8.1.3 Chemical
injection lines, concentrated treatment injection lines, inert gas
injection lines and sampling point are to be of a rigid construction
and be properly supported.
8.1.4 Risk of leakage from degassing equipment is to be prevented. Vent
arrangements are to be directed to an area on open deck with no ignition hazard.
8.1.5 Degassing equipment shall be made of a suitable material. Non-metallic materials may be
allowed for components inside degassing equipment subjected to special consideration.
8.1.6 Degassing equipment shall be arranged to ensure any hydrogen present is at a
concentration less than the 4 per cent Lower Explosive Limit (LEL) before venting.
Failure of such arrangement is to activate BWTS shutdown.