Section
2 Cargo containment
2.1 Functional requirements
2.1.1 Details of the proposed design of cargo containment systems are to be
submitted for consideration, and it is recommended this is done at as early a stage
as possible. For a description of LR’s system of approval, refer to the Marine
Survey Guidance System. See also
Pt 11, Ch 1, 1.4 Alternative arrangements.
2.1.2 The design life of the cargo containment system shall not be less than
the design life of the ship unit.
2.1.3 Cargo containment systems shall be designed with site-specific
environmental loads for the proposed area of operation. The cargo containment system
shall also be designed for all transit conditions as applicable to the operational
philosophy of the unit; this includes delivery voyages and sail-away disconnect
conditions.
2.1.4 Cargo containment systems shall be designed with suitable safety
margins:
- to withstand, in the intact condition, the environmental
conditions anticipated for the cargo containment system’s design life and
the loading conditions appropriate for them, which include loads derived for
the following scenarios: on-site operation, inspection/maintenance,
transit/disconnect and accidental. The most onerous loading conditions are
to be considered.
- that are appropriate for uncertainties in loads, structural
modelling, fatigue, corrosion, thermal effects, material variability, ageing
and construction tolerances.
2.1.5 The cargo containment system structural strength shall be assessed
against failure modes, including but not limited to plastic deformation, buckling,
and fatigue. The specific design conditions that should be considered for the design
of each cargo containment system are given in Pt 11, Ch 4, 6.1 Type A independent tanks to Pt 11, Ch 4, 6.5 Integral tanks. The following three main categories of design
conditions are to be assessed:
-
On-site operation design conditions – The cargo containment system
structure and its structural components shall withstand loads liable to
occur during its construction, testing and anticipated use in service,
without loss of structural integrity. The design shall take into account
proper combinations of the following loads:
- Internal pressure.
- External pressure.
- Dynamic loads due to the motion of
the ship unit.
- Thermal loads.
- Sloshing loads.
- Loads corresponding to deflections
of the ship unit.
- Tank and cargo weight with the
corresponding reaction in way of supports.
- Insulation weight.
- Loads in way of towers and other
attachments.
- Test loads.
The loads are to be calculated at a return period of
100 years.
The relevant acceptance criteria and
allowable stresses are to be in accordance with Pt 11, Ch 4, 6.1 Type A independent tanks 6.1.5,
Pt 11, Ch 4, 6.2 Type B independent tanks 6.2.3,
Pt 11, Ch 4, 6.3 Type C independent tanks 6.3.3,
Pt 11, Ch 4, 6.4 Membrane tanks 6.4.3, Pt 11, Ch 4, 6.5 Integral tanks and Pt 11, Ch 4, 6.4 Membrane tanks 6.4.2 as
appropriate.
-
Fatigue design conditions – The cargo containment system structure
and its structural components shall not fail under accumulated cyclic
loading.
-
Accident design conditions – The cargo containment system shall
provide the indicated response to each of the following accident conditions
(accidental or abnormal events), addressed in this Part:
The relevant acceptance criteria and allowable stresses are to be in
accordance with Pt 11, Ch 4, 6.2 Type B independent tanks 6.2.2, or Pt 11, Ch 4, 6.3 Type C independent tanks 6.3.4, or Pt 11, Ch 4, 6.4 Membrane tanks 6.4.2, or Pt 11, Ch 4, 6.5 Integral tanks 6.5.2 as appropriate.
2.1.6 Measures shall be applied to ensure that scantlings required meet the
structural strength provisions and will be maintained throughout the design life.
Measures include, but are not limited to, material selection, coatings, corrosion
additions, cathodic protection and inerting.
Corrosion allowance need not be required in addition to the thickness
resulting from the structural analysis. However, where there is no environmental
control, such as inerting around the cargo tank, or where the cargo is of a
corrosive nature, LR may require a suitable corrosion allowance.
2.1.7 In areas where excessive corrosion might be expected, a corrosion
addition may be required if means of protection are not installed.
2.1.8 An inspection/survey plan for the cargo containment system shall be
developed and approved at the time of build. The inspection/survey plan shall
identify areas that need inspection during surveys throughout the cargo containment
system’s life and in particular all necessary in-service survey and maintenance that
was assumed when selecting cargo containment system design parameters. Cargo
containment systems shall be designed, constructed and equipped to provide adequate
means of access to areas that need inspection as specified in the inspection/survey
plan. Cargo containment systems, including all associated internal equipment shall
be designed and built to ensure safety during operations, inspection and maintenance
(see
Pt 11, Ch 3, 1.5 Access to spaces in the cargo area).
2.2 Cargo containment safety
principles
2.2.1 The containment systems shall be provided with a full secondary
liquid-tight barrier capable of safely containing all potential leakages through the
primary barrier and, in conjunction with the thermal insulation system, of
preventing lowering of the temperature of the structure of the ship unit to an
unsafe level.
2.2.3 Cargo containment systems for which the probability for structural
failures to develop into a critical state has been determined to be extremely low,
but where the possibility of leakages through the primary barrier cannot be
excluded, shall be equipped with a partial secondary barrier and small leak
protection system capable of safely handling and disposing of the leakages.
The arrangements shall comply with the following requirements:
- Failure developments that can be reliably detected before
reaching a critical state (e.g. by gas detection or inspection) shall have a
sufficiently long development time for remedial actions to be taken.
- Failure developments that cannot be safely detected before
reaching a critical state shall have a predicted development time that is
much longer than the expected lifetime of the tank.
2.2.4 No secondary barrier is required for cargo containment systems, e.g.
Type C independent tanks, where the probability for structural failures and leakages
through the primary barrier is extremely low and can be neglected.
2.2.5 No secondary barrier is required where the cargo temperature at
atmospheric pressure is at or above –10°C.
2.3 Secondary barriers in relation to tank
types
2.3.1 Secondary barriers in relation to the tank types defined in Pt 11, Ch 4, 6.1 Type A independent tanks to Pt 11, Ch 4, 6.6 Semi-membrane tanks shall be provided in accordance with Table 4.2.1 Secondary barriers in
relation to tank.
Table 4.2.1 Secondary barriers in
relation to tank
Cargo
temperature at atmospheric pressure
|
–10°C and
above
|
Below –10°C
down to –55°C
|
Below
–55°C
|
Basic tank
type
|
No
secondary barrier required
|
Hull may
act as secondary barrier
|
Separate
secondary barrier where required
|
Integral
|
|
Tank type not normally allowed, see Note 1
|
Membrane
|
|
Complete secondary barrier
|
Semi-membrane
|
|
Complete secondary barrier see Note 2
|
Independent
|
|
|
Type A
|
|
Complete secondary barrier
|
Type B
|
|
Partial secondary barrier
|
Type C
|
|
No secondary barrier required
|
NOTES
|
1. A complete secondary barrier should normally be
required if cargoes with a temperature at atmospheric pressure
below –10°C are permitted in accordance with Pt 11, Ch 4, 6.5 Integral tanks 6.5.1
|
2. In the case of semi-membrane tanks that comply in
all respects with the requirements applicable to Type B
independent tanks, except for the manner of support, the
Administration may, after special consideration, accept a
partial secondary barrier.
|
2.4 Design of secondary barriers
2.4.1 Where the cargo temperature at atmospheric pressure is not below –55°C,
the hull structure may act as a secondary barrier based on the following:
- the hull material shall be suitable for the cargo temperature at
atmospheric pressure as required by Pt 11, Ch 4, 5.2 Construction processes 5.2.1 (d); and
- the design shall be such that this temperature will not result
in unacceptable hull stresses.
2.4.2 The design of the secondary barrier shall be such that:
- it is capable of containing any envisaged
leakage of liquid cargo for the RD, as specified in Pt 11, Ch 4, 4.3 Design conditions 4.3.3 (f) , unless different project-specific
requirements apply, taking into account the load spectrum referred to in
Pt 11, Ch 4, 4.3 Design conditions. Project-specific requirements are to be submitted for
consideration.
- physical, mechanical, or operational events within the cargo
tank that could cause failure of the primary barrier shall not impair the
due function of the secondary barrier, or vice versa.
- failure of a support or an attachment to the hull structure will
not lead to loss of liquid tightness of both the primary and secondary
barriers.
- it is capable of being periodically checked
for its effectiveness by means acceptable to LR of a visual inspection or a
pressure/vacuum test or other suitable means carried out according to a
documented procedure agreed with LR.
- The methods required in Pt 11, Ch 4, 2.4 Design of secondary barriers 2.4.2.(d) shall be approved by LR and shall include, where
applicable to the test procedure:
- Details on the size of defect acceptable and the
location within the secondary barrier, before its liquid tight
effectiveness is compromised.
- Accuracy and range of values of the proposed method for
detecting defects in Pt 11, Ch 4, 2.4 Design of secondary barriers.
- Scaling factors to be used if full scale model testing
is not undertaken.
- Effects of thermal and mechanical cyclic loading on the
effectiveness of the proposed test.
- The secondary barrier shall fulfil its functional requirements
at a static angle of heel of 30°.
- Proposals for the periodical examination of the secondary
barrier are to be submitted for consideration.
2.5 Partial secondary barriers and primary
barrier small leak protection system
2.5.1 Partial secondary barriers shall be used with a small leak protection
system and meet all the requirements in Pt 11, Ch 4, 2.4 Design of secondary barriers 2.4.2. The small leak protection system shall include means to detect
a leak in the primary barrier, provision such as a spray shield to deflect any
liquid cargo down into the partial secondary barrier, and means to dispose of the
liquid, which may be by natural evaporation.
2.5.2 The capacity of the partial secondary barrier shall be determined, based
on the cargo leakage corresponding to the extent of failure resulting from the load
spectrum referred to in Pt 11, Ch 4, 4.3 Design conditions 4.3.3 (f), after the initial detection of a primary leak. Due account
may be taken of liquid evaporation, rate of leakage, pumping capacity and other
relevant factors.
2.5.3 The required liquid leakage detection may be by means of liquid sensors,
or by an effective use of pressure, temperature or gas detection systems, or any
combination thereof.
2.6 Supporting arrangements
2.6.1 The cargo tanks shall be supported by the hull in a manner that prevents
bodily movement of the tank under the static and dynamic loads defined in Pt 11, Ch 4, 3.2 Permanent loads to Pt 11, Ch 4, 3.5 Accidental loads, where applicable, while allowing contraction and expansion of
the tank under temperature variations and hull deflections without undue stressing
of the tank and the hull.
2.6.2 Tank supporting arrangements are generally to be located in way of the
primary support structure of the tank and the hull of the ship unit. Steel seatings
are to be arranged, where possible, on both the inner bottom and underside of the
cargo tank so as to ensure an effective distribution of the transmitted load and
reactions into the cargo tanks and double bottom structure.
2.6.3 The strength of supporting arrangements is to be verified by direct
calculation.
2.6.4 Anti-flotation arrangements shall be provided for independent tanks and
be capable of withstanding the loads defined in Pt 11, Ch 4, 3.5 Accidental loads 3.5.2 without plastic deformation likely to endanger the hull
structure.
2.6.6 An adequate clearance is to be provided between the anti-flotation
chocks and the hull of the ship unit in all operational conditions.
2.7 Associated structure and equipment
2.7.1 Cargo containment systems are to be designed for the loads imposed by
associated structure and equipment. This includes pump towers, cargo domes, cargo
pumps and piping, stripping pumps and piping, inert gas piping, access hatches,
ladders, piping penetrations, liquid level gauges, independent level alarm gauges,
spray nozzles, and instrumentation systems (such as pressure, temperature and strain
gauges).
2.8 Thermal insulation
2.8.2 In determining the insulation performance, due regard should be paid to
the amount of the acceptable boil-off in association with the liquefaction or
reliquefaction plant on board, gas consumers if present or other temperature control
system.
|