Section 21 Testing and trials
Clasification Society 2024 - Version 9.40
Clasifications Register Rules and Regulations - Rules and Regulations for the Classification of Special Service Craft, July 2022 - Part 16 Control and Electrical Engineering - Chapter 2 Electrical Engineering - Section 21 Testing and trials

Section 21 Testing and trials

21.1 Testing

21.1.1 Tests in accordance with Pt 16, Ch 2, 21.1 Testing 21.1.2 are to be satisfactorily carried out on all electrical equipment, complete or in sections, at the manufacturer's premises and a test report issued by the manufacturer.

21.1.2 A high voltage at any frequency between 25 and 100Hz is to be applied between:

  1. all current carrying parts connected together and earth;

  2. all current carrying parts of opposite polarity or phase.

For rotating machines the value of test voltage is to be 1000 V plus 2 x rated voltage with a minimum of 2000 V, and for other electrical equipment, it is to be in accordance with Table 2.21.1 Test voltage. Items of equipment included in the assembly for which a test voltage lower than the above is specified may be disconnected during the test and tested separately at the appropriate lower test voltage. The test is to be commenced at a voltage of about one-third the test voltage and is to be increased to full value as rapidly as is consistent with its value being indicated by the measuring instrument. The full test voltage is then to be maintained for one minute, and then reduced to one-third full value before switching off. The assembly is considered to have passed the test if no disruptive discharge occurs.

Table 2.21.1 Test voltage

Rated voltage, Un Test voltage a.c. (r.m.s.), V
Un V
Un ≤ 60 500
60 < Un ≤ 1000 2Un + 1000
1000 < Un ≤ 2500 6500
2500 < Un ≤ 3500 10000
3500 < Un ≤ 7200 20000
7200 < Un ≤ 12000 28000
15000 < Un ≤ 22000 50000
22000 < Un ≤ 33000 70000
33000 < Un ≤ 35000 80000

21.1.3 When it is desired to make additional high voltage tests on equipment which has already passed its tests, the voltage of such additional tests is to be 80 per cent of the test voltage the equipment has already passed.

21.1.4 Immediately after the high voltage test, the insulation resistance is to be measured using a direct current insulation tester, between:

  1. all current carrying parts connected together and earth;

  2. all current carrying parts of different polarity or phase.

The minimum values of test voltage and insulation resistance are given in Table 2.21.3 Test voltage and minimum insulation.

21.1.5 Tests in accordance with the standard with which the equipment complies may be accepted as an alternative to the above.

21.1.6 Tests at the manufacturers’ works and after installation on board are to include such tests necessary to demonstrate the suitability and safety of the lithium battery system for its intended duty and location. As a minimum, the tests listed in Table 2.21.2 Test requirements on lithium battery systems are required.

Table 2.21.2 Test requirements on lithium battery systems

Item Tests Trials
Performance test X  
Sensor failures test X
SOC indication test X X
SOH indication test X X
High voltage test X
Insulation resistance test X
Required alarms and safeguards X X
Communication failure between BMS and external charge control system test X X
Verification of thermal management at maximum achievable load under service conditions during trials   X
Tests of the safety functions in the battery compartment, i.e., fire detection and extinguishing, gas detection, off-gas exhaust/extraction, ventilation etc as applicable to the installation   X

21.2 Trials

21.2.1 Before a new installation, or any alteration or addition to an existing installation, is put into service the applicable trials in Pt 16, Ch 2, 21.2 Trials 21.2.2 are to be carried out. These trials are in addition to any acceptance tests which may have been carried out at the manufacturer's works.

21.2.2 The insulation resistance is to be measured of all circuits and electrical equipment, using a direct current insulation tester, between:

  1. all current carrying parts connected together and earth; and so far as is reasonably practicable,

  2. all current carrying parts of different polarity or phase;

The minimum values of test voltage and insulation resistance are given in Table 2.21.3 Test voltage and minimum insulation. The installation may be subdivided and appliances may be disconnected if initial tests produce results less than these figures.

21.2.3 Tests are to be made to verify the effectiveness of:

  1. earth continuity conductor;

  2. the earthing of non-current carrying exposed metal parts of electrical equipment and cables not exempted by Pt 16, Ch 2, 1.12 Earthing of non-current carrying parts 1.12.2 or Pt 16, Ch 2, 20.7 Earthing 20.7.2;

  3. bonding for the control of static electricity.

Table 2.21.3 Test voltage and minimum insulation

Rated voltage Minimum voltage of the tests, V Minimum insulation resistance, MΩ
Un V
Un ≤ 250 2Un 1
250 < Un ≤ 1000 500 1
1000 < Un ≤ 7200 1000
7200 < Un ≤ 15000 5000
Un > 15000 5000

21.2.4 It is to be demonstrated that the Rules have been complied with in respect of:

  1. satisfactory performance of each electrical propulsion, essential auxiliary or emergency power source including its ancillary services throughout a run at full rated load;

  2. temperature of joint, connections, circuit-breakers and fuses;

  3. the operation of engine governors, synchronising devices, overspeed trips, reverse-current, reverse-power and over-current trips and other safety devices;

  4. voltage regulation of every generator when full rated load is suddenly thrown off and when starting the largest motor connected to the system;

  5. voltage drop at the worst case condition;

  6. harmonic distortion of the voltage waveform. Where harmonic filters are installed the calculation results provided by the system integrator are to be verified by the Surveyor. Simulation of harmonic filter failure during trials is not to exceed the THD limit. See Pt 16, Ch 2, 5.11 Harmonic filtering;

  7. satisfactory parallel operation, and kW and KVA load sharing of all generators capable of being operated in parallel at all loads up to normal working load;
  8. alarm sound pressure levels;
  9. all essential and other important equipment are to be operated under service conditions, though not necessarily at full load or simultaneously, for a sufficient length of time to demonstrate that they are satisfactory; and
  10. satisfactory performance of each electrical propulsion, essential auxiliary or emergency energy store including its ancillary services throughout a run at full rated charging capacity.

21.2.5 Measurements are to be taken as part of the trials specified in Pt 16, Ch 2, 21.2 Trials 21.2.4.(c), Pt 16, Ch 2, 21.2 Trials 21.2.4.(d), Pt 16, Ch 2, 21.2 Trials 21.2.4.(e) and Pt 16, Ch 2, 21.2 Trials 21.2.4.(f) to verify that the installation will provide a quality of power supply in accordance with the values listed in Pt 16, Ch 2, 1.8 Quality of power supplies.

21.2.6 It is to be demonstrated by practical tests that the Rules have been complied with in respect of fire, crew and passenger emergency and craft safety systems.

21.2.7 On completion of the general emergency alarm system and public address system tests, the Surveyor is to be provided with two copies of the test schedule, detailing the measured sound pressure levels. Such schedules are to be signed by the Surveyor and the Builder.


Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is exclusively on the terms and conditions set out in that contract.