Section
11 Factory Acceptance Test and Shipboard Trials of Internal Combustion Engines
11.1 Safety
11.1.1 Before any test run is carried out, all relevant equipment for the safety of
attending personnel is to be made available by the manufacturer/ shipyard and is to
be operational. This is to include crankcase explosive conditions protection,
overspeed protection and any other shutdown function.
11.1.2 The overspeed protective device is to be set to a value which is not higher than the
overspeed value that was demonstrated during the type test for that engine. This set
point is to be verified by the Surveyor.
11.2 General
11.2.1 Engines which are to be subjected to trials on the test bed at the
manufacturer’s works and under attendance by the Surveyor(s) are to be tested in
accordance with the scope of works trials specified in Vol 2, Pt 2, Ch 1, 11.3 Works trials (factory acceptance test). The scope of the trials is to be agreed between
the LR Surveyor and the manufacturer prior to testing.
11.2.2 Where multiple engines of the same design are manufactured, a quality
assurance approach to approval may be applied if the manufacturer meets the
requirements of and is registered on the Quality Assurance Scheme for Machinery
(QAM), see
Vol 2, Pt 2, Ch 1, 10 Safety arrangements.
11.2.3 Before any official testing the engines are to be run in as prescribed by the engine
manufacturer.
11.2.4 Adequate test bed facilities for loads as required in Table 1.11.1 Scope of works trials for
engines are to be provided. All fluids used for testing
purposes such as fuel, lubrication oil and cooling water are to be suitable for the
purpose intended, e.g. they are to be clean and if necessary, pre-heated to achieve
the recommended operating temperature. This applies to all fluids used temporarily
or repeatedly for testing purposes only.
11.2.5 Survey of the engine is to include:
- Jacketing of high-pressure fuel oil lines including the system used for the
detection of leakage.
- Screening of pipe connections in piping containing flammable liquids.
- Insulation of hot surfaces by taking random temperature readings that are to
be compared with corresponding readings obtained during the type test. This
is to be done while running at the maximum approved rating for the actual
application. Use of contact thermometers may be accepted at the discretion
of the attending Surveyor. If the insulation is modified subsequently to the
Type Approval Test, LR may request more enhanced temperature measurements as
required by the LR’s Type Approval Test Specification No. 4, Chapter 2,
1.3.10 (Fire Protection Measures).
These surveys are normally to be made during the works trials by the manufacturer and
the attending Surveyor, but at the discretion of LR parts of these surveys may be
postponed to the shipboard testing.
11.2.6 Where the type test was not carried out on the complete engine, as
described in Vol 2, Pt 2, Ch 1, 1.2 Scope 1.2.2, integration tests are
to be conducted as part of the works or shipboard trials to confirm satisfactory
operation of the complete engine. This includes satisfactory functioning on all fuel
types on which the engine is to operate. See also
Vol 2, Pt 2, Ch 1, 11.4 Shipboard trials 11.4.6.
11.3 Works trials (factory acceptance test)
11.3.1 The purpose of the works trials is to verify design parameters such as
power, adherence to approved limits (e.g. maximum pressure) and functionality, and
to establish reference values or base lines for later reference in the operational
phase.
11.3.2 During testing the environmental conditions are to be recorded, including ambient air
temperature, ambient air pressure and atmospheric humidity.
11.3.3 For each load point the parameters to be recorded include: power and
speed; fuel index (or equivalent reading); maximum combustion pressures; exhaust gas
temperature before turbine and from each cylinder (or from manifold, see Note
5 in Table 1.7.1 Engines for propulsion purposes:
Alarms and slow-downs); charge air temperature and pressure; and turbocharger
speed (only for category B and C turbochargers).
11.3.4 For all stages of the works trials the pertaining operation values are
to be measured and recorded by the engine manufacturer. All results are to be
compiled in an acceptance protocol to be issued by the engine manufacturer. Where
the engine designer requires through life monitoring of crankshaft deflections, such
measurements are also to be taken before and after works acceptance trials in
accordance with the engine designer’s requirements.
11.3.5 In each case given in Table 1.11.1 Scope of works trials for
engines, all measurements conducted at the
various load points are to be carried out at steady operating conditions. The
readings for MCR, i.e. 100 per cent power (rated maximum continuous power at
corresponding rpm) are to be taken twice at an interval of at least 30 minutes. For
all load points provision should be made for time needed by the Surveyor to carry
out visual inspections.
11.3.6 Calibration records for the instrumentation are, upon request, to be
presented to the attending Surveyor.
Table 1.11.1 Scope of works trials for
engines
Main engines driving propellers and
waterjets
|
Trial condition
|
Duration
|
Note
|
100% power (rated power) at
rated engine speed, R
|
≥60 minutes
|
—
|
110% power at engine speed
corresponding to 1,032*R
|
15 minutes
|
Or after having reached steady
conditions, whichever is shorter, see Notes 1 and 4
|
Approved intermittent overload
(if applicable)
|
—
|
Testing for duration to be
agreed with the manufacturer
|
90% (or maximum continuous
power), 75%, 50% and 25%
|
—
|
Powers in accordance with the
nominal propeller curve, sequence to be selected by the manufacturer
|
Reversing manoeuvres (if
applicable)
|
—
|
—
|
Testing of governor and
independent overspeed protective device
|
—
|
See
Vol 2, Pt 2, Ch 1, 7 Control and monitoring of main, auxiliary and emergency engines
|
Shutdown device
|
—
|
See
Vol 2, Pt 2, Ch 1, 7 Control and monitoring of main, auxiliary and emergency engines
|
Engines driving generators for electric propulsion
or driving generators for auxiliary purposes
|
Trial condition
|
Duration
|
Note
|
100% power (rated power) at
rated engine speed, R
|
≥60 minutes
|
—
|
110% power
|
15 minutes
|
Or after having reached steady
conditions, see Note 2. For auxiliary engines, see
Note 1
|
75%, 50% and 25% power and idle
run
|
—
|
See Note 2
|
Start-up tests
|
—
|
—
|
Testing of governor and
independent overspeed protective device
|
—
|
See
Vol 2, Pt 2, Ch 1, 7 Control and monitoring of main, auxiliary and emergency engines
|
Shutdown device
|
—
|
See
Vol 2, Pt 2, Ch 1, 7 Control and monitoring of main, auxiliary and emergency engines
|
Propulsion engines driving power
take off (PTO) generator
|
Trial condition
|
Duration
|
Note
|
100%
power (rated power) at rated engine speed, R
|
≥60
minutes
|
—
|
110%
power
|
15
minutes
|
Or
after having reached steady conditions, see Note 3
|
Approved intermittent overload (if applicable)
|
—
|
Testing for duration to be agreed with the manufacturer
|
90%
(or normal continuous cruise power), 75%, 50% and 25%
|
—
|
For
variable speed engines. Powers in accordance with the nominal
propeller curve or at constant speed R, sequence to be
selected by the manufacturer
|
Engines driving mechanical
auxiliaries
|
Trial condition
|
Duration
|
Note
|
100%
power (rated power) at rated engine speed, R
|
≥30
minutes
|
—
|
110%
power
|
15
minutes
|
Or
after having reached steady conditions, see Note 1
|
Approved intermittent overload (if applicable)
|
—
|
Testing for duration to be agreed with the manufacturer
|
75%,
50% and 25%
|
—
|
For
variable speed engines. Powers in accordance with the nominal
propeller curve, sequence to be selected by the manufacturer
|
Note 1.After running
on the test bed, the fuel delivery system of main engines is
normally to be so adjusted that overload power cannot be given
in service unless intermittent overload power is approved by LR,
in which case the limit is to be adjusted to that power. The
setting of the restriction is to be made as applicable to the
intended fuel. Any restriction settings, and other changes to
the engine’s fuel injection equipment required for operation on
special fuels, are to be recorded and included by the engine
manufacturer.
Note 2. After
running on the test bed, the fuel delivery system of diesel
engines driving generators is to be adjusted so that full power
plus a 10 per cent margin for transient regulation can be given
in service after installation on board. The transient overload
capability is required so that the required transient governing
characteristics are achieved also at 100% loading of the engine,
and so that the protection system utilised in the electric
distribution system can be activated before the engine
stalls.
Note 3. After
running on the test bed, the fuel delivery system of propulsion
engines also driving power take off (PTO) generators is to be
adjusted so that full power plus a margin for transient
regulation can be given in service after installation on board.
The transient overload capability is required so that the
electrical protection of downstream system components is
activated before the engine stalls. This margin may be 10% of
the engine power but at least 10% of the PTO power.
Note 4. Only required once for each different engine/turbocharger
configuration.
|
11.3.7 Alternatives to the detailed tests may be agreed between the
manufacturer and LR when the overall scope of tests is found to be equivalent. The
scope of the trials may be expanded depending on the engine application, service
experience, or other relevant reasons.
11.3.9 For electronically controlled engines:
- integration tests in accordance with Vol 2, Pt 2, Ch 1, 1.4 Submission requirements 1.4.2; and
- verification of engine configuration, see
Vol 2, Pt 2, Ch 1, 4.3 Control engineering systems 4.3.2, and that the approved software quality
plans, including the software configuration management process, are to be
applied.
11.3.10 Checks of components to be presented for inspection after the works
trials are left to the discretion of the Surveyor.
11.4 Shipboard trials
11.4.1 The purpose of the shipboard testing is to verify compatibility with
power transmission and driven machinery in the system, safety, control and auxiliary
systems necessary for the engine and integration of engine/ shipboard control
systems, as well as other items that had not been dealt with in the FAT (Factory
Acceptance Testing).
11.4.2 After installation on board, engines are to undergo shipboard trials as
specified in Table 1.11.2 Scope of shipboard trials for
engines. The scope of the trials may be
expanded depending on the engine application, service experience or other relevant
reasons, and is to be agreed between the LR Surveyor and the Shipyard prior to
testing.
Table 1.11.2 Scope of shipboard trials for
engines
Main engines driving fixed-pitch propeller or
waterjet (see Note 1)
|
Trial condition
|
Duration
|
Note
|
At rated engine speed,
R
|
≥ 4 hours
|
–
|
At engine speed corresponding
to normal continuous power
|
≥ 2 hours
|
–
|
At engine speed corresponding
to 1,032*R
|
30 minutes
|
Where the engine adjustment
permits, see
Vol 2, Pt 2, Ch 1, 11.2 General 11.2.6
|
Approved intermittent overload
(if applicable)
|
-
|
Testing for duration as agreed
with the manufacturer
|
Minimum engine speed to be
determined
|
–
|
–
|
Starting and reversing
manoeuvres
|
–
|
See
Vol 2, Pt 2, Ch 1, 9 Starting arrangements (see
Note 5)
|
Reverse direction of propeller
rotation is to be demonstrated (during the dock or sea trials)
|
10 minutes
|
See also
Vol 2, Pt 2, Ch 1, 11.4 Shipboard trials 11.4.7 and Vol 2, Pt 2, Ch 1, 11.4 Shipboard trials 11.4.8 (see Note 6)
|
Control, monitoring, alarms and
safety systems
|
–
|
Operation to be
demonstrated
|
Where imposed, test to ensure
engine can pass safely through barred speed range
|
–
|
–
|
Main engines driving controllable pitch
propellers
|
Trial
condition
|
Duration
|
Note
|
At 100% power
|
≥ 4 hours
|
See Note 2
|
Approved
intermittent overload (if applicable)
|
–
|
Testing for
duration as agreed with the manufacturer
|
With reverse
pitch suitable for manoeuvring
|
–
|
See
Vol 2, Pt 2, Ch 1, 11.4 Shipboard trials 11.4.7 and Vol 2, Pt 2, Ch 1, 11.4 Shipboard trials 11.4.8 for additional requirements in the case of a
barred speed range
|
Control,
monitoring, alarm and safety systems
|
-
|
Operation to be
demonstrated
|
Engine(s) driving a generator(s) for electrical
propulsion and/or main power supply
|
Trial condition
|
Duration
|
Note
|
100% power (rated electrical
power of generator)
|
60 minutes
|
See Notes 3 and
4
|
At normal continuous propulsion
power
|
≥ 2 hours
|
See Note
|
110% power (rated electrical
power of generator)
|
≥10 minutes
|
See Note 4
|
Starting manoeuvres
|
–
|
See Note 5
|
Control, monitoring, alarm and
safety systems
|
–
|
Operation to be
demonstrated
|
Demonstration of the generator
prime movers’ and governors’ ability to handle load steps
|
-
|
See
Vol 2, Pt 2, Ch 1, 7.3 Auxiliary and emergency engine governors
|
Propulsion engines driving power take off (PTO)
generator
|
Trial
condition
|
Duration
|
Note
|
100% engine power (MCR) at
corresponding speed, R
|
≥ 4 hours
|
–
|
100% propeller branch power at
engine speed, R (unless already covered above)
|
2 hours
|
–
|
100% PTO branch power at
engine speed, R
|
≥ 1 hour
|
-
|
Control, monitoring, alarm and
safety systems
|
-
|
Operation to be demonstrated
|
Engines driving mechanical auxiliaries
|
Trial
condition
|
Duration
|
Note
|
100% engine power (MCR) at
corresponding speed, R
|
≥ 30 minutes
|
-
|
Approved intermittent overload
(if applicable)
|
-
|
Testing for duration as
approved
|
Control, monitoring, alarm and
safety systems
|
-
|
Operation to be demonstrated
|
Note 1. For main
propulsion engines driving reversing gears the tests for main
engines driving fixed-pitch propellers apply as
appropriate.
Note 2. Controllable
pitch propellers are to be tested with various propeller
pitches. The 100% power test is to be conducted at rated engine
speed R with a propeller pitch set of MCR (or to the maximum
achievable power if 100% cannot be reached).
Note 3. The tests
are to be performed at rated speed with a constant governor
setting.
Note 4. Tests are to
be based on the rated electrical powers of the electric
propulsion motors.
Note 5. Starting
manoeuvres are to be carried out in order to verify the capacity
of the starting media. The ability of reversible engines to be
operated in the reverse direction is to be demonstrated. See
Vol 2, Pt 1, Ch 3, 4.8 Astern power.
Note 6. Where R, or
the nominal ahead propeller speed is taken at the normal ship
service speed (or cruising speed). Acceptance of alternative
trial conditions will be subject to consideration by LR.
|
11.4.3 Engines driving electrical generators are to be tested either:
- at 100 per cent electrical power for at least 60 minutes and 110 per cent of
rated electrical power of the generator for at least 10 minutes; or
- During the electrical propulsion plant test which requires testing with 100 per
cent propulsion power (i.e. total electric motor capacity for propulsion) by
distributing the power on as few generators as possible. The duration of this
test is to be sufficient to reach stable operating temperatures of all rotating
machines or for at least 4 hours.
11.4.4 Trials are to include demonstration of engine control, monitoring, alarm
and safety system operation to confirm that they have been provided, installed and
configured as intended and in accordance with the relevant requirements for main,
auxiliary or emergency engines except items already verified during the works
trials.
11.4.5 For electronically controlled engines:
- shipboard tests in accordance with Vol 2, Pt 2, Ch 1, 1.4 Submission requirements 1.4.3; and
- verification of engine configuration, see
Vol 2, Pt 2, Ch 1, 4.3 Control engineering systems 4.3.2 and Vol 2, Pt 2, Ch 1, 1.4 Submission requirements 1.4.3.(a), and that the approved software quality plans, including the
software configuration management process, are to be applied.
11.4.6 The suitability of an engine to burn residual or other special fuels is
to be demonstrated where the machinery installation is arranged to burn such fuels
in service. Dual- or multi-fuel engines are to be tested on all fuels that the
engine is specified to use. Where engines operate on a mix of different fuels, then
this is to be demonstrated. See also
Vol 2, Pt 9, Ch 12, 1.7 Unattended machinery space operation - UMS notation.
11.4.7 For both manual and automatic engine control systems, acceleration and
deceleration through any barred speed range, is to be demonstrated. The transit
times are to be equal or less than the times stated in the approved documentation
and are to be recorded. This also applies when passing through the barred speed
range in reverse rotational direction, especially during the stopping test. The
ship’s draught and speed during all these demonstrations are to be recorded. Where a
controllable pitch propeller is fitted, the pitch is also to be recorded.
11.4.8 The engine is to be checked for stable running (steady fuel index) at
both upper and lower borders of the barred speed range. Steady fuel index means an
oscillation range less than five per cent of the effective stroke (idle to full
index).
|