Section
11 Factory Acceptance Test and Shipboard Trials of Engines
11.1 Safety
11.1.1 Before any test is carried out, all relevant equipment for the safety of attending
personnel is to be made available by the manufacturer/shipyard and is to be
operational. This is to include crankcase explosive conditions protection, overspeed
protection and any other shutdown function.
11.1.2 The overspeed protective device is to be set to a value which is not higher than the
overspeed value that was demonstrated during the type test for that engine. This set
point is to be verified by the Surveyor.
11.2 General
11.2.1 Engines which are to be subjected to trials on the test bed at the
manufacturer's works and under attendance by the Surveyor(s) are to be tested in
accordance with the scope of works trials specified in Pt 10, Ch 1, 11.3 Works trials (factory acceptance test). The scope of the trials is to be agreed between LR and the manufacturer prior to
testing.
11.2.3 Before any official testing the engines are to be run in as prescribed by the engine
manufacturer.
11.2.4 Adequate test bed facilities for loads as required in Table 1.11.1 Scope of works trials for
engines are to be provided. All fluids used for testing
purposes such as fuel, lubrication oil and cooling water are to be suitable for the
purpose intended, e.g. they are to be clean, and if necessary pre-heated to achieve
the recommended operating temperature. This applies to all fluids used temporarily
or repeatedly for testing purposes only.
11.2.5 Survey of the engine is to include:
- Jacketing of high-pressure fuel oil lines including the system used for the
detection of leakage.
- Screening of pipe connections in piping containing flammable liquids.
- Insulation of hot surfaces by taking random temperature readings that are to
be compared with corresponding readings obtained during the type test. This
is to be done while running at the maximum approved rating for the actual
application. Use of contact thermometers may be accepted at the discretion
of the attending Surveyor. If the insulation is modified subsequently to the
Type Approval Test, LR may request more enhanced temperature measurements as
required by the LR’s Type Approval Test Specification No. 4 – Type
Testing of Reciprocating Internal Combustion Engines and Associated
Ancillary Equipment, Section 10.2.7 (Fire Protection
Measures).
These surveys are normally to be made during the works trials, but at the discretion
of LR parts of these surveys may be postponed to the shipboard testing.
11.2.6 Where the type test was not carried out on the complete engine, as
described in the scope of this chapter, integration tests are to be conducted as
part of the works or shipboard trials to confirm satisfactory operation of the
complete engine. This includes satisfactory functioning on all fuel types on which
the engine is to operate. See also
Pt 10, Ch 1, 11.4 Shipboard trials 11.4.6.
11.2.7 For the duration of the acceptance test, no interventions or adjustments
will be made to the machinery under test.
11.3 Works trials (factory acceptance
test)
11.3.1 The purpose of the works trials is to verify design parameters such as power, fire
protection and prevention arrangements, adherence to approved limits (e.g. maximum
pressure) and functionality, and to establish reference values or base lines for later
reference in the operational phase.
11.3.2 During testing the environmental conditions are to be recorded, including ambient air
temperature, ambient air pressure and atmospheric humidity.
11.3.3 For each trial condition the parameters to be recorded include: power and
speed; fuel index (or equivalent reading); maximum combustion pressures; exhaust gas
temperature before turbine and from each cylinder (or from manifold, see Note 5
in Table 1.7.1 Engines for propulsion purposes:
alarms and safeguards slow-downs ); charge air temperature and pressure, and
turbocharger speed (only for category B and C turbochargers).
11.3.4 For all stages of the works trials the pertaining operation values are to be
measured and recorded by the engine manufacturer. All results are to be compiled in an
acceptance protocol to be issued by the engine manufacturer. Where the engine designer
requires through life monitoring of crankshaft deflections, such measurements are also
to be taken before and after works acceptance trials in accordance with the engine
designer’s requirements.
11.3.5 In each case given in Table 1.11.1 Scope of works trials for
engines, all measurements
conducted at the various trial conditions are to be carried out at steady operating
conditions. The readings for MCR, i.e. 100 per cent power (rated maximum continuous
power at corresponding rpm) are to be taken twice at an interval of at least 30 minutes.
For all trial conditions provision should be made for time needed by the Surveyor to
carry out visual inspections.
11.3.6 Calibration records for the instrumentation are, upon request, to be presented to the
attending Surveyor.
Table 1.11.1 Scope of works trials for
engines
Main engines driving propellers and waterjets
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated power) at rated
engine speed, R
|
≥ 60 minutes
|
-
|
110 per cent power at engine speed
corresponding to 1,032*R
|
15 minutes
|
or after having reached steady
conditions, whichever is shorter, see Notes 1and 4
|
Approved intermittent overload (if
applicable)
|
-
|
Testing for duration
to be agreed with the manufacturer
|
90 per cent (of normal continuous power), 75
per cent, 50 per cent and 25 per cent power
|
-
|
Engines speed in accordance
with the nominal propeller curve, sequence to be selected by the
manufacturer
|
Reversing manoeuvres (if applicable)
|
-
|
-
|
Testing of governor
and independent overspeed protective device
|
-
|
See
Pt 10, Ch 1, 7 Control and monitoring of main, auxiliary and emergency engines
|
Shutdown
device
|
-
|
See
Pt 10, Ch 1, 7 Control and monitoring of main, auxiliary and emergency engines
|
Engines driving generators for electric propulsion or driving
generators for auxiliary purposes
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated power) at rated
engine speed, R
|
≥ 60 minutes
|
-
|
110 per cent power
|
15 minutes
|
Or after having reached steady
conditions see Note 2
For auxiliary engines, see Note
1
|
75 per cent, 50 per cent and 25 per cent power
and idle run
|
-
|
See Note 2
|
Start-up tests
|
-
|
-
|
Testing of governor and independent overspeed
protective device
|
-
|
See
Pt 10, Ch 1, 7.3 Auxiliary and emergency engine governors
|
Shutdown device
|
-
|
See
Pt 10, Ch 1, 7.4 Overspeed protective devices
|
Propulsion engines driving power take off (PTO)
generator
|
100 per cent power
(rated power) at rated engine speed, R
|
≥ 60
minutes
|
-
|
110 per cent
power
|
15 minutes
|
Or after having
reached steady conditions, see Note 3
|
Approved
intermittent overload (if applicable)
|
-
|
Testing for
duration to be agreed with the manufacturer
|
90 per cent (or
normal continuous power), 75 per cent, 50 per cent and 25 per cent
power
|
-
|
Engine speed in
accordance with the nominal propeller curve or at constant speed
R, sequence to be selected by the manufacturer
|
Engines driving mechanical auxiliaries
|
Trial condition
|
Duration
|
Note
|
100 per cent power
(rated power) at rated engine speed, R
|
≥ 30
minutes
|
-
|
110 per cent
power
|
15 minutes
|
Or after having
reached steady conditions, see Note 1
|
Approved
intermittent overload (if applicable)
|
-
|
Testing for
duration to be agreed with the manufacturer
|
75 per cent, 50 per
cent and 25 per cent power
|
-
|
Engine speed in
accordance with the nominal power consumption curve, sequence to be
selected by the manufacturer
|
Note
1. After running on the test bed, the
fuel delivery system of main and auxiliary engines is normally to
be so adjusted that overload power cannot be given in service
unless intermittent overload power is approved by LR, in which case
the limit is to be adjusted to that power. The setting of the
restriction is to be made as applicable to the intended fuel. Any
restriction settings, and other changes to the engine’s fuel
injection equipment required for operation on special fuels, are to
be recorded and included by the engine manufacturer.
Note
2. After running on the test bed, the
fuel delivery system of diesel engines driving generators is to be
adjusted so that full power plus a 10 per cent margin for transient
regulation can be given in service after installation on board. The
transient overload capability is required so that the required
transient governing characteristics are achieved also at 100 per
cent loading of the engine, and so that the protection system
utilised in the electric distribution system can be activated
before the engine stalls.
Note
3. After running on the test bed, the
fuel delivery system of propulsion engines also driving power take
off (PTO) generators is to be adjusted so that full power plus a
margin for transient regulation can be given in service after
installation on board. The transient overload capability is
required so that the electrical protection of downstream system
components is activated before the engine stalls. This margin may
be 10 per cent of the engine power but at least 10 per cent of the
PTO power
Note 4. Only required once for each
different engine/turbocharger configuration.
|
11.3.7 Calibration records for the instrumentation are, upon request, to be presented to the
attending Surveyor.
11.3.8 Alternatives to the detailed tests may be agreed between the manufacturer and LR when
the overall scope of tests is found to be equivalent. The scope of the trials may be
expanded depending on the engine application, service experience, or other relevant
reasons.
11.3.10 For electronically controlled engines:
-
Factory acceptance tests in accordance with Pt 10, Ch 1, 1.4 Submission requirements 1.4.2;
- integration tests are to be made to verify that the response of the complete
mechanical, hydraulic and electronic system is as predicted for all intended
operational modes and the tests considered as a system are to be carried out at the
works. If such tests are technically unfeasible at the works, then these tests may be
conducted during sea trial; and
-
verification of engine configuration, see
Pt 10, Ch 1, 4.3 Control engineering systems 4.3.2, and that the approved software quality
plans, including the software configuration management process, are being applied.
11.3.11 Checks
of components to be presented for inspection after the works trials
are left to the discretion of the Surveyor.
11.4 Shipboard trials
11.4.1 The purpose of the shipboard testing is to verify compatibility with power transmission
and driven machinery in the system, safety, control and auxiliary systems necessary for
the engine and integration of engine/shipboard control systems, as well as other items
that had not been dealt with in the FAT (Factory Acceptance Testing).
11.4.2 After installation on board, engines are to undergo shipboard trials as
specified in Table 1.11.2 Scope of shipboard trials for
engines. The scope of the trials may be expanded depending
on the engine application, service experience or other relevant reasons, and is to be
agreed between the LR Surveyor and the Shipyard prior to testing.
Table 1.11.2 Scope of shipboard trials for
engines
Main engines driving fixed-pitch propellers or waterjet (see Note
1)
|
Trial condition
|
Duration
|
Note
|
At rated engine speed,
R
|
≥ 4 hours
|
-
|
At engine speed corresponding to
1,032*R
|
30 minutes
|
Where the engine
adjustment permits, see
Pt 10, Ch 1, 11.2 General 11.2.7
|
Approved intermittent overload (if
applicable)
|
-
|
Testing for duration as
agreed with the manufacturer
|
Minimum engine speed to be
determined
|
-
|
-
|
Starting and reversing
manoeuvres
|
-
|
See
Pt 10, Ch 1, 9 Starting arrangements
and
Pt 10, Ch 1, 13 Air compressors (see
Note 5)
|
Reverse direction of propeller
rotation is to be demonstrated (during the dock or sea trials)
|
10 minutes
|
See also
Pt 10, Ch 1, 11.4 Shipboard trials 11.4.7 and Pt 10, Ch 1, 11.4 Shipboard trials 11.4.8
|
Control, monitoring, alarms and
safety systems
|
-
|
Operation to be
demonstrated
|
Where imposed, test to ensure engine
can pass safely through barred speed range
|
-
|
See
Pt 10, Ch 1, 11.4 Shipboard trials 11.4.7 and Pt 10, Ch 1, 11.4 Shipboard trials 11.4.8
for additional requirements in the case of a barred speed range
|
Main engines driving controllable pitch
propellers
|
Trial
condition
|
Duration
|
Note
|
At 100 per cent power
|
≥ 4 hours
|
See Note
2
|
Approved intermittent overload (if
applicable)
|
-
|
Testing for duration as
agreed with the manufacturer
|
With reverse pitch suitable for
manoeuvring
|
-
|
See
Pt 10, Ch 1, 11.4 Shipboard trials 11.4.7 and Pt 10, Ch 1, 11.4 Shipboard trials 11.4.8
for additional requirements in the case of a barred speed range
|
Control, monitoring, alarm and safety
systems
|
-
|
Operation to be
demonstrated
|
Engine(s) driving generator(s) for electrical propulsion and/or main
power supply
|
Trial condition
|
Duration
|
Note
|
100 per cent power (rated electrical
power of generator)
|
60 minutes
|
See Notes 3 and
4
|
110% power (rated
electrical power of generator)
|
≥ 10
minutes
|
See
Note 4
|
Starting manoeuvres
|
-
|
See Note
5
|
Control, monitoring, alarm and safety
systems
|
-
|
Operation to be
demonstrated
|
Demonstration of the generator prime
movers’ and governors’ ability to handle load steps
|
|
See
Pt 10, Ch 1, 7.3 Auxiliary and emergency engine governors
|
Propulsion engines driving power take off (PTO)
generator
|
Trial
condition
|
Duration
|
Note
|
100 per cent engine power (MCR) at
corresponding speed, R
|
≥ 4 hour
|
-
|
100 per cent propeller branch power at
engine speed, R (unless already covered above)
|
2 hours
|
-
|
100 per cent PTO branch power at
engine speed, R
|
≥ 1 hour
|
-
|
Control, monitoring, alarm and safety
systems
|
-
|
Operation to be
demonstrated
|
Engines driving mechanical auxiliaries
|
Trial
condition
|
Duration
|
Note
|
100 per cent engine power (MCR) at
corresponding speed, R
|
≥ 30 minutes
|
–
|
Approved intermittent overload (if
applicable)
|
-
|
Testing for duration
as approved
|
Control, monitoring, alarm and safety
systems
|
-
|
Operation to be
demonstrated
|
Note
1. For main propulsion engines driving or
reversing gears, the tests for main engines driving fixed-pitch
propellers apply as appropriate.
Note
2. Controllable pitch propellers are to
be tested with various propeller pitches. The 100 per cent power test
is to be conducted at rated engine speed R with a propeller
pitch set at MCR (or to the maximum achievable power if 100 per cent
cannot be reached).
Note
3. The tests to be performed at rated
speed with a constant governor setting.
Note
4. Tests are to be based on the rated
electrical powers of the electric propulsion motors.
Note 5. Starting manoeuvres are to be carried out in order to verify
the capacity of the starting media. The ability of reversible engines to
be operated in the reverse direction is to be demonstrated. See
Pt 9, Ch 1, 4.7 Astern power .
|
11.4.3 Engines driving electrical generators are to be tested either:
-
at 100 per cent electrical power for at least 60 minutes and 110 per cent of
rated electrical power of the generator for at least 10 minutes; or
- During the electrical propulsion plant test which requires testing
with 100 per cent propulsion power (i.e. total electric motor capacity for
propulsion) by distributing the power on as few generators as possible. The
duration of this test is to be sufficient to reach stable operating temperatures
of all rotating machines or for at least 4 hours.
11.4.4 Trials
are to include demonstration of engine control, monitoring, alarm
and safety system operation to confirm that they have been provided,
installed and configured as intended and in accordance with the relevant
requirements for main, auxiliary or emergency engines.
11.4.5 For
electronically controlled engines:
-
On board tests in accordance with the approved schedule, see
also
Pt 10, Ch 1, 1.4 Submission requirements 1.4.2; and
-
verification of engine configuration, see
Pt 10, Ch 1, 4.3 Control engineering systems 4.3.2 and Pt 10, Ch 1, 1.4 Submission requirements 1.4.3, and that the approved software quality plans,
including the software configuration management process, are being applied.
11.4.6 The suitability of an engine to burn residual or other special fuels is to
be demonstrated, where the machinery installation is arranged to burn such fuels in
service. Dual- or multi-fuel engines are to be tested on all fuels that the engine is
specified to use. Where engines operate on a mix of different fuels then this is to be
demonstrated. See also
Pt 16, Ch 1, 7.2 Unattended machinery space operation - UMS notation 7.2.1.
11.4.7 For both manual and automatic engine control systems acceleration and
deceleration through any barred speed range, is to be demonstrated. The transit times
are to be equal or less than the times stated in the approved documentation and are to
be recorded. This also applies when passing through the barred speed range in reverse
rotational direction, especially during the stopping test. The ship’s draft and speed
during all these demonstrations are to be recorded. Where a controllable pitch propeller
is fitted, the pitch is also to be recorded.
11.4.8 The engine is to be checked for stable running (steady fuel index) at both upper and
lower borders of the barred speed range. Steady fuel index means an oscillation range
less than five per cent of the effective stroke (idle to full index).
11.5 Additional Shipboard Trial requirements
11.5.1 At the discretion of the attending Surveyor, the scope of the trials may
be expanded in consideration of special operating conditions, such as towing,
trawling, etc.
|