Section
13 Single pass loading
13.1 Scope and application
13.1.1 The
requirements of this Section are to be applied to all ore carriers
with a deadweight greater than 200 000 tonnes. The requirements are
for single pass loading where the maximum permissible cargo intake
per cargo hold may be loaded in a single loading pour.
13.1.2 Where the requirements of this Section have been complied with, then, on application
from the Owners, the descriptive note Single pass loading may be entered in
column 6 of the Register Book, see
Pt 1, Ch 2, 2.8 Descriptive notes.
13.2 Information required
13.2.2 The
cargo loading sequences as required by Pt 4, Ch 11, 13.2 Information required 13.2.1.(c) are to include the
following:
-
Start and end
times of each cargo pour and the intended loading rate.
-
Start and end
times of each deballasting operation and the intended discharge rate.
-
Intermediate
points (in time) during pours and between pours. In general, the interval
between intermediate points is not to be greater than 1 hour.
-
The ship’s
loading condition, including the ship’s draughts at the fore
and aft perpendiculars, amount of cargo in each hold and amount of
ballast in each tank, and the still water bending moments and shear
forces, are to be provided for each point (in time) of the loading
operation specified in Pt 4, Ch 11, 13.2 Information required 13.2.2, Pt 4, Ch 11, 13.2 Information required 13.2.2.(b) and Pt 4, Ch 11, 13.2 Information required 13.2.2.(c).
13.3 Definitions
13.3.1
Pour. A pour is defined by the start and finish of loading of a
cargo hold. A pour finishes when the loading equipment changes position
to a new cargo hold.
13.3.2
Overshooting. Overshooting is to be taken as the consequence of mistiming
the loading of cargo, resulting in cargo overloading.
13.4 Cargo loading conditions for design assessment
13.4.1 For
the purpose of the design assessment, the following conditions are
assumed:
-
Cargo loading
and deballasting operations are coordinated, with the deballast capacity
and arrangement of the vessel designed to accommodate the specified
loading sequences.
-
The cargo is
distributed symmetrically in a hold space.
-
Deballasting
is carried out for each pair of symmetrical port and starboard tanks
simultaneously, so that each pair of symmetrical port and starboard
ballast tanks contain equal amounts of water ballast throughout deballasting
operations.
-
To improve deballasting
and stripping, the trim of the ship is to be, in general, by the stern
throughout the cargo loading operation.
-
A cargo overshoot
per cargo hold is taken as 10 per cent of the maximum permissible
hold cargo mass or 3000 tonnes, whichever is the lesser, but not less
than 5 per cent of the maximum permissible hold cargo weight, in any
case. A higher cargo overshoot may be specially considered.
-
Loading more
than one cargo hold simultaneously in a single pass, i.e. simultaneous
filling of two or more holds, will be specially considered. The specific
loading conditions are to be submitted for appraisal in addition to
the condition(s) for standard single-pass loading.
13.5 Design assessment
13.5.1 The
following criteria are to be complied with in all cargo loading sequences:
-
Still water
bending moment and shear force are within the allowable limits.
-
Single hold
loading is within the allowable hold mass curve.
-
Two adjacent
holds loading are within the allowable hold mass curve.
13.5.3 The
primary structure and plating within the cargo hold region are to
be assessed in accordance with the ShipRight SDA Procedure for
Ore Carriers.
13.6 Ballast arrangements
13.6.1 The
deballasting capacity of the vessel, including arrangement of ballast
tanks, pumps and relevant piping system, is to be sufficient for the
loading operations as agreed in the approved loading plan.
13.6.2 A
smaller diameter stripping system with separate main and branch lines
may need to be provided in order to achieve the required deballasting
capacity.
13.7 Loading manual
13.7.1 All
loading sequences of single pass loading, maximum loading rates and
ballast pumping details are to be submitted for approval and included
in the Loading Manual. Loading conditions at intermediate points as
described in Pt 4, Ch 11, 13.2 Information required 13.2.2.(c) need
not be included in the Loading Manual.
13.8 Loading computer
13.8.1 The
ship is to be installed with sensors for remote measurement of water
ballast, fuel oil and ship’s draughts.
13.8.2 In
addition, it is recommended that an interface with the onboard loading
computer, connecting to the installed sensors detailed in Pt 4, Ch 11, 13.8 Loading computer 13.8.1, is to be provided to check
the ship’s condition during loading and unloading.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
![](LR-FooterLogo.png) |
|