacturer
is to provide a system of regular supervision of all welding, by suitably
qualified and experienced personnel.
1.4.4 Welding
is to be performed in covered workshops as far as practicable. Where
this is not possible, provision is to be made in the welding area
to give adequate protection from wind, rain and cold, etc.
1.4.5 Where required,
arrangements are to be such as to permit adequate ventilation and
access for preheating, and for the satisfactory completion of all
welding operations.
1.4.6 The location
of welding connections and sequences of welding are to be arranged
to minimise distortion and the build up of residual stresses. Welded
joints are to be so arranged as to facilitate the use of downhand
welding wherever possible.
1.4.7 In the case
of repairs to existing structures or components, care is to be exercised
when attaching fit-up aids by welding to ensure that the base materials
in way of the attachments are of weldable quality.
1.5 Cutting of materials
1.5.1 Materials
may be cut to the required dimensions by thermal means, shearing or
machining in accordance with the manufacturing drawings or specifications.
1.5.2 Cold shearing
is not to be used on materials in excess of 25 mm thick. Where used,
the cut edges that are to remain un-welded are to be cut back by machining
or grinding for a minimum distance of 3 mm.
1.5.3 Material,
which has been thermally cut, is to be free from excessive oxides,
scale and notches.
1.5.4 All cut
edges are to be examined to ensure freedom from material and/or cutting
defects. Visual examination may be supplemented by other techniques.
1.5.5 Thermal
cutting of alloy and high carbon steels may require the application
of preheat, and special examination of these cut edges will be required
to ensure no cracking. In these cases, the cut edge is to be machined
or ground back a distance of at least 2 mm, unless it has been demonstrated
that the cutting process has not damaged the material.
1.5.6 Any material
damaged in the process of cutting is to be removed by machining, grinding
or chipping back to sound metal. Weld repair may only be performed
with the agreement of the Surveyor.
1.6 Forming and bending
1.6.1 Plates,
pipes, etc. may be formed to the required shape by any process which
does not impair the quality of the material.
1.6.2 Where hot forming is employed the manufacturer is required to demonstrate
that the forming procedure is compliant with a recognised National or International
Standard or shall demonstrate by appropriate qualification tests that the material
properties remain acceptable in the ‘as formed’ condition.
1.6.3 Materials that are cold formed, such that the permanent strain exceeds 10 per cent, or
formed to a diameter to thickness ratio less than 10, are to be subjected to a
subsequent softening heat treatment in accordance with the material manufacturers
recommendations, unless it is demonstrated by testing that the material properties are
acceptable in the ‘as formed’ condition.
1.6.4 As far as
practicable, forming is to be performed by the application of steady
continuous loading using a machine designed for that purpose. The
use of hammering, in either the hot or cold condition is not to be
employed.
1.6.5 Material
may be welded prior to forming or bending, provided that it can be
demonstrated that the weld mechanical properties are not impaired
by the forming operation. All welds subjected to bending are to be
inspected on completion to ensure freedom from surface breaking defects.
1.7 Assembly and preparation for welding
1.7.1 Excessive
force is not to be used in fairing and closing the work. Where excessive
root gaps exist between surfaces or edges to be joined, corrective
measures are to be adopted.
1.7.2 Provision
is to be made for retaining correct alignment during welding operations
in accordance with the approved manufacturing specifications and welding
procedures.
1.7.3 Tack welds
are to be avoided as far as practicable. When used, tack welds are
to be of the same quality as the finished welds, made in accordance
with approved welding procedures, and where they are to be retained
as part of the finished weld, they are to be clean and free from defects.
1.7.4 Generally,
tack welds are not to be applied in lengths of less than 30 mm for
mild steel grades and aluminium alloys, and 50 mm for higher tensile
steel grades. Smaller tack welds may be accepted for steels, provided
that the carbon equivalent of the materials being welded is not greater
than 0,36 per cent.
1.7.5 Where deep
penetration welding is used (see
Ch 13, 2.4 Construction and workmanship 2.4.6), welding procedure tests are
to demonstrate that the specified degree of penetration is achieved
in way of tack welds left in place.
1.7.6 Where temporary
bridge pieces or strong-backs are used, they are to be of similar
materials to the base materials and welded in accordance with approved
welding procedures.
1.7.7 Any fit-up
aids and tack welds, where welded to clad materials, are to be attached
to the base material and not to the cladding.
1.7.8 Surfaces
of all parts to be welded, are to be clean, dry and free from rust,
grease, debris and other forms of contamination.
1.7.9 When misalignment
of structural members either side of bulkheads, decks etc. exceeds
the agreed tolerance, the misaligned item is to be released, realigned
and rewelded in accordance with an approved procedure.
1.8 Welding equipment and welding consumables
1.8.1 Welding
plant and equipment is to be suitable for the purpose intended and
properly maintained, taking into account relevant safety precautions.
1.8.2 Suitable
means of measuring the welding parameters (i.e. current, voltage and
travel speed) are to be available. Electrical meters are to be properly
maintained and have current calibrations.
1.8.3 Welding
consumables are to be suitable for the type of joint and grade of
material to be welded, and in general, are to be LR Approved in accordance
with Ch 11 Approval of Welding Consumables.
1.8.4 Special
care is to be taken in the distribution, storage and handling of all
welding consumables. They are to be kept in heated dry storage areas
with a relatively uniform temperature in accordance with the consumable
manufacturer’s recommendations. Condensation on the metal surface
(e.g. wire electrodes and studs) during storage and use is to be avoided.
1.8.5 Prior to
use, welding consumables are to be dried and/or baked in accordance
with the consumable manufacturer’s recommendations.
1.8.6 Satisfactory
storage and handling facilities for consumables are to be provided
close to working areas and the condition of welding consumables are
to be subject to regular inspections.
1.9 Welding procedure and welder qualifications
1.9.1 Welding
procedures are to be developed by the manufacturer for all welding,
include weld repairs, and are to be capable of achieving the mechanical
property requirements and non-destructive examination quality appropriate
to the work being undertaken.
1.9.2 Welding
procedures are to be established for the welding of all joints and
are to be qualified by testing in accordance with Ch 12 Welding Qualifications. The welding procedures are to give details of the
welding process, type of consumable, joint preparation, welding position
and filler metals to be used.
1.9.3 The proposed
welding procedures are to be approved by the Surveyor prior to construction.
1.9.4 All welders
and welding operators are to be qualified in accordance with the requirements
of Ch 12 Welding Qualifications. Qualification records
to demonstrate that welding personnel have the skills to achieve the
required standard of workmanship are to be available to the Surveyor.
1.10 Welding during construction
1.10.1 Materials
to be assembled for welding are to be retained in position by suitable
means such that the root gaps and alignment are in accordance with
the approved manufacturing specifications and welding procedures.
1.10.2 Surfaces
of all parts to be welded, are to be clean, dry and reasonably free
from rust, scale and grease.
1.10.3 Pre-heat
is to be applied, as specified in the approved welding procedure,
for a distance of at least 75 mm from the joint preparation edges.
The method of application and temperature control are to be such as
to maintain the required level throughout the welding operation.
1.10.4 When the
ambient temperature is 0°C or less, or where moisture resides
on the surfaces to be welded, due care is to be taken to pre-heat
the joint to a minimum of 20°C, unless a higher pre-heat temperature
is specified.
1.10.5 Where
tack welds are to be removed from the root of the weld joint, this
is to be carried out such that the surrounding material and joint
preparation is not damaged.
1.10.6 The welding
arc is to be struck on the parent metal which forms part of the weld
joint or on previously deposited weld metal.
1.10.7 Where
the welding process used is slag forming (e.g. manual metal arc, submerged
arc, etc.) each run of deposit is to be cleaned and free from slag
before the next run is applied.
1.10.8 Full penetration
welds are to be made from both sides of the joint as far as practicable.
Prior to welding the second side, the weld root is to be cleaned,
in accordance with the requirements of the approved welding procedure,
to ensure freedom from defects. When air-arc gouging is used, care
is to be taken to ensure that the ensuing groove is slag and oxide
free and has a profile suitable for welding.
1.10.9 Where
welding from one side only, care is to be exercised to ensure the
root gap is in accordance with the approved welding procedure and
the root is properly fused.
1.10.10 Particular
care is to be exercised in welding in the vertical position with direction
of travel downward (Vd) to avoid welding defects. The use of solid
wire gas metal arc (GMAW) process in the vertical down position is
to be avoided.
1.10.11 Welding
is to proceed systematically with each welded joint being completed
in correct sequence without undue interruption.
1.10.12 After
welding has been stopped for any reason, care is to be taken in restarting
to ensure that the previously deposited weld metal is thoroughly cleaned
of slag and debris, and preheat has been re-established.
1.10.13 Care
is to be taken to avoid stress concentrations such as sharp corners
or abrupt changes of section, and completed welds are to have an even
contour, blending smoothly with the base materials. The weld shape
and size is to be in accordance with that specified in the approved
drawings or specifications.
1.10.14 Welded
temporary attachments used to aid construction are to be removed carefully
by grinding, cutting or chipping. The surface of the material is to
be finished smooth by grinding followed by crack detection.
1.10.15 Where
fabricated and welded components require to be machined, all major
welding operations are to be completed prior to final machining.
1.10.16 Welding
to parts which are subjected to rotating fatigue (e.g. shafts) is
not generally permitted.
1.10.17 Welding
onto parts that have been hardened for wear resistance or strength
(e.g. gear teeth) is not permitted.
1.10.18 Where
welding of clad ferritic steel plates is to be undertaken, the clad
materials are to be ground back from the prepared edge by at least
10 mm. In general, the ferritic materials are to be welded prior to
welding of the cladding material.
1.11 Non-destructive examination of welds
1.11.1 Non-destructive examinations are to be made in accordance with approved
written procedures and shall comply with the general NDE requirements as per of the
Ch 1, 5 Non-destructive examination.
1.11.3 Effective arrangements are to be provided by the manufacturer for the
inspection of finished welds to ensure that all welding, and where necessary, all
post-weld heat treatment, has been satisfactorily completed.
1.11.4 Welds are to be clean and free from paint at the time of visual inspection
unless specified otherwise in the following Sections.
1.11.5 The weld surface finish is to ensure accurate and reliable detection of
defects. Where the weld surface is irregular or has other features likely to interfere
with the interpretation of non-destructive examination, the weld is to be ground or
machined.
1.11.6 Prior to inspection, welded temporary attachments and lifting eyes used to
aid construction are to be removed carefully by grinding, cutting or chipping or other
approved means. The surface of the material is to be finished smooth by grinding
followed by crack detection. Any defects caused in the removal process are to be
repaired and re-inspected.
1.11.7 For welds in steels with specified yield strength less than 420
N/mm 2, and with carbon equivalent less than or equal to 0,41 per cent, NDE
may be performed as soon as the test assembly has cooled to ambient temperature. For the
steels shown in Table 13.1.1 Cooling times prior to
non-destructive examination the following cooling times are to be observed prior to the
application of non-destructive examination to completed welding.
Table 13.1.1 Cooling times prior to
non-destructive examination
Type of steel
|
Cooling time prior to applying NDE
(after all welds have
reached ambient temperature and after any applicable post-weld heat
treatment)
|
Specified yield strength < 420 N/mm2 and CE ≤ 0,41
|
On
welded structure reaching ambient temperature
|
420
N/mm2 ≤ Specified yield strength ≤ 690
N/mm2
|
Not
before 48 hours after completion of welding
|
Specified yield strength > 690 N/mm2
|
Not
before 72 hours after completion of welding
|
Note 1. At the
discretion of the Surveyor, the 72 hour interval may be reduced to 48
hours for radiographic or ultrasonic inspection, provided there is no
indication of delayed cracking, and a complete visual and random
magnetic particle or penetrant inspection to the satisfaction of the
Surveyor is conducted 72 hours after welds have been completed and
cooled to ambient temperature.
Note 2. Regardless
of yield strength, consideration is to be given to requiring a delayed
inspection where evidence of delayed cracking has been observed in
production welds.
Note 3. At the
discretion of the Surveyor, a longer interval and/or additional random
inspection at a later period may be required, for example, in case of
high thickness welds.
|
1.11.8 Non-destructive examinations are to be performed in accordance with the
requirements of the Rules. Examinations are to be in accordance with agreed written
procedures prepared by the manufacturer or ship builder.
1.11.9 The Surveyor may request additional inspections where there is reason to
question the quality of workmanship, or where the weld is part of a complicated
fabrication where there is high restraint or high residual stresses.
1.11.10 Welds are to be examined after completion of any post-weld heat
treatment.
1.11.11 Where weld defects are discovered, the full extent is to be ascertained by
applying additional non-destructive examinations where required. Unacceptable defects
are to be completely removed and, where necessary, weld repaired in accordance with the
relevant Sections of this Chapter. The repairs are to be re-inspected using the same
technique as the original inspection.
1.11.12 Results of non-destructive examinations are to be recorded and evaluated by
the constructor on a continual basis in order that the quality of welding can be
monitored. These records are to be available to the Surveyor.
1.11.13 The constructor is to be responsible for the review, interpretation,
evaluation and acceptance of the results of NDE. Reports stating compliance or otherwise
with the criteria established in the inspection procedure are to be issued. Reports are
to comply, as a minimum, with the requirements of Ch 1, 5 Non-destructive examination.
1.11.14 The extent of applied non-destructive examination is to be increased when
warranted by the analysis of previous results.
1.11.15 Ultrasonic testing of welds in austenitic and duplex stainless steels
requires specific procedures, appropriately qualified personnel and suitable equipment
including angle-compression wave and creep wave probes, in addition to the above
requirements.
1.11.16 In general, start/stop points in welds made using automatic welding
processes (i.e. welding in which all welding operations are performed without welding
operator intervention during the process and manual adjustment of welding parameters by
the welding operator is not possible) or fully mechanised welding processes, these are
to be examined using radiographic or ultrasonic inspection, except for internal members
where the extent of testing is to be agreed with the Surveyor.
1.11.17 Consideration may be given for a reduction in inspection frequency for welds where
volumetric inspection and the quality assurance techniques applied indicate satisfactory
quality.
1.11.18 Where the Surveyor becomes aware that an NDE location has been repaired without a record
of the original defect, the shipyard is to carry out additional examinations on areas
adjacent to the repaired area, to the satisfaction of the Surveyor.
1.11.19 Where PWHT is carried out the requirement for testing after a delay period may be
relaxed, at the discretion of the Surveyor.
1.12 Routine weld tests
1.12.1 Routine
or production weld tests may be specified as a means of monitoring
the quality of the welded joints. This type of quality control test
is generally specified for pressure vessel and LNG construction but
may be used for other types of welded fabrication.
1.12.2 Routine
weld tests may be requested by the Surveyor where there is reason
to doubt the quality of workmanship.
1.13 Rectification of material defects
1.13.1 Repair
of defects found in base materials is not to be carried out without
the prior approval of the Surveyor.
1.13.2 In general,
surface defects in the material may be removed by grinding, chipping,
etc. provided the remaining material thickness is not reduced below
the minimum thickness tolerance, and the area is ground to blend in
smoothly with the surrounding material.
1.13.3 Confirmation
that the defect has been removed is required by performing visual
examination, augmented by either magnetic particle or dye penetrant
examination techniques.
1.13.5 Any defects
in the structure resulting from the removal of temporary attachments
are to be prepared, efficiently welded and ground smooth so as to
achieve a defect free repair.
1.14 Rectification of distortion
1.14.1 Fairing,
by linear or spot heating, to correct distortions due to welding,
may be carried out. In order to ensure that the properties of the
material are not adversely affected, approved procedures are to be
utilised. On completion of such processes, visual examination of all
heat affected areas in the vicinity is to be carried out to ensure
freedom from cracking.
1.14.2 When misalignment
of members exceeds the agreed tolerance, the misaligned item is to
be cut apart, realigned and re-welded in accordance with an approved
procedure.
1.15 Rectification of welds defects
1.15.1 Where repairs are extensive the manufacturer is to investigate the reason
for the defects and take the necessary actions to prevent recurrence. In addition,
consideration is to be given to the sequence of repairs and to providing temporary
supports to prevent misalignment or collapse. When unacceptable indications are found,
additional areas of the same weld length are to be examined unless it is agreed with the
Surveyor and the manufacturer that the indication is verified as being isolated.
1.15.2 Cracks
are to be reported to the Surveyor and the cause established prior
to undertaking weld repairs.
1.15.3 Defects
may be removed by grinding, chipping or thermal gouging. Where thermal
gouging is used, the repair groove is to be subsequently ground clean
to remove oxides and debris. The groove is to have a profile suitable
for welding.
1.15.4 Prior
to commencing repair welding, it is to be confirmed that no defect
exists on the prepared surface by performing visual examination, augmented
by either magnetic particle or dye penetrant examination techniques.
1.15.5 Repair
welding is to be performed using approved welding procedures.
1.15.6 Completed
repairs are to be re-examined by the non-destructive examination method(s)
that detected the original defect and are to confirm that the original
defect has been removed.
1.15.7 Where
the component or structure has been subjected to post-weld heat treatment
prior to weld repair, this is to be repeated after completion of all
repair welding.
1.15.8 Where
non-destructive examination reveals that the original defect has not
been successfully removed, one more repair attempt may be performed.
1.15.9 The manufacturer
is to monitor the quality of welding and maintain records of welding
repairs and take the necessary corrective actions where repair rates
are outside normal limits.
1.15.10 All radiographs exhibiting non-conforming indications are to be brought to the attention
of the Surveyor, and such welds are to be repaired and re-inspected as required by the
procedures and the test plans. When non-conforming indications are observed at the end
of the radiograph, additional radiographic inspection will generally be required to
determine their extent. As an alternative measure, the manufacturer may, upon agreement
with the Surveyor, excavate and repair the affected welds to fully determine the extent
of defects.
1.15.11 The manufacturer is to monitor and record the repair rate and take such corrective
actions as are required and identified by the Quality Assurance system.
1.16 Post-weld heat treatment
1.16.1 On completion
of welding, post-weld heat treatment may be required depending on
the type of welded construction, the material type and thickness as
specified by the relevant Parts or Sections of the Rules.
1.16.2 In general,
heat treatment after welding is to be a stress relief treatment in
order to reduce residual stresses introduced by welding and is generally
applicable to ferritic steels. Where other types of heat treatment
(e.g. normalising, solution annealing) are proposed, demonstration
of acceptable mechanical properties of the weldment are to be confirmed
by a welding procedure test which includes a simulated heat treatment.
1.16.3 Parts
are to be properly prepared for heat treatment. Machined surfaces
(e.g. flange faces, screw threads, etc.) are to be protected against
scaling and sufficient temporary supports provided to prevent distortion
or collapse of the structure.
1.16.4 Details
of the heat treatment to be applied, soaking time and temperature,
heating and cooling rates, etc. are to be submitted for review prior
to commencing.
1.16.5 Post-weld
heat treatment is to be carried out in a purpose built furnace which
is efficiently maintained. In special cases, where the configuration
of the component is such that thermal stresses during heating and
cooling can be minimised, local post-weld heat treatment may be used.
This would not normally apply to the complex geometry of cast materials
during manufacture within the foundry environment.
1.16.6 In all
cases, the heat treatment facilities and arrangements are to be capable
of controlling the temperature throughout the heat treatment cycle
and adequate means of measuring and recording the component temperature
are to be provided. Thermocouples are to be attached so they are in
contact with the component.
1.16.7 Unless
specified otherwise, stress relief heat treatment is to be carried
out by means of controlled heating from 300°C, to the soak temperature,
holding within the prescribed soaking temperature range for the time
specified (usually 1 hour per 25 mm of weld thickness) followed by
controlled cooling to below 300°C.
1.16.8 Where
post-weld stress relief is specified for welded constructions that
contain joints between different materials (e.g. ferritic to austenitic
steels), the details of the materials, welding procedures and heat
treatment cycle to be applied are to be submitted for special consideration
and approval.
1.16.9 Non-destructive
examination of welds is to be performed after completion of any heat
treatment.
1.17 Certification
1.17.1 Products
or components are not to be considered complete until all the requirements
of the construction specification have been met and all activities
have been completed.
1.17.2 Upon completion
of the works, the manufacturer is to provide documentation which indicates
that:
-
All welds are complete
and there are no outstanding repairs.
-
The appropriate post-weld
heat treatments have been performed.
-
Appropriate destructive
tests have been performed.
-
Proof testing of
welds has been performed.
1.17.3 Before
the test certificates or shipping statements are signed by the Surveyor,
the manufacturer is required to provide a written declaration stating
that the product is in accordance with the requirements of Ch 13, 1.17 Certification 1.17.2.
|