Section
21 Testing and trials
21.1 Testing
21.1.1 Tests in accordance with Pt 16, Ch 2, 21.1 Testing 21.1.2 are to be satisfactorily carried out on
all electrical equipment, complete or in sections, at the manufacturer's premises and a
test report issued by the manufacturer.
21.1.2 A high voltage at any frequency between 25 and 100Hz is to be applied
between:
-
all current carrying parts connected together and earth;
-
all current carrying parts of opposite polarity or phase.
For rotating machines the value of test voltage is to be 1000 V plus 2 x
rated voltage with a minimum of 2000 V, and for other electrical equipment, it is to be
in accordance with Table 2.21.1 Test voltage. Items of equipment included in the assembly
for which a test voltage lower than the above is specified may be disconnected during
the test and tested separately at the appropriate lower test voltage. The test is to be
commenced at a voltage of about one-third the test voltage and is to be increased to
full value as rapidly as is consistent with its value being indicated by the measuring
instrument. The full test voltage is then to be maintained for one minute, and then
reduced to one-third full value before switching off. The assembly is considered to have
passed the test if no disruptive discharge occurs.
Table 2.21.1 Test voltage
Rated voltage,
Un
|
Test
voltage a.c. (r.m.s.), V
|
Un V
|
Un ≤ 60
|
500
|
60 <
Un ≤ 1000
|
2Un
+ 1000
|
1000 <
Un ≤ 2500
|
6500
|
2500 <
Un ≤ 3500
|
10000
|
3500 <
Un ≤ 7200
|
20000
|
7200 <
Un ≤ 12000
|
28000
|
15000 < Un ≤
22000
|
50000
|
22000 < Un ≤
33000
|
70000
|
33000 < Un ≤
35000
|
80000
|
21.1.3 When it is desired to make additional high voltage tests on equipment which
has already passed its tests, the voltage of such additional tests is to be 80 per cent
of the test voltage the equipment has already passed.
21.1.4 Immediately after the high voltage test, the insulation resistance is to be
measured using a direct current insulation tester, between:
-
all current carrying parts connected together and earth;
-
all current carrying parts of different polarity or phase.
The minimum values of test voltage and insulation resistance are given in
Table 2.21.3 Test voltage and minimum
insulation.
21.1.5 Tests in accordance with the standard with which the equipment complies may
be accepted as an alternative to the above.
21.1.6 Tests at the manufacturers’ works and after installation on board are to
include such tests necessary to demonstrate the suitability and safety of the lithium
battery system for its intended duty and location. As a minimum, the tests listed in
Table 2.21.2 Test requirements on lithium
battery systems
are required.
Table 2.21.2 Test requirements on lithium
battery systems
Item
|
Tests
|
Trials
|
Performance test
|
X
|
|
Sensor
failures test
|
X
|
|
SOC
indication test
|
X
|
X
|
SOH
indication test
|
X
|
X
|
High
voltage test
|
X
|
|
Insulation resistance test
|
X
|
|
Required alarms and
safeguards
|
X
|
X
|
Communication failure between BMS and external charge control system
test
|
X
|
X
|
Verification of thermal management at maximum achievable load under service
conditions during trials
|
|
X
|
Tests of the safety
functions in the battery compartment, i.e., fire detection and
extinguishing, gas detection, off-gas exhaust/extraction, ventilation etc as
applicable to the installation
|
|
X
|
21.2 Trials
21.2.1 Before
a new installation, or any alteration or addition to an existing installation,
is put into service the applicable trials in Pt 16, Ch 2, 21.2 Trials 21.2.2 are to be carried
out. These trials are in addition to any acceptance tests which may
have been carried out at the manufacturer's works.
21.2.2 The
insulation resistance is to be measured of all circuits and electrical
equipment, using a direct current insulation tester, between:
-
all current carrying
parts connected together and earth; and so far as is reasonably practicable,
-
all current carrying
parts of different polarity or phase;
The minimum values of test voltage and insulation resistance
are given in Table 2.21.3 Test voltage and minimum
insulation.
The installation may be subdivided and appliances may be disconnected
if initial tests produce results less than these figures.
21.2.3 Tests
are to be made to verify the effectiveness of:
-
earth continuity
conductor;
-
the earthing of
non-current carrying exposed metal parts of electrical equipment and
cables not exempted by Pt 16, Ch 2, 1.12 Earthing of non-current carrying parts 1.12.2 or Pt 16, Ch 2, 20.7 Earthing 20.7.2;
-
bonding for the
control of static electricity.
Table 2.21.3 Test voltage and minimum
insulation
Rated voltage
|
Minimum
voltage of the tests, V
|
Minimum
insulation resistance, MΩ
|
Un V
|
Un ≤ 250
|
2Un
|
1
|
250 <
Un ≤ 1000
|
500
|
1
|
1000 <
Un ≤ 7200
|
1000
|
|
7200 <
Un ≤ 15000
|
5000
|
|
Un > 15000
|
5000
|
|
21.2.4 It is
to be demonstrated that the Rules have been complied with in respect
of:
-
satisfactory performance of each electrical propulsion, essential
auxiliary or emergency power source including its ancillary services throughout a
run at full rated load;
-
temperature of
joint, connections, circuit-breakers and fuses;
-
the operation of
engine governors, synchronising devices, overspeed trips, reverse-current,
reverse-power and over-current trips and other safety devices;
-
voltage regulation
of every generator when full rated load is suddenly thrown off and
when starting the largest motor connected to the system;
-
voltage drop at
the worst case condition;
-
harmonic distortion of the voltage waveform. Where harmonic filters
are installed the calculation results provided by the system integrator are to be
verified by the Surveyor. Simulation of harmonic filter failure during trials is
not to exceed the THD limit. See
Pt 16, Ch 2, 5.11 Harmonic filtering;
- satisfactory parallel operation, and kW and KVA load sharing of all generators
capable of being operated in parallel at all loads up to normal working load;
- alarm sound pressure levels;
- all essential and other important equipment are to be operated under
service conditions, though not necessarily at full load or simultaneously, for a
sufficient length of time to demonstrate that they are satisfactory; and
- satisfactory performance of each electrical propulsion, essential auxiliary or
emergency energy store including its ancillary services throughout a run at full
rated charging capacity.
21.2.5 Measurements
are to be taken as part of the trials specified in Pt 16, Ch 2, 21.2 Trials 21.2.4.(c), Pt 16, Ch 2, 21.2 Trials 21.2.4.(d), Pt 16, Ch 2, 21.2 Trials 21.2.4.(e) and Pt 16, Ch 2, 21.2 Trials 21.2.4.(f) to verify
that the installation will provide a quality of power supply in accordance
with the values listed in Pt 16, Ch 2, 1.8 Quality of power supplies.
21.2.6 It is
to be demonstrated by practical tests that the Rules have been complied
with in respect of fire, crew and passenger emergency and craft safety
systems.
21.2.7 On completion
of the general emergency alarm system and public address system tests,
the Surveyor is to be provided with two copies of the test schedule,
detailing the measured sound pressure levels. Such schedules are to
be signed by the Surveyor and the Builder.
|
Copyright 2022 Clasifications Register Group Limited, International Maritime Organization, International Labour Organization or Maritime
and Coastguard Agency. All rights reserved. Clasifications Register Group Limited, its affiliates and subsidiaries and their respective
officers, employees or agents are, individually and collectively, referred to in this clause as 'Clasifications Register'. Clasifications
Register assumes no responsibility and shall not be liable to any person for any loss, damage or expense caused by reliance
on the information or advice in this document or howsoever provided, unless that person has signed a contract with the relevant
Clasifications Register entity for the provision of this information or advice and in that case any responsibility or liability is
exclusively on the terms and conditions set out in that contract.
|
![](LR-FooterLogo.png) |
|